W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-07_Submittal_Register.pdf

PDF 40 KB Posted

Attached to
W50S8X26QA028 HH-60G STATIC DISPLAY CONCRETE PAD
Solicitation number
W50S8X26QA028
Issued by

About this file

This document is a submittal and documentation requirements table for the HH-60 Static Display Foundation construction project (Project Number QMSN262004, Solicitation W50S8X26QA028). The contract is being administered by Contracting Officer Nick Ochs and Contract Specialist Jack Woods, with the Project Manager position currently to be determined.

The table specifies 31 documentation items organized into three primary categories: Contract Administration, Technical/Quality Management, and Closeout/Technical Record. Contract Administration items (Items 1-13, 31) include insurance certification, progress schedules, monthly progress reports, quality control plans, and daily quality control reporting, with submissions required before work commencement, during construction, and at specified milestones. Technical items (Items 14-24) encompass design drawings, calculations, product data, concrete mixture documentation, aircraft support and anchorage details, drainage calculations, grounding and lightning protection evaluations, solar lighting data, and quality-control test reports, with most submissions required before construction of affected work begins. Closeout items (Items 25-30) include warranties, operation and maintenance information, final construction photographs, final calculations, approved submittal compilations, and concrete/compaction test report compilations, all due at project closeout. Additional requirements include verification of dimensions and discrepancies before affected work, security/access information before site access, and survey/layout information before layout-dependent construction. Executive compensation and first-tier subcontract award reporting is required per applicable contract clause timing.

View the file

Other files

File Type Posted
Questions and Answers.pdf PDF
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-02_WD_CA20260018_Mod-8.txt TXT text file
Solicitation Amendment W50S8X26QA0280002 SF 30.pdf PDF
Site Visit sign In sheet.pdf PDF
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-06_Site_Map.pdf PDF
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-04_Fig_B11-9_Grounding.png PNG image
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-01_Weather_Data.pdf PDF
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-03_Fig_B11-6_Mooring_Point.png PNG image
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-05_Fig_B11-11_USAF_Tiedown_Profile.png PNG image
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-02_WD_CA20260018_Mod-7.txt TXT text file
W50S8X26QA028_QMSN262004_CRHP_SF1442_Atch-06_Site_Map.pdf PDF
W50S8X26QA028_QMSN262004_CRHP_SF30_Amendment01.pdf PDF
W50S8X26QA028_QMSN262004_CRHP_SF1442_Confromed_Amendment.pdf PDF
W50S8X26QA026_CRHP_Pad_SF1442_Atch-01_Weather_Data.pdf PDF
W50S8X26QA026_CHRP_Pad_SF1442_Atch-03_Fig_B11-6_Mooring_Point.png PNG image
Solicitation - W50S8X26QA028.pdf PDF
W50S8X26QA026_CHRP_Pad_SF1442_Atch-02_WD_CA20260018_Mod-7.txt TXT text file
W50S8X26QA026_CHRP_Pad_SF1442_Atch-06_Site_Map.pdf PDF
W50S8X26QA026_CHRP_Pad_SF1442_Atch-04_Fig_B11-9_Grounding.png PNG image
W50S8X26QA026_CHRP_Pad_SF1442_Atch-05_Fig_B11-11_USAF_Tiedown_Profile.png PNG image
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number QMSN262004 PM TBD Description HH-60 Static Display Foundation Contracting Officer Nick Ochs Solicitation W50S8X26QA028 Contract Specialist Jack Woods Contract

Item No.

Submittal / Documentation Item

Category Source Purpose / Content Timing

Insurance Certification Contract Administration

Section 01 00 00

Written certification to the KO that required insurance has been obtained; proof of required insurance for contractor and subcontractors

Before start of work / upon request

Progress Schedule

Contract Administration

Section 01 00 00 Practicable/composite construction schedule submitted to the KO; updated progress schedule as work proceeds

Within required time after work commences; updated as required

Monthly Progress Reports

Contract Administration

Section 01 00 00 Percentage complete and related project status reporting, including AF Form 3065 or approved equivalent

Monthly

Schedule of Value / Military Real Property Data Support

Contract Administration

Section 01 00 00 Schedule and progress support reflecting Military Real Property Data requirements

As required with schedule/progress reporting

Military Real Property Data Support - DD1354

Contract Administration

Section 01 00 01 Schedule and progress support reflecting Military Real Property Data requirements

As required with schedule/progress reporting

Pre-Final Inspection Documentation

Contract Administration

Section 01 00 00 Contractor-conducted Pre-Final Inspection and correction of discrepancies prior to Final Inspection

Before Final Inspection

Request for Final Inspection

Contract Administration

Section 01 00 00 Written request to the KO to schedule Final Inspection

No later than 5 working days before desired date, unless otherwise coordinated

Contractor Representative Contact Information

Contract Administration

Section 01 00 00 Contact information for contractor representative(s) during regular working hours

Prior to commencing on-site construction

Asbuilts Closeout / Technical Record

Section 01 00 00 and

SOW

Onsite record of changes and final record/as-built documentation showing completed installation and utility/location information

Maintain during project;

submit at closeout

Verification of Dimensions / Discrepancy Notice

Contract Administration

Section 01 00 00 Field verification of dimensions and notice to the KO of discrepancies before proceeding

Before affected work

Security / Access Information

Contract Administration

Section 01 00 00 Information required for background checks, access processing, and installation/facility access compliance

Before access / as required

Quality Control Plan (QCP)

Contract Administration / Quality Management

Section 01 00 00 Contractor’s proposed QCP and any later changes submitted to KO

After award / before NTP as required; updates before implementation

Daily Contractor Quality Control Report / Adverse Weather Documentation

Contract Administration / Quality Management

Section 01 00 00 Daily CQC reporting, including adverse weather occurrence and impact to scheduled work

Daily after NTP, throughout contract

Survey / Layout Information Technical SOW

Pad geometry, elevations, drainage layout, anchor coordinates, and aircraft orientation control information

Before layout-dependent construction

Design Drawings and Calculations

Technical SOW

Contractor design package for foundation, anchorage, supports, drainage, grounding/electrical, and other engineered features required by the SOW

Before construction of affected work

Product Data and Shop Drawings

Technical SOW Technical data for materials, components, fixtures, and fabricated items incorporated into the work

Before installation of affected products

Concrete Mixture Documentation

Technical SOW Concrete mix information, including JMD, JMF, and supporting technical data

Before concrete placement

Aircraft Support and Anchorage Details

Technical SOW Support configuration, tie-down / mooring anchor details, load path information, and interface with aircraft hard points

Before construction of affected work

Drainage Calculations Technical SOW

Civil calculations supporting grading, runoff management, and drainage performance

Before construction of affected work

Grounding / Lightning Protection Evaluation

Technical SOW Static grounding design, testing approach, and lightning protection evaluation and design, if applicable

Before construction of affected work

Solar Lighting Data Technical SOW Product data, fixture details, controls, autonomy information, mounting/foundation details, and performance characteristics

Before installation of lighting components

Quality-Control Test Reports Technical / Quality Verification

SOW

Field density/compaction results, concrete batch documentation, slump/temperature/air results when applicable, and compressive-strength reports

During construction, as completed

Grounding-Resistance Test Results

Technical / Quality Verification

SOW

Resistance-to-earth and related grounding test results

Before final acceptance / at closeout

Drainage Verification

Technical / Acceptance Support

SOW

Documentation demonstrating completed drainage performance and functional verification

Before final acceptance / at closeout

25 Warranties Closeout SOW Manufacturer warranties and any required contractor warranty documentation

At closeout

Operation and Maintenance Information

Closeout SOW Operation, maintenance, and product care information for solar fixtures and other applicable installed components

At closeout

Final Construction Photographs

Closeout SOW Photographic documentation of completed work

At closeout

Final Calculations Closeout / Technical Record

SOW

Final design calculations, where updated from the approved design package or required to document the completed installation

At closeout, as applicable

Approved Submittal Compilation

Closeout / Administrative Convenience

SOW

Consolidated set of approved technical submittals included with closeout package

At closeout, if required

Concrete and Compaction Test Report Compilation

Closeout / Technical Record

SOW

Final compiled set of concrete and compaction test documentation

At closeout

Executive Compensation / First-Tier Subcontract Award Reporting

Contract Administration

Section 01 00 00 Required reporting for applicable contracts and subcontracts

As required by clause timing

File details come from the government source that posted it. Updated .