This is a Memorandum for Record documenting the minutes of a pre-proposal conference and site visit held on 27 August 2026 for solicitation W50S8U-26-R-A014, HVAC Replacement/Repair Base-wide, issued by the Department of the Air Force Headquarters 138th Fighter Wing in Tulsa, Oklahoma. The site visit was conducted from 1000 to 1230 hours on 27 August 2026 and was led by Mr. Billy Lawrence of 138 Civil Engineering. MSgt Zak McClintock provided an overview of solicitation requirements via PowerPoint presentation, and attendees were permitted to visit work locations.

The memorandum establishes critical procedural requirements for proposal submission and communication. All contractor questions must be submitted in writing via email to 138.FW.MSC@us.af.mil and routed exclusively through the Contracting Office; contractors are expressly prohibited from contacting Design Engineers or Government Engineers directly. Answered questions will be posted to www.SAM.gov, and any amendments to plans or specifications will be issued as official amendments and posted to the same website. Contractors are advised to check www.SAM.gov frequently for all correspondence, Q&As, amendments, and other updates. Follow-on site visits are permitted but must be coordinated through the email address provided. When submitting proposals via email, contractors should request acknowledgement and contact the contracting office if no reply is received, as submissions may not have been received. Government attendees included representatives from the 138th Contracting Office and 138th Civil Engineering.

View the file

Other files for this federal contract opportunity

Other files attached to 138th FW Base Wide Electrical Repairs, newest first.
File Type Posted
FY26-1 Electrical Contract WorkList.pdf PDF
Basewide Electrical RFIs_1Sep26.pdf PDF
Electrical Repairs Combo Amended.pdf PDF
Electrical Repairs Combo Extend Due Date.pdf PDF
Site Visit Sign In_Redacted.pdf PDF
Site Visit Slides Electrical Projects.pptx PPTX presentation
UPD RFI - Electrical Repairs.pdf PDF
RFI - Electrical Repairs.pdf PDF
Electrical Repairs SAM Combo Doc.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 138TH FIGHTER WING

9100 EAST 46TH STREET NORTH

TULSA OKLAHOMA 74115-1000

27 August 2026

MEMORANDUM FOR RECORD

FROM: 138th MSG/MSC

SUBJECT: MINUTES OF PRE-PROPOSAL CONFERENCE AND SITE VISIT,

SOLICITATION W50S8U-26-R-A014, HVAC Replacement/Repair Base-wide

1. The list of contractors attending the meeting is shown on the attached sign-in sheet. The following Government representatives attended the subject meeting:

Name Position

Mr. Frank Friedl 138 Contracting Office

Mrs. Amanda Lonsdale 138 Contracting Office

MSgt Zak McClintock 138 Contracting Office

MSgt Hassan Bakhshandeh 138 Contracting Office

Capt Anthony Turner 138 Civil Engineering

Mr. Billy Lawrence 138 Civil Engineering

Mr. Justin Browning 138 Civil Engineering

2. The Site Visit was held on 27 August 2026, 1000 – 1230 hours.

3. The following items were discussed during the Pre-proposal Conference:

a. MSgt McClintock provided an overview of the solicitation requirements to attendees.

(Power Point presentation attached)

b. MSgt McClintock stressed the importance of questions asked must be submitted in writing to be official

c. Follow-on visits are allowed, but must be coordinated – 138.FW.MSC@us.af.mil

d. Mr. Lawrence led the group to the job site

3. Attendees were allowed to visit work locations.

4. Questions must be submitted in writing via email, especially technical questions to:

138.FW.MSC@us.af.mil DO NOT CONTACT the Design Engineers or the Government

Engineers. All questions must be routed through the Contracting Office. All Contractor questions when answered will be posted to www.SAM.gov If a question arises that will result in a change to the plans or specifications, an official amendment will be issued. All correspondence, questions and answers, amendments etc. will be posted on www.SAM.gov

5. Any amendments that are issued will posted to www.SAM.gov. Contractors are advised to check the website frequently.

mailto:138.FW.MSC@us.af.mil mailto:138.FW.MSC@us.af.mil http://www.sam.gov/ http://www.sam.gov/ http://www.sam.gov/

6. When you email your proposal, if you do not receive an acknowledgement reply, please reach out to the contracting office – 138.FW.MSC@us.af.mil – as we may not have received your submission.

7. The pre-proposal conference and site visit concluded at 1230 hours.

AMANDA J. LONSDALE, CIV, ANG

CONTRACTING SPECIALIST

Attachment:

Power Point Slides

Sign in sheet mailto:138.FW.MSC@us.af.mil

2026-08-27T17:05:02-0500