This document is a Pre-Bid Conference presentation slide deck related to an Invitation for Bid (IFB) for the Renovation of the Communications Server Room at the 179th Cyberspace Wing, Mansfield, Ohio.
The key details are:
- The project is a firm-fixed price construction contract to expand the existing computer server room, replace the computer room air conditioning unit, and replace two air cooled condensing units and associated cooling equipment (NAICS 236220, $45M size standard).
- The IFB is a 100% small business set-aside, with a bid range of $500,000 - $1,000,000.
- The bid opening is scheduled for 16 May 2024 at 1:00 PM EST. Bids must be submitted by the deadline, with no late bids accepted.
- Detailed submission requirements are provided in Sections 00 10 00 and 00 21 00. A bid bond, performance and payment bonds are required.
- All questions must be submitted as Requests for Information (RFIs) to the Contracting Officer, with answers posted on the SAM.gov website. The deadline for submitting RFIs is 6 working days prior to the bid due date.
- General site access and working conditions are outlined, including security requirements and utilities provided.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMM SERVER ROOM
IFB: W50S8R-24-B-0001
PRE-BID/SITE VISIT CONFERENCE
17 April 2024
U N I T E D S T A T E S P R O P E R T Y & F I S C A L O F F I C E R for O H I O Module 4 2008
Before we get started… Subcontractors Presence is not a Government endorsement Conversations Past, present, future Pictures Allowed…Ask before taking Parameters Red-lines
KEY PERSONNEL
Contracting Officer Gordon Strom – 179th CW Contracting Officers Representative Capt Clayton McCarthy – 179th CW/Deputy Base Civil Engineer Other Personnel David Krutsch – 179th CW Communications
COMM Server Room/SCOPE Firm-Fixed Price Construction Project Project No: PBXP 202107 – Renovate Communications Server Room, which is for expanding the existing computer Server (Frame) Room, replacing a computer room air conditioning (CRAC) unit, and replacing two (2) air cooled condensing units and associated DX cooling coils and refrigerant lines in Building 164, Communications Squadron.
INVITATION FOR BID (IFB)
Small business set-aside (100%) NAISC 236220 $45 Million Size Standard $500,000 - $1,000,000 Public Bid Opening 16 May 24 @ 1:00 PM This Bldg. and room Arrive minimum 15 minutes prior to bid closing, to ensure all bid documents are submitted to Contracting Officer no later than bid opening time (if hand-carrying bid).
Late bids will not be accepted.
SUBMISSION REQUIREMENTS
SEE SECTION 00 10 00 NOTES AND SECTION 00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICE TO OFFERORS.
CLIN 0001 is Base Bid. No options or ABI’s.
Note any post-award requirements in Section 01 00 00.
PRICE
As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering price & Responsibility.
CONSTRUCTION WAGE RATES/BONDS
Most current DOL Construction Wage rates will apply Wage determination will be updated 10 days prior to bid opening.
BID BOND:
Required SEE 52.228-1 ***IMPORTANT: ensure bid bond is submitted as specified in Section 00 10 00 Notes, 4.(c).***
Performance and Payment Bond Required SEE 52.228-15
IMPORTANT REMINDERS
IFB Award will be made without discussion
READ ENTIRE SOLICITATION REQUIREMENTS CAREFULLY
Ensure Bid Package is Complete and all signatures are present (sec 00 10 00 note 4) Plus Bid Schedule/CLIN filled out Ensure Section 00 45 00 Reps/Certs are completed Read Section 01 00 00 General Contract Conditions Anticipate Award no later than 30 Sep 24.
SOLICITATION QUESTIONS
Submit ALL RFI’s (requests for information) to the Contracting Officer at the email show below. DO NOT contact AE, 179th Civil Engineering personnel or any other Government employee directly. Doing so will only delay your answer. ALL questions shall come through the Contracting Office. RFI format within solicitation shall be used by contractor for all questions; template sent out with solicitation Email: gordon.strom.1@us.af.mil ***ALL RFI’s need to come from prime contractor submitting bid; please ensure subcontractors are sending you their RFI’s, for you to submit contracting officer***
ANSWERS TO QUESTIONS
All Questions/Requests are answered and distributed on a Non-Attribution Basis and will be posted to Contract Opportunities on SAM.gov website.
Addendums will be issued for RFI’s answered and any applicable documents will be posted to noted website.
Amendments will be issued for any Solicitation changes, and will be posted to noted website.
Check Web Site Regularly And Don’t Forget To Refresh Web Page Submit all questions/RFI’s NO LATER THAN 6th working day prior to bid due date (as of today, that day would be 1:00pm/08 May 24).
Give more time if expected response is likely to lead to impactful changes to solicitation.
HELPFUL WEBSITES
https://sam.gov/ Home will have links to Contract Opportunities, SAM registration and wage determinations.
SS 2011 Module 5
IFB DUE DATE
16 May 24 @ 1:00 PM EST Will only be changed by issuing an Amendment to IFB
General Working Conditions There should not be any unreasonable mitigated access to/from work site. However, note current Security gate/installation access procedures. Clean-up as needed to prevent Foreign Object Debris (FOD) from roadways (including mud clods, etc).
Daily safety briefings by site superintendent.
All vehicles entering the base will be inspected daily.
All on-site workers for any duration shall require a background investigation (Security access form); specific clearance guidance will be provided post-award/pre-construction meeting).
Delivery drivers may require security clearance or front gate pass; however, they shall be coordinated through COR (will cover more in-depth during pre-construction meeting).
General Conditions Electricity and water available will provided in reasonable amounts to facilitate construction. Note specification requirements for use of utilities Fuel for temporary heating - if required, shall be furnished by the contractor.
Primary access to project site shall be through front gate.
END OF PRESENTATION