Solicitation Amendment 1 - W50S8J25QA0170001 SF 30.pdf
PDF 3 MB Posted
- Attached to
- Stratton ANGB - Repair Roof Building 26
- Solicitation number
- W50S8J25QA017
About this file
This document is a Standard Form 30 (SF 30) Amendment of Solicitation/Modification of Contract for the Stratton Air National Guard Base roof repair project. The amendment updates several key aspects of the original solicitation:
-
The Statement of Work (SOW) has been revised to specify that the Building 26 Section A roof membrane manufacturer warranty shall be 30 years, with an installation warranty of 2 years. The amendment also addresses questions from a government-provided site visit on July 1, 2025, clarifying responsibilities for disconnecting and hoisting recovery units and handling split unit condensate lines. Additionally, the Wage Determination NY20250002 has been updated to modification 9, dated 06/20/2025.
-
The contract documents have been updated, with a new Statement of Work dated July 2, 2025, replacing the previous version from June 17, 2025. The amendment provides specific guidance on unit disconnection and removal, giving contractors flexibility in addressing roof replacement around split units. The modification maintains the original solicitation's core requirements while providing additional clarity on technical and logistical aspects of the roof repair project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW Repair Roof Bldg 26 - 2 July 25.docx | DOCX document | |
| B26 Existing Roof As Built.pdf | ||
| Solicitation - W50S8J25QA017.pdf | ||
| SOW Repair Roof Bldg 26 - 17 JUN 25.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of this amendment is to:Block 14 (Description of Amendment/Modification):
1) Update Wage Determination NY20250002 to modification 9, dated 06/20/2025.
2) Revise the Statement of Work (SOW) to state that the Building 26 Section A roof membrane manufacturer warranty shall be 30 years, and the installation warranty shall be 2 years.
3) Answer questions resulting from the Government provided site visit held on 01 July 2025 @ 1000.
Question 1: Whose responsibility is to disconnect and hoist the recovery unit?
Answer 1: Base personnel will disconnect the electricity to the unit. Contractor is responsible of removing /hoisting the unit out.
Question 2: Split units have a copper condensate line attached. Who is responsible of disconnecting the units?
Answer 2: Should contractor decide to temporarily disconnect the unit, contractor is responsible of the labor. In the past similar projects, contractors managed to replace the roof under the units without the need to disconnect them. Contractor has the freedom to decide how they would like to address the replacement of the roof under the split units.
Section 00 01 15 - List of Drawing Sheets
The attachments table has changed from:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
SOW Repair Roof Bldg 26 - 17 JUN 25
Statement of Work 17 Jun 2025 11 Attachment No
B26 Existing Roof As Built
Drawings 21 Jun 1995 Attachment No
To:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
SOW Repair Roof Bldg 26 - 2 July 25
Statement of Work 02 Jul 2025 11 Attachment No
B26 Existing Roof As Built
Drawings 21 Jun 1995 1 Attachment No
The following contract documents were added:
SOW Repair Roof Bldg 26 - 2 July 25
The following contract documents were deleted:
SOW Repair Roof Bldg 26 - 17 JUN 25
W50S8J25QA0170001
Section 00 73 00 - Supplementary Conditions
Miscellaneous text in this section has been modified to:
"General Decision Number: NY20250002 06/20/2025
Superseded General Decision Number: NY20240002
State: New York
Construction Types: Building, Heavy and Highway
Counties: Albany, Columbia, Fulton, Greene, Montgomery, Rensselaer, Saratoga, Schenectady, Schoharie and Washington Counties in New York.
BUILDING CONSTRUCTION PROJECTS (For all counties except COLUMBIA, FULTON, GREENE & MONTGOMERY) (does not include single family homes and apartments up to a including 4 stories), HEAVY
AND HIGHWAY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed|
| | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025 1 02/07/2025 2 02/28/2025 3 03/07/2025 4 03/14/2025 5 05/16/2025 6 05/23/2025 7 06/06/2025 8 06/13/2025 9 06/20/2025
ASBE0040-002 05/01/2024
Rates Fringes
Asbestos/Insulator Worker SCOPE OF WORK: includes application of all insulating materials, protective, coverings, coating and finishing to all types of mechanical systems.....................$ 40.46 26.86
HAZARDOUS MATERIAL HANDLER
Duties limited to preparation wetting;
stripping; removal;
scrapping; vacuuming;
bagging; and disposing of all insulation materials, whether they contain asbestos or not from mechancial systems..........$ 38.40 24.42
BOIL0197-002 01/01/2025
Rates Fringes
BOILERMAKER......................$ 43.34 27.66
BRNY0002-019 07/01/2024
Rates Fringes
BRICKLAYER
BRICKLAYERS, STONE MASONS,
CEMENT MASONS, PLASTERERS,
POINTERS, CAULKERS &
CLEANERS....................$ 36.19 20.48
HEAVY & HIGHWAY
CONSTRUCTION
CEMENT MASONS..............$ 37.23 19.51
MARBLE, TILE & TERRAZZO
FINISHERS...................$ 29.38 19.16
MARBLE, TILE & TERRAZZO
WORKERS.....................$ 34.66 19.58
CARP0279-006 07/01/2024
Rates Fringes
Carpenters:
HEAVY AND HIGHWAY
CONSTRUCTION (COLUMBIA AND
GREENE COUNTIES)
Carpenters, Millwrights, Pile Drivers...............$ 43.50 30.22
CARP0291-005 07/01/2024
Rates Fringes
Carpenters:
SARATOGA COUNTY
BUILDING....................$ 35.64 24.00
WASHINGTON COUNTY
BUILDING....................$ 30.68 23.01
PAID HOLIDAYS: Labor Day, provided the employee has been on the payroll the calender week or any of the holiday week preceding the holiday and works the day after the holiday.
CARP0291-008 07/01/2024
ALBANY, FULTON, MONTGOMERY, RENSSELAER, SCHENECTADY AND
SCHOHARIE COUNTIES
Rates Fringes
Carpenters:
BUILDING CONSTRUCTION
(Excluding Montgomery County)
Carpenters & Soft Floor Layers.....................$ 35.64 24.00 Piledriver.................$ 31.68 20.60
HEAVY & HIGHWAY
CONSTRUCTION
Carpenters.................$ 44.28 24.50
CARP0291-010 07/01/2024
Rates Fringes
Carpenters:
CARPENTERS..................$ 44.28 24.50
DIVER TENDERS...............$ 34.02 21.10
DIVERS (Dry Day)............$ 45.28 24.50
DIVERS......................$ 69.28 24.50
PILEDRIVERS.................$ 33.02 21.10
ELEC0236-001 06/01/2024
ALBANY; COLUMBIA; FULTON; GREENE (that portion North of a line following the south limits of the city of Catskill);
MONTGOMERY; RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE;
WASHINGTON
Rates Fringes
ELECTRICIAN......................$ 48.00 32.09
ELEC0363-004 04/01/2024
GREENE COUNTY (Portion of)
Rates Fringes
ELECTRICIAN......................$ 46.50 3%+39.17+a
FOOTNOTE:
a. Paid Holidays: New Year's Day, President's Day, Memorial Day, Fourth of July, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day
* ELEC1249-003 05/05/2025
Rates Fringes
ELECTRICIAN (LINE
CONSTRUCTION: LIGHTING AND
TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems)
Flagman.....................$ 31.72 7%+27.65 Groundman (Truck Driver)....$ 42.29 7%+27.70 Groundman Truck Driver (tractor trailer unit)......$ 47.57 7%+27.70 Lineman & Technician........$ 52.86 7%+31.90 Mechanic....................$ 42.29 7%+27.70
FOOTNOTE:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.
* ELEC1249-004 05/05/2025
Rates Fringes
ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :
Flagman....................$ 35.34 7%+27.65 Groundman digging machine operator...................$ 55.40 7%+27.90 Groundman truck driver (tractor trailer unit).....$ 49.25 7%+27.70 Groundman Truck driver.....$ 49.25 7%+27.70 Lineman and Technician.....$ 61.56 7%+31.90 Mechanic...................$ 49.25 7%+27.70 Substation:
Cable Splicer..............$ 63.14 7%+29.40 Flagman....................$ 35.34 7%+27.65 Ground man truck driver....$ 49.25 7%+27.70 Groundman digging machine operator...................$ 55.40 7%+27.90 Groundman truck driver (tractor trailer unit).....$ 49.25 7%+27.70 Lineman & Technician.......$ 61.56 7%+31.90 Mechanic...................$ 49.25 7%+27.70 Switching structures;
railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 64.59 7%+38.40 Flagman....................$ 35.34 7%+27.65 Groundman Digging Machine Operator...................$ 55.40 7%+27.90 Groundman Truck Driver (tractor-trailer unit).....$ 49.25 7%+27.70 Groundman Truck Driver.....$ 49.25 7%+27.70 Lineman & Technician.......$ 61.56 7%+31.90 Mechanic...................$ 49.25 7%+27.70
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-007 05/05/2025
COLUMBIA COUNTY
Rates Fringes
ELECTRICIAN (LIGHTING AND
TRAFFIC SIGNAL INCLUDING ANY
AND ALL FIBER OPTIC CABLE
NECESSARY FOR THE TRAFFIC
SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD
WEATHER INFORMATION SYSTEMS)
Flagman.....................$ 32.51 7%+27.65 Groundman Digging Machine Operator....................$ 48.77 7%+27.90 Groundman Truck Driver (Tractor-trailer unit)......$ 43.53 7%+27.70 Groundman Truck Driver......$ 49.25 7%+27.70
Lineman and Technician......$ 54.19 7%+31.90 Mechanic....................$ 43.35 7%+27.70
PAID HOLIDAYS:
a. Memorial Day, New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-008 01/01/2025
Rates Fringes
ELECTRICIAN (Line Construction)
TELEPHONE, CATV
FIBEROPTICS CABLE AND
EQUIPMENT
Cable splicer..............$ 40.81 3%+5.77 Groundman..................$ 20.53 3%+5.77 Installer Repairman- Teledata Lineman/Technician- Equipment Operator.........$ 38.73 3%+5.77 Tree Trimmer................$ 31.45 3%+10.48
a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.
ELEV0035-001 01/01/2025
ALBANY; COLUMBIA (Towns of Claverack, Hillsdale, Ghent, Stockport, Austerlitz, Canaan, New Lebanon, Chatham, Kinderhook, Styvesant and Greenport); FULTON; GREENE (Towns of Durham, Greenville, New Baltimore, Coxcsackie and Athens);
MONTGOMERY, RENSSELAER, SARATOGA, SCHENECTADY, SCHOHARIE AND
WASHINGTON COUNTIES
Rates Fringes
Elevator Constructor.............$ 57.73 38.435+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ELEV0138-004 01/01/2025
COLUMBIA COUNTY (THE TOWNS OF ANCRAM, CLERMONT, COPAKE,
GALLATIN, GERMANTOWN, LIVINGSTON, AND TAGHKANIC); GREEN COUNTY
(THE TOWNS OF HUNTER AND CATSKILL)
Rates Fringes
ELEVATOR MECHANIC................$ 73.07 38.435+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ENGI0158-008 07/01/2024
BUILDING
EXCLUDING MONTGOMERY COUNTY
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP A(1)..................$ 53.11 32.58
GROUP A.....................$ 52.62 32.58
1..........................$ 49.06 30.74 2..........................$ 50.06 30.74
GROUP B.....................$ 51.60 32.58
GROUP C.....................$ 48.70 32.58
Hazardous work - Anytime Operating Engineers are involved with level C or above, $2.50 per hour over regular rate.
FOOTNOTE:
a. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (BUILDING):
GROUP A(1): Crane, hydraulic cranes, tower crane, locomotive crane, piledriver, cableway, derricks, whirlies, dragline, boom truck (over 5 tons)
GROUP A(1): Crane Premiums:
1 over 150'- $1.00 2 over 200'- $2.00
GROUP A: Shovel, All Excavators (including rubber tire full swing), gradalls, power road grader, all CMI equipment, front-end rubber tire loader, tractor-mounted drill (quarry master), mucking machine, concrete central mix plant, concrete pump, Belcrete system, automated asphalt concrete plant and tractor road paver, boom truck (5 tons and under), maintenance engineer, self contained crawler, drill-hydraulic rock drill.
GROUP B: Backhoe, (rubber-tired backhoe/loader combination), bulldozer, pushcat, tractor, traxcavator, scraper, LeTourneau grader, form fine grader, road roller, blacktop roller, blacktop spreader, power brooms, sweepers, trenching machine, Barber Green loader, side booms, hydrohammer, concrete spreader, concrete finishing machine, one drum hoist, power hoisting (single drum), hoist - two drum or more, three drum engine, power hoisting (two drum and over), two drum and swinging engine, three drum swinging engine, hod hoist, A-L frame winches, cord and well drillers (one drum), post hole digger, model CHB Vibro-Tamp or similar machine, batch bin and plant operator, dinkey locomotive, skid steer loader, track excavator 5/8 cu. yd. or smaller
GROUP C: Fork lift, high lift, lull, oiler, fireman and heavy- duty greaser, boilers, and steam generators, pump, vibrator, motor mixer, air compressor, dust collector, welding machine, well point, mechanical heater, generators, temporary light plants, concrete pumps, electric submersible pump 4"" and over, murphy type diesel generator, conveyor, elevators, concrete mixer and belcrete power pack (belcrete system), seeding, and mulching machines, pumps
ENGI0158-026 07/01/2024
HEAVY & HIGHWAY
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 54.90 32.45
GROUP 2.....................$ 53.99 32.45
GROUP 3.....................$ 51.42 32.45
GROUP 4.....................$ 60.90 32.45
GROUP 5.....................$ 59.40 32.45
GROUP 6.....................$ 57.90 32.45
GROUP 7.....................$ 57.01 32.45
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY & HIGHWAY):
GROUP 1: Asphalt Curb Machine, Self Propelled, Slipform, Automated Concrete Spreader (CMI Type), Automatic Fine Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Back Filling Machine, Belt Placer (CMI Type), Blacktop Plant (Automated), Boom truck , Cableway, Caisson Auger, Central Mix Concrete Plant (Automated), Concrete Curb Machine, Self Propelled, Slipform, Concrete Pump, Crane, Cherry Picker, Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane, Directional Drilling Machine, Dredge, Dual Drum Paver, Excavator (All Purpose Hydraulically Operated) (Gradall or Similar), Front End Loader ( 4 cu. yd. and Over), Head Tower (Sauerman or Equal), Hoist (Two or Three Drum), Holland Loader, Maintenance Engineer, Mine Hoist, Mucking Machine or Mole Pavement Breaker(SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P.)
Quad 9, Quarry Master (or equivalent), Scraper, Fireman, Form Tamper, Grout Pump, Gunite Machine, Hammers (Hydraulic self-propelled), Hydra-Spiker, ride-on, Hydraulic Pump (jacking system), Hydro-Blaster (Water), Mulching Machine, Oiler, Parapet Concrete or Pavement, Shovel, Side Boom, Slip Form Paver, Tractor Drawn, BeltType Loader, Truck or Trailer Mounted Log , Chipper (Self Feeder), Tug Operator (Manned Rented Equipment Excluded), Tunnel Shovel
GROUP 2: Asphalt Paver, Backhoe (Tractor Mounted, Rubber Tired), Bituminous Recycler Machine, Bituminous Spreader and Mixer, Blacktop Plant (NonAutomated), Blast or Rotary Drill (Truck or Tractor Mounted), Boring Machine, Cage Hoist, Central Mix Plant (NonAutomated) and All Concrete Batching Plants, Cherry Picker (5 tons capacity and under), Concrete Paver (Over 16S), Crawler Drill, Self-contained, Crusher, Diesel Power Unit, Drill Rigs, Tractor Mounted, Front End Loader (Under 4 cu. yd.), Greaseman/Lubrication Engineer, HiPressure Boiler (15 lbs. and over), Hoist (One Drum), Hydro-Axe, Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive Mixer (for stabilized base selfpropelled), Monorail Machine, Plant Engineer, Profiler (105 H.P. and under), Grinder, Post Hole Digger and Post Driver, Power Broom (towed), Power Heaterman, Power Sweeper, Revinius Widener, Roller (Grade and Fill), Scarifier, ride-on, Shell Winder, Skid steer loader (Bobcat or similar), Span-Saw, ride-on, Steam Cleaner, Pug Mill, Pump Crete Ready Mix Concrete Plant Refrigeration Equipment (for soil stabilization)Road Widener, Roller (all above subgrade), Sea Mule, Self-contained Ride-on Rock Drill, Excluding Air-Track Type Drill, Skidder, Tractor with Dozer and/or Pusher, Trencher.
Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat
GROUP 3: A Frame Winch Hoist on Truck , Articulated Heavy Hauler, Aggregate Plant, Asphalt or Concrete Grooving, Machine (ride on), Ballast Regulator, Ride-on Boiler (used in conjunction with production), Bituminous Heater, self-propelled, Boat (powered), Cement and Bin Operator, Compressors, Dust Collectors, Fork Lift, Generators, Pumps, Welding Machines, Light Plants, Heaters (hands-off equipment), Concrete Pavement Spreader and Finisher, Concrete Paver or Mixer (16S and under), Concrete Saw (self-propelled), Conveyor, Deck Hand, Directional Drill Machine Locator, Drill, (Core), Drill, (Well,) Farm Tractor with accessories, Fine Grade Machine, Tamper, ride-on, Tie Extractor, ride-on, Tie Handler, ride-on, Tie Inserter, ride-on, Tie Spacer, ride-on, Tire Repair, Track Liner, ride-on, Tractor, Tractor (with towed accessories), Vibratory Compactor, Vibro Tamp, Well Point
GROUP 4: Tower Cranes
GROUP 5: Cranes 50 tons and over
GROUP 6: Cranes 49 tons and below
GROUP 7: Master Mechanic
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
IRON0012-011 07/01/2024
ALBANY; COLUMBIA; FULTON (Albin, Bleecker, Broad, Johnstown, Mayfield, Northampton and Perth); GREENE, MONTGOMERY (Amsterdam, Charleston, Florida, Glen, Mohawk and Root);
RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE; and WASHINGTON
COUNTIES:
Rates Fringes
Ironworkers:
Sheeter, Bucker-up..........$ 38.75 25.48 Sheeter.....................$ 38.75 25.48 Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcing, Stone Derrickmen..................$ 38.50 25.48
IRON0440-007 07/01/2024
FULTON (Twps. of Caroga, Ephratah, Oppenheim, Stratford);
MONTGOMERY (Twps of Canajoharie, Minden, Palatine, St.
Johnsville):
Rates Fringes
IRONWORKER
Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcement, and Stone Derrickman..................$ 33.50 32.03
LABO0017-001 07/01/2019
COLUMBIA COUNTY (Twps of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
Rates Fringes
LABORER
COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont, and the City of Hudson) (Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) HEAVY & HIGHWAY GROUP 1:...................$ 38.90 27.15+a GROUP 2:...................$ 43.15 27.15+a GREENE COUNTY (Township of Catskill) HEAVY & HIGHWAY:
GROUP 1:...................$ 34.15 27.15+a GROUP 2:...................$ 38.90 27.15+a GROUP 3:...................$ 43.15 27.15+a GROUP 4:...................$ 48.00 27.15+a
TUNNEL, SHAFT & CAISSON
WORK
GROUP 1....................$ 48.05 29.50+a
For HEAVY & HIGHWAY CLASSIFICATIONS in COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
HEAVY & HIGHWAY CLASSIFICATIONS
GROUP 1: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective equipment and clothing are not required
GROUP 2: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required
For HEAVY & HIGHWAY CLASSIFICATIONS in GREENE COUNTY (Township of Catskill)
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Lincoln's Birthday, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day, provided the employee is an employee of the company prior to the scheduled holiday and reports to work the first day following the holiday unless prevented from doing so for legitimate reasons.
GROUP 1: Flagperson, gateperson
GROUP 2: General laborers, chuck tender, handling and distributing drinking water, distributing all tools and supplies of laborers, nipper, powder carrier, magazine tender, warehouse laborers, concrete man, vibrator man, mason tender, mortar man, spraying, brushing and covering of concrete for curing and preservative purposes, traffic striper, scaffold builder, concrete curb and sidewalk form setter; permanent traffic striping and reflective devices, placing and maintenance of all flares, cones, lights, signs, barricades, traffic patterns, and all temporary reflective type materials for traffic control, custodial work, traffic directors, temporary heat or light tenders, tool room, dewatering pump men, pitman, dumpmen, snow removal and firewatch, asphalt man, joint setter, signal person, pipelayer, pipe lining and relining, wellpoints, conduit and duct layer, wire puller, rip rap and dry stone layer, steel rod carrier, core drill, rock splitter, Hilti gun air or electric, jackhammer, bush hammer, pavement breaker, chipping hammer, wagon drill, air track, jib rig, joy drill, gunite and sand blasting, coal passer and other machine operators, power tool operator, sprayer and nozzle man on mulching and seeding machine, all guard rail and fence, all seeding and sod laying, all landscape work, grade checker, all bridge work, walk behind self-propelled power saw, grinder, groover or similar type machine, walk behind tamper and roller of all types, salvage, stripping, wrecking and dismantling laborer (including barman, cutting torch and burner man), sheeting and shoring coming under laborers jurisdiction, bit grinder, operator of form pin puller and drivers, sandblasting, joint and jet sealer, filling and wiring baskets for gabion walls, permanent sign man, median barrier, sta-wall or similar type product, chain saw operator, railroad track laborer, waterproofer, pre-stressed and pre-cast concrete brick, block and stone pavers, power tools used to perform work usually done by laborers, power buggy and pumpcrete operator, fireproof, plaster and caustic pump, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous materials abatement when protective clothing and equipment is not required, power brush cutter, retention liners, artificial turf, retaining walls, walk behind surface planer, welding related to laborers work, remote controlled equipment normally operated by laborers, all technician work including but not limited to stitching, seaming, heat welding, fireproof sprayer, mortar mixer, concrete finisher, form setter for concrete curbs and flatwork.
Gunite nozzle man, stone cutters, granite stone layer, manhole, catch basin or inlet installing, laser men.
Ground man on milling machine
GROUP 3 Ingersoll Rand heavy duty crawler-master HCMZ, any drill using a 4"" or larger bit, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required, all working foremen including grade, pipe concrete, clearing, blacktop, drill, paving and blaster etc., Hydraulic drill or similar, forklift for masonry only, Blaster and asphalt screedman
GROUP 4: Asbestos, toxic, lead or hazardous material abatement foreman
For TUNNEL, SHAFT & CAISSON WORK CLASSIFICATIONS
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day
GROUP 1: Laborer, Pit and Dumpman, Chuck Tender, Brakeman and Powderman;
Miner and all machine men, Safety Miner, all shaft work, caisson work, drilling, blow pipe, all air tools, tugger, scaling, nipper gunniting from pot to nozzle, bit grinder, signal man (top and bottom), shield driven tunnel, mixed face and soft ground liner plate tunnel in free air
LABO0035-001 07/01/2017
FULTON (TWPS OF CAROGA, EPHRATA, OPPENHEIM, AND STRAFORD);
MONTGOMERY (TWPS OF CANAJOHARIE, MINDEN AND PALATINE, ROOT AND
ST. JOHNSVILLE)
Rates Fringes
Laborers Building Construction Asbestos Removal............$ 24.00 20.64+a Blasters, Form Setters, MotorBuggy Operator (Rider Type)......................$ 23.00 20.64+a Hazardous Waste Removal Hazardous waste removal includes wetting, stripping, removal, scrapping, vaccuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems.........$ 24.00 20.64+a
HEAVY & HIGHWAY:
GROUP 1:...................$ 28.05 23.74+a GROUP 2:...................$ 28.25 23.74+a GROUP 3:...................$ 28.45 23.74+a GROUP 4:...................$ 28.65 23.74+a Laborers....................$ 22.50 20.64+a Pipelayers, Motor Mixers, Motor Buggy Operator (Walk Behind) Power Lift (Walk Behind)...............$ 22.65 20.64+a Wagon Drill Operator........$ 22.90 20.64+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
GROUP 1: Common Laborers, Flagman, Outboard and Hand boats
GROUP 2: Bull Float, Chain Saw, Concrete aggregate bin, Concrete Bootman, Gin Buggy, Hand or Machine Vibrator, Jackhammer, Mason Tender, Mortar Mixer, Pavement Breaker, Handlers of all steel mesh, Small generators for laborer's tools, Installation of bridge drainage, Pipelayers, Vibrator type rollers, Tamper, Drill doctor, Tail or Screw Operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding and sand blasting), Laborers on chain link fence erection, Rock splitter and power unit, Pusher type concrete saw and all other gas, electric, oil, and air tool operators, Wrecking laborers
GROUP 3: All rock or drilling machine operators (except quarry master and similar type), Acetylene torch operators, and Asphalt paver, Powderman
GROUP 4: Blasterers, Form setters, Stone or Granite Curb setters
LABO0157-001 07/01/2023
FULTON (Twps. of Bleeker, Mayfield, Northhampton, Johnstown, Broadalbin and Perth); MONTGOMERY (Twps. of Mohawk, Glen, Charleston, Amsterdam, and Florida); SARATOGA (Twps. of Day, Hadley, Edinburg, Corinth, Moreau, South Glens Falls, Providence, Greenfield, Wilton, Northcumberland, Galway, Milton, Saratoga Springs, Charlton, Ballston, Malta and Clifton Park); SCHENECTADY and SCHOHARIE COUNTIES.
Rates Fringes
LABORER
BUILDING:
GROUP 1....................$ 28.74 20.14+a GROUP 2....................$ 30.09 20.14+a
HEAVY & HIGHWAY:
GROUP 1:...................$ 39.19 26.75
GROUP 2:...................$ 39.39 26.75
GROUP 3:...................$ 39.59 26.75
GROUP 4:...................$ 39.79 26.75
GROUP 5:...................$ 41.69 26.75
LABORER CLASSIFICATIONS
Group 1: Common Laborers
Group 2: Asbestos and Toxic Materials
Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less, excluding demolition work (the complete razing of structures) 75% of the basic wage scale with full benefits will apply
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
LABORER CLASSIFICATIONS
GROUP 1: Common laborers, flagman, outboard & hand boats
GROUP 2: Bull float, chain saw, concrete aggregate bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tamper, drill doctor, tail or screw operator on asphalt paver, water pump operator (1 1/2"") and single diaphragm), nozzle (asphalt, gunnite, seeding, and sand blasting), laborers on chain fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, and air tool operators, wrecking laborers
GROUP 3: All rock drilling machine operators (except quarry master and similar type), acetylene torch operator, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb setters
GROUP 5: Hazardous waste removal
LABO0190-001 07/01/2024
ALBANY; GREEN; RENSSELAER COUNTY, WASHINGTON COUNTY, SARATOGA
COUNTY (Townships of Stillwater, Halfmoon, Saratoga)
Rates Fringes
Laborers:
BUILDING:
GROUP 1....................$ 36.16 26.68
GROUP 2....................$ 37.51 26.68
LABORERS CLASSIFICATIONS
GROUP 1: Common Laborers
GROUP 2: Hazardous waste removal Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less excluding demolition work, (complete razing of structures) will receive 75% of basic wage scale with full fringes will apply
LABO0190-002 07/01/2024
ALBANY; RENSSELAER; COLUMBIA (Twps. of Stuyvesant, Stockport, Kinderhook, New Lebanon, Cannan, Ghent, Chatham, Austerlitz).
GREENE (except Catskill Township). WASHINGTON COUNTY. SARATAGO COUNTY (Townships of Stillwater, Halfmoon Saratoga)
Rates Fringes
Laborers:
HEAVY & HIGHWAY:
GROUP 1:...................$ 41.69 27.65
GROUP 2:...................$ 41.89 27.65
GROUP 3:...................$ 42.09 27.65
GROUP 4:...................$ 42.29 27.65
GROUP 5:...................$ 44.19 27.65
FOOTNOTE:
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
LABORERS CLASSIFICATIONS
GROUP 1: Common laborers, flagmen, outboard and hand boats
GROUP 2: Bull float, chain saw, concrete aggregated bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tampers, drill doctor, Tail or screw operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding, and sand blasting) Laborers on chain link fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, air tool operators, and wrecking laborers
GROUP 3: All rock air drilling machine operators (except quarry master and similar type), acetylene torch operators, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb setters
GROUP 5: Hazardous waste removal
LABO0235-006 05/01/2023
COLUMBIA (Twps. of Greenport, Claverack, Hillsdale, Livingston, Germantown, Taghkanic, Copake, Clermont, Gallatin, Ancram):
Rates Fringes
Laborers:
HEAVY & HIGHWAY
GROUP 1....................$ 36.45 27.80+a GROUP 2....................$ 42.80 27.80+a GROUP 3....................$ 43.90 27.80+a
LABORERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Flagperson; Placing and maintenance of all flares, cones, lights, signs, barricades; traffic control custodial work; traffic directors; temporary heat or light tenders;
tool rooms
GROUP 2: General Laborers, Dumpman, Pitman, Concrete man;
Signal man; Pipelayers; Rip rap; Dry stone layer; Jack hammer; Powderman; Highscalers power buggy operator; Steel rod carrier; Vibratory operator; other machine operator;
wrecking; Vibrator operator-compactor; Gunite and sandblasting; Water pump 2"" or under; Nipper; Chucker;
Asphalt Workers
GROUP 3: Asphalt raker; Asphalt Screedman; Drillers (all);
Laser Beam Operator; Form Setter/Aligners; Blasters
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Presidents Day, Good Friday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, November Election Day, Thanksgiving Day, and Christmas Day
PAIN0009-013 05/01/2025
Rates Fringes
GLAZIER..........................$ 37.25 33.54
PAIN0155-002 05/01/2021
COLUMBIA AND GREENE COUNTIES
Rates Fringes
Painters:
Drywall Finisher............$ 35.94 24.66 Lead Abatement Work.........$ 35.94 24.66
Painter/Paperhanger.........$ 35.94 24.66 Spray Rate..................$ 36.94 24.66
PAIN0201-001 05/01/2025
Rates Fringes
Painters:
Lead Abatement Workers, Structural Steel Zone 1.....................$ 34.50 21.69 Zone 2.....................$ 34.50 21.69 Painters, Drywall Finishers, Spray Zone 1.....................$ 33.50 21.69 Zone 2.....................$ 33.50 21.69
Zone #1 Entire counties of ALBANY, FULTON, MONTGOMERY, RENNSELAER, SCHOHARIE, SCHENECTADY AND SARATOGA
ZONE #2 All of WASHINGTON County
PAIN0806-002 10/01/2024
ALBANY, COLUMBIA, FULTON, GREENE, MONTGOMERY, RENNSELAER,
SCHOHARIE, SCHENECTADY, SARATOGA AND WASHINGTON
Rates Fringes
Painters:
Structural Steel and Bridge.$ 56.25 55.14
PLUM0007-001 05/01/2025
ALBANY; COLUMBIA; FULTON; GREENE; MONTGOMERY; RENSSELAER;
SCHENECTADY; SARATOGA (Towns of Charlton, Clifton Park, Galway, Halfmoon, Milton, Stillwater and Waterford)
Rates Fringes
PLUMBER/PIPEFITTER...............$ 55.26 29.12
PLUM0112-019 05/01/2023
Townships of Canajoharie and Minden
Rates Fringes
PLUMBER (Including Steamfitting) Northern Zone...............$ 31.40 31.70
PLUM0773-002 05/01/2025
SARATOGA (Remainder of County); WASHINGTON COUNTY:
Rates Fringes
PLUMBER/PIPEFITTER...............$ 44.88 33.60
ROOF0203-003 06/01/2023
SCHOHARIE COUNTY:
Rates Fringes
ROOFER...........................$ 30.50 19.84
ROOF0241-001 06/01/2024
Rates Fringes
ROOFER...........................$ 37.05 23.52
SFNY0669-001 01/01/2025
Rates Fringes
SPRINKLER FITTER.................$ 44.73 27.64
SHEE0083-001 06/01/2019
Rates Fringes
Sheet metal worker...............$ 33.73 33.04+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. If any of these holidays fall on a Saturday or Sunday, either the preceding Friday or following Monday will be observed as the holiday.
TEAM0294-003 07/01/2024
Rates Fringes
Truck drivers:
HEAVY & HIGHWAY
GROUP 1....................$ 39.20 30.52+a GROUP 2....................$ 39.26 30.52+a GROUP 3....................$ 39.35 30.52+a GROUP 4....................$ 39.48 30.52+a GROUP 5....................$ 39.64 30.52+a
TRUCK DRIVERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Pick-ups, panel trucks, flatboy material trucks (straight jobs), single axle dump trucks, dumpsters, receivers, greasers, truck tireman
GROUP 2: Tandems, batch trucks, mechanics
GROUP 3: Semi-trailers, low-boy trucks, asphalt distributor trucks, agitator, mixer trucks and dumpcrete type vehicles, truck mechanic, fuel truck
GROUP 4: Specialized earth moving equipment - euclid type or similar off-highway equipment, where not self-loaded, straddle (ross) carrier, self-contained concrete unit
GROUP 5: Off-highway tandem back dump, twin engine equipment and double hitched equipment where not self-loaded
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, provided the employee works the day before and the day after the holiday.
TEAM0294-004 07/01/2024
BUILDING CONSTRUCTION
EXCLUDING MONTGOMERY COUNTY
Rates Fringes
Truck drivers:
GROUP 1.....................$ 32.13 29.80+a GROUP 2.....................$ 32.43 29.80+a
FOOTNOTES:
a. One week vacation after 1 year; 2 weeks vacation after 5 years.
TRUCK DRIVERS BUILDING CLASSIFICATIONS
GROUP 1: Straight, winch, transit mix on job site, road oilers, dump, panel, pick-up, water and fuel trucks on site (including nozzle)
GROUP 2: Euclid or similar equipment, lowboy or lowboy trailers
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
| IDCode: J |
| Page: 1 |
| Pages: 27 |
| AmendNo: 0001 |
| EffDate: 02 JUL 2025 |
| ReqNo: |
| ProjNo: VBDZ252103 |
| IssCode: W50S8J |
| AdmCode: |
| IssuedBy: W7NR USPFO ACTIVITY NYANG 109 |
KO FOR NYANG DO NOT DELETE, 1 AIR NATIONAL GUARD RD
SCOTIA, NY 12302-9572
UNITED STATES
JOSHUA KING, EMAIL: JOSHUA.KING.54@US.AF.MIL TELEPHONE: 518-344-2511
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W50S8J25QA017 |
| SolDate: 17 JUN 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: SEE SCHEDULE |
| ContNameTitle: |
| CoNameTitle: JOSHUA KING |
| ContDate: |
| CODate: 02 JUL 2025 |
File details come from the government source that posted it. Updated .