Attachment 1 - SOW_ dated 30May23.pdf
PDF 381 KB Posted
- Attached to
- Construct Transformer Pad Federal contract opportunity
- Solicitation number
- W50S8J-23-Q-0008
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit QandA.pdf | ||
| Site Visit Minutes_25May23.pdf | ||
| Site Visit Sign-in Sheet.pdf | ||
| A00002 Amendment to Update SOW and Extend RFQ due date.pdf | ||
| W50S8J23Q0008P00001 Amend Eval Criteria_ NAICS_ Site Visit Info.pdf | ||
| Attachment 1 - SOW_ dated 24 Apr 23.pdf | ||
| W50S8J23Q0008 Construct Transformer Pad.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Project Number VBDZ232104
Construct Transformer Pad
DESCRIPTION:
Contractor shall provide all material, labor, equipment, and supervision required to build a concrete pad for a three-phase oil-filled transformer. Pad specifications are provided in the Electric System Bulletin (ESB) 759B July 2010 that can be downloaded from http://www.nationalgridus.com/electricalspecifications. ESB 759B is also included with this Statement of Work (SOW) as Attachment 1. Should there be any conflicting requirements between the ESB 759B and the SOW, Contractor shall bring the conflict to the Contracting Officer Representative (COR) before proceeding with material purchase and/or construction. In ESB 759B, please note that references to the “Company” refer to National Grid.
ESB 759B requires Contractor to coordinate inspections with National Grid and the Base throughout construction.
1. PROJECT SCOPE
1.1. Location
1.1.1. Transformer pad location shall be marked by the base. The pad’s approximate location is shown in the Figure #1. The location of the concrete transformer pad shall be approved by National Grid in advance of the construction.
1.1.2. Should Contractor discover that the pad location is within 10 feet from a buried utility line or 25 feet from exposed utilities, Contractor shall stop the work and notify the Base.
1.1.3. The site location does not have water readily available for the concrete work.
Contractor shall provide water for concrete work.
Figure #1: Approximate Transformer Location
1.2. Excavation
1.2.1. Contractor shall obtain a Dig Permit for the area of operation to ensure that no underground infrastructure or utilities are compromised. Our facility has both an external and an internal dig permit process.
1.2.2. No mechanical excavation shall be permitted near utilities if found.
1.2.3. Excavation work shall be performed in a safe and proper manner with appropriate precautions being taken against all hazards. Excavations shall provide adequate working space and clearances for the work to be performed therein. In no case shall excavation faces be undercut for extended footings.
1.2.4. Excavated material shall be removed from the site.
1.2.5. Contractor shall provide and maintain adequate dewatering equipment to remove and dispose of all surface and groundwater entering excavations, trenches, or other parts of the work. Each excavation shall be kept dry during subgrade preparation and continually thereafter until the concrete is poured.
1.3. Construction
1.3.1. Subgrade surfaces shall be leveled and made clean and free of loose material of any kind when concrete is placed thereon.
1.3.2. Transformer pad is to be oriented to allow the high voltage side to face the pole.
1.3.3. Contractor to install two (2) conduits between pole and high side of transformer.
These conduits are to be trenched and encased concrete per Sections 20.0 through
20.3 of Attachment 1. The conduits shall be at least 4”. Distance shall be field measured by the Contractor prior to bidding, however assumed to be approximately 25 feet. One conduit is a spare.
1.3.4. Contractor to provide two (2) 10’ long buried rigid conduits on the low side of transformer towards the anticipated building location. Conduits shall be 3” in diameter.
1.3.5. Fourteen (14) bollards shall be installed per section 11.0 Transformer Mechanical Protection/Bollards of ESB 759B July 2010. Additional bollard detail is in Section
29.0 Bollard Detail of ESB 759B July 2010. Also, bollards located in front of the transformer pad shall be located a minimum of 10’ from the pad to the bollard.
1.3.6. Transformer pad shall be installed per section 12.0 Transformer pad of ESB 759B July 2010. The transformer pad shall be as the one on page 38, Figure 27.0-2 15kV Transformer Pad 750-1500kVA 44-114 (ref-44-114/UF8B) of ESB 759B July 2010. (Please note there is an error in the ESB and the 2500 kVA should be 1500 kVA) Please be prepared to potentially mortar in open conduits.
1.3.7. The conduit sweeps shall be installed per section 14.0 Transformer Sweep Entry.
Contractor shall be responsible for the installation of expanding foam Hilti Inc.
CF810.
1.3.8. The grounding and bonding shall be installed per section 15.0 Transformer Grounding and Bonding.
1.3.9. Oil containment shall be installed per section 16.0 Oil Containment. Additional, step-by-step, oil containment specifications are also provided as Attachment 2 to this SOW.
1.3.10. Grounding and bonding to be included as part of the SOW with G4 ground clamps as shown in Step 5 of Attachment 2.
1.3.11. The concrete specifications shall comply with section 30.0 Concrete Specifications of ESB 759B July 2010.
1.3.12. The pad shall be leveled.
1.3.13. Backfilling and construction of fills and embankments during freezing weather shall not be done. No backfill, fill, or embankment materials shall be installed on frozen surfaces, nor shall frozen materials, snow, or ice be placed in any backfill, fill, or embankment.
1.4. General
1.4.1. Contractor to provide material submittals as noted for approval of all materials prior to installation.
1.4.2. Material applications shall follow the manufacturer’s recommendations.
Approved pre-cast manufacturers are available on page 53 of Attachment 1.
1.4.3. Contractor shall provide all equipment necessary to perform the work including any lifts, hoists, and rigging.
1.4.4. Contractor shall fill out and sign a form DD1354 to signify the acceptance of the project by ANG and authorize the capitalization of the asset. The Project will not be approved past 95% payment without the DD1354 completed and ready for signature. Draft DD1354 is attached (Fill out the company information and the line cost per building. Line cost must add up to the project cost).
1.4.5. Contractor shall submit a Detailed Work Plan including work sequence, material lead times, and weather-related delays.
1.4.6. Contractor to coordinate timing of project with the COR and National Grid’s schedule.
1.4.7. Special National Grid inspections will be required during construction to evaluate conduit, ground grid, and other aspects as required.
2. CONTRACTOR REQUIREMENTS
2.1. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
2.2. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
2.3. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through MyLearning by completing the Force Protection CBT. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.
2.4. Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 90 days of employees’ initial assignment to the contract and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) and refresher training (Protecting Sensitive Information) are both available on the MyLearning website. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.
2.5. The use and possession of controlled substances to include marijuana (medical or recreational use) on the installation is in violation of Title 10 US Code 912a. Art 112a.
Contractors are notified this policy is strictly enforced and violators will be denied entry.
Personnel caught on the installation can be prosecuted.
2.6. The Contractor shall provide all personnel and the necessary equipment to establish an adequate and safe work zone. OSHA is applicable at the site and inspectors appear unexpectedly.
2.7. Contractor is responsible for site cleanliness and shall remove any waste or debris after the work is complete. All materials shall be secured to prevent loose objects from blowing and hindering flying operations in any manner.
2.8. The Contractor shall recycle to the greatest extent possible and turn in weigh slips to 109 Environmental Management Office for construction debris.
2.9. The Contractor shall bring any unforeseen project conditions to the attention of the COR immediately. Unexpected or differing site conditions, which may alter the scope of work, shall be approved by the contracting officer (KO) prior to such work being performed.
2.10. The Contractor must get approval from the COR prior to any utility shutdowns.
(do not have the contractor contact production control directly)
2.11. The Contractor shall notify the COR prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take a receipt, shall not be accepted and turned away.
2.12. Contractor shall repair or replace in kind any property that is damaged.
2.13. Contractor hours are 0700-1530 Monday thru Friday, excluding Government holidays.
3. PROPOSED PROJECT SCHEDULE
The Project shall begin 14 days after the Notice to Proceed is issued. The project shall be completed within 90 days following the Notice to Proceed or agreed start date.