PWS Range Demo_16 Feb 21.pdf

PDF 541 KB Posted

Attached to
Demolish Old Firing Range - Scotia, NY
Solicitation number
W50S8J21Q0003
Issued by

View the file

Other files

File Type Posted
Site Visit Minutes_16Feb21.pdf PDF
109AW Contractor Envr Requirements.pdf PDF
Site Visit Sign-in_16Feb21.pdf PDF
Site Visit QandA.pdf PDF
21-Q-0003 Amendment 01.pdf PDF
PWS_SOW Range Demo.pdf PDF
RFQ - W50S8J-20-Q-0003.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

Project Number VBDZ212101

Demo Range B54

DESCRIPTION:

The Contractor shall provide all construction services and materials to demolish Building 54 and the covered firing positions. Bldg 54 is approximately 2,240sf and is a wood framed building placed on a concrete slab. There are 20 firing positions that are enclosed by a wood structure supported by concrete columns. The semi-structure surrounding the firing positions is approximately 1,500sf.

1. DEMOLITION

a. All building structure will be demolished, removed and properly disposed from the site.

b. The baffles on the range will remain in place. The Contractor is not responsible for repairing the baffles if they collapse after removal of Bldg 54. The boundary for removal shall be the metal straps that are connected to the baffle structure.

c. The concrete slab and concrete piers will be demolished and removed

d. The septic system that services Bldg 54 will be completely demolished and removed to include the underground tank. There is no leach field. The septic tank has a 3000gal capacity and will need to be pumped empty by the Contractor prior to demolition.

e. Telephone poles, flag pole and stormwater drains are to remain in place.

f. Only the side of the chain link fence that connects to Bldg 54 (approximately 165ft) will be removed. Fence poles will be removed from the ground along with the concrete anchors. The remaining holes will be backfilled with topsoil by the Contractor, it is not necessary to re-seed after soil backfill.

g. The R-22 refrigerant in the HVAC equipment will be recovered properly and amounts reported to 109CES. Personnel from 109CES will provide the refrigerant recovery sheet.

h. The building has a connection to a nearby water well. This is a dug well that is approximately 30 feet deep. The pump and associated piping is to be removed and disposed of. The bollards that surround the well will also be demolished and removed.

The well is to be decommissioned according to the attached NYS Department of Health Fact Sheet for a dug well.

i. The facility is currently closed due to an animal infestation. The Contractor will need to assess the air quality to determine if PPE is required during demolition.

j. There will not be a bathroom within a mile of the work area, Contractor will need to provide portable restroom facilities for the duration of the job.

k. There will be convenience outlets in the fire trainer which is adjacent to the work area, the Contractor can utilized the outlets if needed for power tools or charging batteries.

l. The facility was constructed in 1999 by base personnel, there were no asbestos containing materials used in construction.

2. SITE IMPROVEMENTS

a. The holes created by the removal of the septic tank, concrete slab and fence posts will be backfilled with soil and compacted to match the existing grade by the Contractor. Fill material is to be approved by Base Civil Engineering office.

3. CONTRACTOR REQUIREMENTS

a. The Contractor will notify DigSafe and have a signed form from CES prior to any excavation.

b. The Contractor is responsible for site cleanliness.

c. AT Level I Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable.

Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through ADLS by completing the Force Protection CBT. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.

d. Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 90 days of employees’ initial assignment to the contract and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) and refresher training (Protecting Sensitive Information) are both available on the ADLS website. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.

e. The use and possession of controlled substances to include marijuana (medical or recreational use) on the installation is in violation of Title 10 US Code 912a. Art 112a.

Contractors are notified this policy is strictly enforced and violators will be denied entry. Personnel caught on the installation can be prosecuted.

f. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

g. The Contractor shall provide all personnel and necessary equipment to establish an adequate and safe work zone.

h. The Contractor will recycle to the greatest extent possible and turn in weight slips to 109CEE for construction debris.

i. The Contractor will conform to the 109th CEE Environmental requirements

4. SITE PHOTOS

Septic tank to be removed

Bldg 54

Single side of fence to be removed

Firing position enclosure

Baffles to remain

PROPOSED PROJECT SCHEDULE

The project will begin 14 days following the Notice to Proceed. The project shall be completed within 30 days following the notice to proceed. Notice to Proceed will be issued on or around April 1, 2021.