Questions and Answers Document 1.pdf
PDF 98 KB Posted
- Attached to
- Fire Inspection and Fire Extinguishers
- Solicitation number
- W50S8G20Q0006
- Issued by
-
Department of the Army National Guard
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Document 1 W50S8G‐20‐Q‐0006
19 August 2020
Q1. How many fusible links on each system / hood?
A1. The personnel at the 150 Civil Engineering Squadron are not expertise in this field. It is highly recommended that any contractor interested in submitting a quote for this requirement attend the site visit to verify the type of hood installed in each building.
Q2. What are the sizes, type and quantity of fire extinguishers to be inspected? C02, ABC , K Class…..?
A2. The following types and sizes are to be replaced not inspected: It is the contractor’s responsibility to verify the types of fire extinguishers currently in place.
Quantity Type Model or Similar
168 ABC AMEREX B456
2 Restaurant AMEREX B262
1 D AMEREX B570
The original solicitation and the original Performance Work Statement state 140 fire extinguishers and
11 hoods. An amendment will be issued to correct the number of fire extinguishers, 171, and hoods, 10, on both the solicitation and Performance Work Statement.
Q3. What is the typical time hood inspections can begin?
A3. Begin time can be as early as 7:30 AM
‐‐ End Questions and Answers Document 1 –
File details come from the government source that posted it. Updated .