F9E7CE3119AW44

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1- Q&A for 12MAY22 2- update Wage Determination 10 days prior to bid opening

1. CONTRACT ID CODE PAGE OF PAGES

J 1 17

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 12-May-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S8E23B0001

X 9B. DATED (SEE ITEM 11)

18-Apr-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-May-2023

CODE

USPFO NY PURCHASING & CONTRACTING

330 OLD NISKAYUNA ROAD

LATHAM NY 12110-2224

W912PQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S8E23B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

NONE.

Q&A for 12MAY2023:

Q1) Are the Contractor Crossing Guards required to man the posts shown on the phasing drawings for the entirety of the work shift even when contractor equipment isn’t traversing the property?

A1) Crossing guards are required through working hours. Where there is less need for a guard can be worked through in weekly construction meetings and pre-pave meetings. Equally important is having site control personnel in touch with airfield operations and the maintenance operations cell via radio contact. After hours the lighted low profile barriers from the drawings/specifications will suffice for control of the worksite.

Q2) In regards to the Is the rainwater cleanout, are the risers to be 8” ductile iron, or 6” PVC? Is the cleanout casting to be a cast iron casting or 8” PVC plug? Also, please provide what schedule pipe is to be used for the risers.

A2) The cleanout to be cast-iron soil pipe and fittings meeting ASTM A74.

Q3) In regards to the Is the rainwater cleanout, are the risers to be 8” ductile iron, or 6” PVC? Is the cleanout casting to be a cast iron casting or 8” PVC plug? Also, please provide what schedule pipe is to be used for the risers.

A3) The cleanout to be cast-iron soil pipe and fittings meeting ASTM A74.

Q4) We are requesting a bid date extension of 30 days.

A4) The bid request extension will not be granted at this time.

The following RFIs have been submitted for answers:

Q5) Drawing C-501 (WKVB142112) shows the doweled contraction joints and concrete pavement joints. However the callouts “A” and “D” are not called out anywhere on drawing C-110. Please provide which joints are contraction joints and which are expansion joints. (Received 11MAY)

Q6) The plans & specification SECTION 32 11 33 call for a CEMENT STABILIZED BASE COURSE to be installed at various locations throughout the project. We have researched this item and have been unable to locate any suppliers, subcontractors, or quality control firms that are familiar with this application. As this type of work item has not been used in the Long Island Region, we request an alternative be introduced. (Received 11MAY)

Q7) Are there any soil testing results which would illustrate existing soil classification and characteristics?

Q8) Please provide the length of the 8”x8” downspouts and/or the height of the buildings they are connected to.

Any details of how the downspouts attached to the building would also be appreciated. (Received 10MAY)

Q9) The specifications and details call out a mix-in-place cement stabilized basecourse to be placed at the HH-60 apron, C-130 apron, and inactive apron repairs. We have reached out to multiple contractors as well as testing and design facilities in this regard. They have advised us that the proposed spec may not be a viable option due to the subbase being poorly graded sand and silt. Also, with limited space for concrete replacement at the inactive apron, it will create an issue for proper mixing of the subbase. That being said we would like to propose an alternate subbase.

On previous projects at Gabreski ANG when reconstructing concrete pavement repairs, they have specified the use of a subbase consisting of crush rock base course. Please see the specs below from Project No. WKVB082010 Repair POD Ramp January 2014. Please advise. (Received Monday 08MAY)

RFIs 5-9 will be answered in Amendment 04.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

WAGE DETERMINATION

"General Decision Number: NY20230012 04/14/2023

Superseded General Decision Number: NY20220012

State: New York

Construction Types: Building, Heavy, Highway and Residential

Counties: Nassau and Suffolk Counties in New York.

BUILDING CONSTRUCTION PROJECTS, RESIDENTIAL CONSTRUCTION

PROJECTS (including single family homes and apartments up to and including 4 stories), HEAVY CONSTRUCTION PROJECTS, HIGHWAY

CONSTRUCTION PROJECTS

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the |

|2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay |

|option is exercised) on or | all covered workers at | |after January 30, 2022: | least $16.20 per hour (or |

| | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours |

| | spent performing on the | | | contract in 2023. |

|If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the |

|January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least |

|30, 2022: | $12.15 per hour (or the | | | applicable wage rate listed| | | on this wage determination,|

| | if it is higher) for all | | | hours spent performing on |

| | that contract in 2023. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the

Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2023 1 01/13/2023 2 02/24/2023 3 04/07/2023 4 04/14/2023

ASBE0012-001 06/01/2022

Rates Fringes

Asbestos Workers/Insulator

Includes application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems.....................$ 70.01 35.16

HAZARDOUS MATERIAL HANDLER.......$ 40.50 15.95

BOIL0005-001 01/01/2021

BOILERMAKER......................$ 63.38 33%+47.22+a

FOOTNOTE:

a. PAID HOLIDAYS: New Year's Day, Thanksgiving Day, Memorial

Day, Independence Day, Labor Day and Good Friday, Friday after Thanksgiving, Christmas Eve Day and New Year's Eve

BRNY0001-001 07/01/2022

BRICKLAYER.......................$ 65.53 31.60

MASON - STONE....................$ 69.72 38.67

CARP0290-001 07/01/2021

Carpenters:

Building

Nassau County (Portion of county that lies west of

Seaford Creek and south of the Southern State

Parkway)...................$ 52.50 46.28 Nassau County (Remainder of County) and Suffolk County.....................$ 50.16 33.48

Heavy & Highway.............$ 50.16 33.48 Residential.................$ 32.63 21.83

CARP0740-001 07/01/2022

MILLWRIGHT.......................$ 57.80 55.96

CARP1556-008 07/01/2022

DIVERS TENDERS..............$ 52.57 53.56

DIVERS......................$ 73.03 53.56

DOCKBUILDERS................$ 58.16 53.56

PILEDRIVERMAN...............$ 58.16 53.56

CARP1556-011 07/01/2022

TIMBERMEN...................$ 53.05 53.94

CARP2287-003 07/01/2022

CARPENTER

Soft Floor Layers...........$ 55.05 47.83

ELEC0025-001 10/29/2022

ELECTRICIAN......................$ 57.50 17%+31.95

* ELEC0025-002 03/25/2023

Electricians:

Maintenance Unit............$ 46.79 14%+22.63 Telephone Unit..............$ 39.68 17.50%+21.39

Wiring for single or multiple family dwellings and apartments up to and including 3 stories.........$ 37.25 13%+18.92

ELEC1049-002 04/03/2022

Line Construction:

Substation and Switching structures pipe type cable installation and maintenance jobs or projects; Railroad electrical distribution/ transmission systems maintenance (when work is not performed by railroad employees) Overhead and

Underground transmission/distribution line work. Fiber optic, telephone cable and equipment;

Groundman..................$ 37.92 26.49 Heavy Equipment Operator...$ 50.56 30.51 Lineman & Cable Splicer....$ 63.20 34.52

Material Man...............$ 54.98 31.91

ELEV0001-002 03/17/2022

ELEVATOR MECHANIC

Elevator Constructor........$ 75.14 47.446+a+b

Modernization and Repair....$ 59.09 45.564+a+b

a. PAID HOLIDAYS: New Year's Day, Good Friday, President's Day, Memorial Day, Independence Day, Labor Day, Columbus

Day, Veteran's Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.

b. PAID VACATION: An employee who has worked less than 5 years shall recieve vacation pay credit on the basis of 4% of his hourly rate for all hours worked; an employee who has worked 5 to 15 years shall receive vacation pay credit on the basis of 6% of his hourly rate for all hours worked;

an employee who has worked 15 or more years shall receive vacation pay credit on the basis of 8% of his hourly rate for all hours worked.

ENGI0138-001 06/01/2022

BUILDING CONSTRUCTION

Power equipment operators:

GROUP 1.....................$ 72.61 38.80+a GROUP 2.....................$ 68.95 38.80+a GROUP 3.....................$ 66.53 38.80+a GROUP 4.....................$ 50.70 38.80+a GROUP 5.....................$ 48.55 38.80+a

NOTES:

Hazmat premiums:

Level A 3.50 Level B 2.50 Level C 1.50 Level D 1.00

Oiler on truck cranes with boom length of 100 ft. or more

.25

a. Paid Holidays: New Year's Day, Lincoln's Birthday, Washington's Birthday or President's Day (in lieu of

Lincoln's or Washington's Birthday), Good Friday, Memorial Day, Indpendence Day, Labor Day, Veteran's Day, Thanksgiving Day, Christmas Day or days celebrated as such.

Any holiday that falls on a Saturday will be celebrated on

Friday.

POWER EQUIPMENT OPERATOR CASSIFICATIONS

GROUP 1: Asphalt spreader, backhoe crawler capacity over cater- piller 225 and lomatsu 300, Boiler (thermoplastic), Cherry picker, over 50 tons, CMI or maxim spreader, concrete pump (with oiler), crane (crawler truck), crane

(on barge), crane (stone setting), crane (structural steel), crane (with clam shell), derrick, dragline, dredge, gradall, grader, hoist (3 drum), loading machine (bucket) cap of 10 yds or over micro-trap, with compressor (negative air machine), milling machine, large pile driver, power winch, Stone setting/structural steel, power winch (truck mounted/stone steel) powerhouse, road paver scoop, carry-all, scraper in tandem shovel, sideboom tractor, sideboom tractor (used in tank work), stone spreader (self propelled tank work), zamboni (ice machine)

GROUP 2: Backhoe, boom truck, bulldozer, cherypicker, conveyor (multi), dinky locomotive, forklift, hoist, 2 drum, loading machine, loading machine (front end) mechanical compactors, (machine drawn), mulch machine (machine-fed), mechanic, power winch, other than stone/structural steel, power winch (truck mounted other than stone steel) pump (hydraulic, with boring machine), roller, (asphalt), scoop (carry-all scraper), tower crane (maintenance man), trenching machine

GROUP 3: Comrpessor (structural steel), Compressor (2 or more in battery), concrete finishing mchine, concrete spreader, conveyor, curb machine (asphalt or concrete), curing machine, fireman, hoist (1 drum), micro-trap, (self contained, negative air machine), pump (4 inches or over), pump (hydraulic), pump (jet), pump (sumbersible), pump

(well point), pulvi-mixer, ridge cutter, roller (dirt), striping machine, vac-all, welding and burning, welding machine (pile work), welding machine (structural steel)

GROUP 4: Compressor, compressor (on crane), compressor (pile work), compressor (stone setting), concrete breaker, concrete saw or cutter, forklift (walk behind, power operated), generator-pile work, generator, hydra hammer, mechanical compactors (hand operated), oiler (truck crane), pin puller, portable heaters, powerbroom, power buggies, pump (double action diaphgrgm), pump (gypsum), trench machine (hand), welding machine

GROUP 5: Batching plant (on site of job), generator (small), mixer (with skip), mixer (2 small with or without skip), mixer (2 bag or over, with or without skip), mulch machine, oiler, pump (centrifugal, up to 3 inches), root cutter, stump chipper, tower crane (oiler), tractor (caterpillar or wheel vibrator)

ENGI0138-002 06/01/2022

HEAVY & HIGHWAY

Power equipment operators:

GROUP 1.....................$ 76.52 39.05+a GROUP 2.....................$ 71.60 39.05+a GROUP 3.....................$ 69.09 39.05+a GROUP 4.....................$ 52.88 39.05+a GROUP 5.....................$ 50.68 39.05+a GROUP 6.....................$ 39.30 12.50+a

NOTES:

Hazmat premiums:

Level A 3.50 Level B 2.50 Level C 1.50 Level D 1.00

Truck and Crawler Cranes long boom premiums:

boom lengths (including jib) 100-149 ft 1.00 boom lenghts (including jib) 150-249 ft 1.50 boom lenghts (including jib) 250-349 ft 2.00 boom lengths (including jib) 350 ft 3.00

Cranes using clamshell buckets .25 Front end loader 10 yds and above .25

Oiler on truck cranes with boom length of 100 ft. or more .25

a. Paid Holidays: New Years Day, Lincoln's Birthday, Washington's Birthday or Presidents Day (in lieu of Lincoln's or Washington's Birthday, Good Friday, Memorial

Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, Christmas Day or days celebrated as such. Any holiday that falls on Saturday will be celebrated on Friday.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt spreader, backhoe crawler (capacity over caterpiller 225 and komatsu 300), boiler (thermoplastic), boring machine (post hole), cgherry picker (over 50 ton), CMI or maxim spreader, concrete pump, with oiler, crane

(crawler truck), crane (on barge), crane (stone setting) crane (structural steel), crane (with clam shell), derrick, dragline, dredge, gradall, grader, hoist (3 drums), loading machine (bucket) capacity of 10 yards or over, micro-trap (with compressor-negative air machine), milling machine (large), piledriver, power winch (stone setting structural steel), power winch (truck mounted/stone steel), power-house, road paver, scoop, carry all (scraper in tandem), shovel, sideboom tractor, sideboom tractor (used in tank work), stone spreader (self-propelled), tank work, tower crane

GROUP 2: Bulldozer, Backhoe, Boom Truck, Boring machine/augur, Cherrypicker, Conveyor (multi), Dinky

Locomotive, Forklift, Hoist (2 drum), Loading Machine, Loading Machine (front end), Mechanical Compactor (machine drawn), Mechanic, Mulch Machine (machine- fed), Power Winch (other than stone/structural steel), Power Winch (truck mounted/other than stone steel), Pump Hydraulic (with boring machine), Roller (asphalt), Scoop (carry-all, scraper), Tower Crane (maintenance man), Trenching Machine, Vermeer Cutter, Work Boat

GROUP 3: Curb Machine (asphalt or concrete), Maintenance Engineer (small equipment), Maintenance engineer (well-point) Mechanic (fieldman), Micro-Trap (self contained, negative air machine), Milling Machine (small), Pulvi-mixer, Pump (4 inches or over), Pump Hydraulic, Pump

Jet, Pump Submersible, Pump (well point), Roller Dirt, Vac-All, Welding and burning, Compressor (structural steel), Compressor (2 or more battery), Concrete Finishing Machine, Concrete Spreader, Conveyor, Curing Machine, Fireman, Hoist (one drum), Ridge Cutter, Striping Machine, Welding Machine (pile work), Welding Machine (structural

Steel).

GROUP 4: Compressor, Compressor on crane, Compressor (pile work), Compressor (stone setting), Concrete Breaker, Concrete Saw or Cutter, Fork Lift (walk behind, power operated), Generator- Pile Work, Generator, Hydra Hammer, Mechanical Compoactors (hand operated), Oiler (truck crane), Pin Puller, Portable Heaters, Powerbroom, Power buggies, Power Grinders, Pump (double action diaphragm), Pump gypsum, Pump (single action 1 to 3 inches), Trench

Machine hand, Welding Machine

GROUP 5: Batching Plant (on site of job), Generator (small), Grinder, Mixer (with skip), Mixer (2 small with or without skip), Mixer (2 bag or over, with or without skip), Mulch Machine, Oiler, Pump (centrifugal, up to 3 inches), Root

Cutter, Stump Chipper, Tower Crane (oiler), Track Tamper (2 engineers, each), Tractor (caterpillar or wheel), Vibrator, Work boat (deckhand), GROUP 6: Well drillers

IRON0046-003 07/01/2022

IRONWORKER

METALLIC LATHERS AND

REINFORCING IRONWORKERS.....$ 56.90 27.80

IRON0197-001 07/01/2021

IRONWORKER

STONE DERRICKMAN............$ 55.63 55.10

IRON0361-001 07/01/2022

IRONWORKER (STRUCTURAL)..........$ 55.70 84.79

IRON0580-001 07/01/2022

IRONWORKER, ORNAMENTAL...........$ 46.65 61.62

LABO0066-001 07/01/2022

BUILDING

Laborers:

Laborers....................$ 39.80 34.16

Plasterers Tenders..........$ 40.80 30.04

LABO0078-001 07/04/2022

LABORERS

BUILDING CONSTRUCTION

ASBESTOS (Removal, Abatement, Encapsulation or Decontamination of asbestos); LEAD; &

HAZARDOUS WASTE LABORERS

(Hazardous Waste, Hazardous Materials, Biochemical and Mold

Remediation, HVAC, Duct Cleaning, Re-spray

Fireproofing, etc).........$ 38.55 19.35

LABO1298-001 06/01/2022

HEAVY & HIGHWAY

Laborers:

Asphalt Rakers; Formsetters.$ 49.93 35.12+a

Asphalt Shovelers, Roller Boys & Tampers..............$ 48.46 35.12+a Regular Laborers............$ 43.99 35.12+a

A. FOOTNOTES:

Laborers working in a hazardous material hot zone shall receive an additional 20% premium.

Where the contract provides for night work outside the regular hours of work, the employees shall be paid at straight time plus a 30% night work premium for the 8 hours worked during the night.

Firewatch work performed after regular hours shall be paid an additional 10% premium. Second and Third Shift work will be paid at a 30% premium.

Contractor requesting laborers certified for hazardous material work and/or employed on hazardous material shall be required to pay an additional 10% premium.

PAIN0009-002 11/01/2022

PAINTER

GLAZIERS....................$ 47.30 50.52

Painters, Drywall Finishers.$ 43.00 38.11

Spray, Scaffold, Sandblasting................$ 46.00 38.11

PAIN0806-010 10/01/2020

Painters:

Stuctural Steel and Bridge..$ 51.50 49.63

PAIN1974-002 06/28/2022

Painters:

DRYWALL TAPERS/POINTERS.....$ 48.47 30.21

PLAS0262-003 08/01/2019

PLASTERER........................$ 45.73 30.37

PLAS0780-001 07/01/2018

CEMENT MASON/CONCRETE FINISHER...$ 51.97 33.56

PLUM0200-001 05/01/2022

PLUMBER

BUILDING CONSTRUCTION:......$ 55.48 43.25

RESIDENTIAL CONSTRUCTION:...$ 29.96 13.41

PLUM0638-001 07/01/2020

PLUMBER

SERVICE FITTERS.............$ 41.75 14.00

SPRINKLER FITTERS,

STEAMFITTERS................$ 59.05 58.34

Service Fitter work shall consist of all repair, service and maintenance work on domestic, commercial and industrial refrigeration, air conditioning and air cooling, stoker and oil burner apparatus and heating apparatus etc., including but not exclusively the charging, evacuation, leak testing and assembling for all machines for domestic, commercial and industrial refrigeration, air conditioning and heating apparatus. Also, work shall include adjusting, including capacity adjustments, checking and repairing or replacement of all controls and start up of all machines and repairing all defects that may develop on any system for domestic, commercial and industrial refrigeration and all air conditioning, air cooling, stoker and oil burner apparatus and heating apparatus regardless of size or type.

ROOF0154-001 05/01/2021

ROOFER...........................$ 45.25 40.36

SHEE0028-002 07/28/2022

SHEET METAL WORKER

BUILDING CONSTRUCTION.......$ 52.10 55.18

RESIDENTIAL CONSTRUCTION....$ 23.84 8.40

TEAM0282-002 07/01/2020

TRUCK DRIVER.....................$ 40.005 49.0325+a

FOOTNOTES:

a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Election Day, Veterans' Day (Armistice Day), Thanksgiving Day, Day after Thanksgiving and Christmas Day. Employees working two (2) days in the calendar week in which a holiday falls are to be paid for such holiday, provided that they shape each remaining workday during such calendar week.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISIO"