SOW Addendum 01.pdf
PDF 155 KB Posted
- Attached to
- VGLZ 242015 Repair HVAC B105
- Solicitation number
- W50S8525BA003
About this file
This document is Addendum 01 to a Statement of Work (SOW) for HVAC repair at Selfridge Air National Guard Base in Michigan. The addendum specifically updates Task 14 of the original SOW to require the contractor to install new isolation valves and unions at inlets/outlets of all pumps and boilers, facilitating easier replacement. Additionally, the contractor must install new flanged stainless steel flex connectors for all pump connections on both inlet and outlet sides. The addendum is dated 23 July 2025 and was prepared by Tom Resh, providing a technical specification update for the HVAC system repair project in Building 105.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OF1419 Abstract of Offers W50S8525BA003.pdf | ||
| Solicitation Amendment W50S8525BA0030001 SF 30.pdf | ||
| Sheet 5 of 8.pdf | ||
| Sheet 6 of 8.pdf | ||
| Sheet 3 of 8.pdf | ||
| RFIs B105 HVAC.pdf | ||
| Sheet 8 of 8.pdf | ||
| Sign In Sheet 7-16-2025.pdf | ||
| W50S8525BA001 Pre-Bid Conference_Site Visit Slides 7-16-2025.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A d d e n d u m 0 1 t o
S T A T E M ENT of WOR K
For
VGLZ 242015
Repair HVAC B105
Selfridge Air National Guard Base, Michigan
By: Tom Resh
23 July 2025
STATEMENT OF WORK
For
Repair HVAC B105
Selfridge Air National Guard Base, Michigan
Updated Note 14 on the Tasks of the SOW as follows in RED
1. The tasks of this SOW are:
14. The contractor will install new isolation valves and unions at inlets/outlets of all pumps and boilers for ease of replacement. The contractor will install new flanged stainless steel flex connectors for all pump connections on inlet and outlet sides.
End of Addendum 01