Sheet 3 of 8.pdf
PDF 178 KB Posted
- Attached to
- VGLZ 242015 Repair HVAC B105
- Solicitation number
- W50S8525BA003
About this file
This document is a mechanical demolition plan sheet for Building 105 at Selfridge Air National Guard Base in Michigan, detailing the comprehensive HVAC system removal and preparation for replacement. The sheet includes keyed technical notes specifying six primary demolition tasks: removing existing boilers and circulation pumps, terminating all piping and combustion/exhaust connections, demolishing pressure relief valves, strainers, chemical shot feeders, expansion tanks, and air separators, removing the existing air compressor, potentially removing a VFD controller, and demolishing the existing humidifier. The plan emphasizes contractor responsibilities for off-site disposal, tracking solid waste, maintaining building heating systems during construction, and coordinating with the Contracting Officer and Construction Contracting Officer's Representative (COR) to ensure uninterrupted building operations during the HVAC system replacement process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OF1419 Abstract of Offers W50S8525BA003.pdf | ||
| Solicitation Amendment W50S8525BA0030001 SF 30.pdf | ||
| Sheet 8 of 8.pdf | ||
| SOW Addendum 01.pdf | ||
| Sheet 6 of 8.pdf | ||
| RFIs B105 HVAC.pdf | ||
| Sheet 5 of 8.pdf | ||
| Sign In Sheet 7-16-2025.pdf | ||
| W50S8525BA001 Pre-Bid Conference_Site Visit Slides 7-16-2025.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 2 3 4 5
1 2 3 4 5
A
B
C
D
A
B
C
D
SHEET OF
Engineer/Consultants
Sheet Title
REPAIR HVAC
BLDG 105
BUILDING 105
DEMO
3 8
REVISIONS:
Project Number:
File:
Drawn By:
Designed By:
Checked By:
J. AUSTIN
Mark Date Description
PROJECT
Scale: 1/2"=1'-0" Date:
P:\CES_CECE Engineers\AutoCAD Users\CE Shared AutoCAD Settings\Templates\Template Graphics\127 WG.jpg P:\CES_CECD Site Development\ArtWork\127CE\CE Color PATCH small.jpg
T. RESH
T. RESH
24JUL2025
VGLZ 242015
MECH. RM.
6'-0" x 8'-0" RELIEF AIR
LOUVER
S
N
W E
MECHANICAL ROOM
SCALE: 1/2" = 1'-0"
HUMIDIFIER
PANEL MSB
SECTION 1 SECTION 2
EXISTING COMBUSTION
AIR LOUVER AND DAMPER
EXP. TANK
KEYED NOTES
1. Demolish existing boilers and circulation pumps, to include termination of all piping connections, combustion air and exhaust. Contractor is responsible for off site disposal and will track solid waste as required from the Selfridge ANG Base environmental engineering department.
The existing combustion and exhaust air will be demoed. It is suggested that the contractor stage the demo in order to maintain HHW to the building during construction as required. Note:
Coordination of continuation of HHW systems to the building will be coordinated with the KO and Construction COR.
2. The existing combustion and exhaust air will be demoed. All new exhaust and combustion air will be thru the roof.
3. The contractor will demo all existing PRV, strainers, chemical shot feeder, expansion tank and air separators.
4. The contractor will demo existing air compressor and terminate all connections to the air compressor.
5. Option 01 - Demo VFD for installation of new VFD controller on main
AHU.
6. The contractor will demo existing humidifier and terminate all connections to the humidifier.
AIR COMPRESSOR
FD
FD
3" HOUSKEEPING PAD
FD
PUMPS
PUMPS
STACKED HOT
WATER BOILERS
COMBUSTION
AIR & EXHAUST
CIRCULATING
PUMPS
21 1
P5 & P4 PANEL
FIRE ALARM
CONTROL PANEL
DDC PANEL
1 5
VFD PANEL
01 7/23/2025 ADDED NOTE 6
AutoCAD SHX Text 127th WING/CIVIL ENGINEER
AutoCAD SHX Text
SELFRIDGE AIR
AutoCAD SHX Text
NATIONAL GUARD
AutoCAD SHX Text
BASE, MICHIGAN