Sheet 3 of 8.pdf

PDF 178 KB Posted

Attached to
VGLZ 242015 Repair HVAC B105
Solicitation number
W50S8525BA003
Issued by

About this file

This document is a mechanical demolition plan sheet for Building 105 at Selfridge Air National Guard Base in Michigan, detailing the comprehensive HVAC system removal and preparation for replacement. The sheet includes keyed technical notes specifying six primary demolition tasks: removing existing boilers and circulation pumps, terminating all piping and combustion/exhaust connections, demolishing pressure relief valves, strainers, chemical shot feeders, expansion tanks, and air separators, removing the existing air compressor, potentially removing a VFD controller, and demolishing the existing humidifier. The plan emphasizes contractor responsibilities for off-site disposal, tracking solid waste, maintaining building heating systems during construction, and coordinating with the Contracting Officer and Construction Contracting Officer's Representative (COR) to ensure uninterrupted building operations during the HVAC system replacement process.

View the file

Other files

File Type Posted
OF1419 Abstract of Offers W50S8525BA003.pdf PDF
Solicitation Amendment W50S8525BA0030001 SF 30.pdf PDF
Sheet 8 of 8.pdf PDF
SOW Addendum 01.pdf PDF
Sheet 6 of 8.pdf PDF
RFIs B105 HVAC.pdf PDF
Sheet 5 of 8.pdf PDF
Sign In Sheet 7-16-2025.pdf PDF
W50S8525BA001 Pre-Bid Conference_Site Visit Slides 7-16-2025.pptx PPTX presentation

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 2 3 4 5

1 2 3 4 5

A

B

C

D

A

B

C

D

SHEET OF

Engineer/Consultants

Sheet Title

REPAIR HVAC

BLDG 105

BUILDING 105

DEMO

3 8

REVISIONS:

Project Number:

File:

Drawn By:

Designed By:

Checked By:

J. AUSTIN

Mark Date Description

PROJECT

Scale: 1/2"=1'-0" Date:

P:\CES_CECE Engineers\AutoCAD Users\CE Shared AutoCAD Settings\Templates\Template Graphics\127 WG.jpg P:\CES_CECD Site Development\ArtWork\127CE\CE Color PATCH small.jpg

T. RESH

T. RESH

24JUL2025

VGLZ 242015

MECH. RM.

6'-0" x 8'-0" RELIEF AIR

LOUVER

S

N

W E

MECHANICAL ROOM

SCALE: 1/2" = 1'-0"

HUMIDIFIER

PANEL MSB

SECTION 1 SECTION 2

EXISTING COMBUSTION

AIR LOUVER AND DAMPER

EXP. TANK

KEYED NOTES

1. Demolish existing boilers and circulation pumps, to include termination of all piping connections, combustion air and exhaust. Contractor is responsible for off site disposal and will track solid waste as required from the Selfridge ANG Base environmental engineering department.

The existing combustion and exhaust air will be demoed. It is suggested that the contractor stage the demo in order to maintain HHW to the building during construction as required. Note:

Coordination of continuation of HHW systems to the building will be coordinated with the KO and Construction COR.

2. The existing combustion and exhaust air will be demoed. All new exhaust and combustion air will be thru the roof.

3. The contractor will demo all existing PRV, strainers, chemical shot feeder, expansion tank and air separators.

4. The contractor will demo existing air compressor and terminate all connections to the air compressor.

5. Option 01 - Demo VFD for installation of new VFD controller on main

AHU.

6. The contractor will demo existing humidifier and terminate all connections to the humidifier.

AIR COMPRESSOR

FD

FD

3" HOUSKEEPING PAD

FD

PUMPS

PUMPS

STACKED HOT

WATER BOILERS

COMBUSTION

AIR & EXHAUST

CIRCULATING

PUMPS

21 1

P5 & P4 PANEL

FIRE ALARM

CONTROL PANEL

DDC PANEL

1 5

VFD PANEL

01 7/23/2025 ADDED NOTE 6

AutoCAD SHX Text 127th WING/CIVIL ENGINEER

AutoCAD SHX Text

SELFRIDGE AIR

AutoCAD SHX Text

NATIONAL GUARD

AutoCAD SHX Text

BASE, MICHIGAN

File details come from the government source that posted it. Updated .