Pre-Award RFI 1.doc

DOC document 36 KB Posted

Attached to
ADD ALTER POL OPS B530 Federal contract opportunity
Solicitation number
W50S83-20-B-0002
Issued by
Department of the Army National Guard

About this file

This document contains a pre-solicitation request for information and related federal contract opportunity for construction services. The Army National Guard is seeking bids to provide an addition and alterations to Building 530 at the Maine Air National Guard Base in Bangor, Maine, with a construction magnitude between $1 million and $5 million. This project is set aside for small businesses with average annual receipts less than $39.5 million. Bids are due by midnight on 30 September 2020, and award will be made based on price and price-related factors to the responsible bidder submitting a conforming bid most advantageous to the government. The work includes all labor, materials, and equipment to complete the project in accordance with provided specifications. A pre-bid conference will be held, and all documents will be available on SAM.gov. Funds are not currently available but are expected to be obligated by the anticipated award date.

View the file

Other files for this federal contract opportunity

Other files attached to ADD ALTER POL OPS B530, newest first.
File Type Posted
W50S83-20-B-0002-0003.pdf PDF
W50S83-20-B-0002-00002 DB Wage Determination Update.pdf PDF
Pre_Bid_Site_Visit.pdf PDF
Pre_Bid_Site_Visit_Sign_In_Sheet.pdf PDF
Final_B530_Drawings_B-3_08-24-2020.pdf PDF
Final_B530_Specifications_B-3_08-24-2020.pdf PDF
W50S83-20-B-0002-00001 52.228-1 Full Text.pdf PDF
W50S83-20-B-0002.pdf PDF
MEANG Form 4 (Change 20190801).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W50S83-20-B-0002 4 September 2020 Point of Contract:

SMSgt Jason Edwards

Contract Specialist jason.edwards.6@us.af.mil Tel: (207) 404-7107 Project Title and No:

Add./Alter. POL OPS Bldg. 530; FKNN182054 The purpose of this amendment is:

1. Address Requests for Information (RFI’s) received as a result of the pre-bid conference/site visit and contractor reviews of the plans and specifications. This is a running document and the final document will be incorporated by amendment prior to bid opening.

Please remember to acknowledge receipt of this Amendment on the original Invitation for Bid (IFB) Form in the appropriate block.

All other terms and conditions remain unchanged by this amendment.

Q1.

Please clarify Field Quality Control in Division 084113 3.7. Will the Government be hiring a testing agency, will a mock up storefront in a laboratory setting be required and the “Water Spray Test”, “Air Leakage Test” and “Water Penetration Test” be required in the laboratory setting?

A1.

Pending

Q2.

Please clarify Field Quality Control in Division 085113 3.3. Is field testing after window installation required?

A2.

Pending

Q3.

Is the project Tax Exempt?

A3.

Yes, state tax exemption form will be provided.

Q4.

Is a Cost Loaded Schedule required?

A4.

National Guard Bureau (NGB) requires all projects over $1.0M to have a cost loaded schedule.

Q5.

Is there a Wage Scale on this project?

A5.

Yes, Section 6 on page 8 of 42 in the Invitation for Bid, as well as page 39-42 indicate the wage determination applicable to this project.

Q6.

Is there a Buy America requirement?

A6.

FAR Clause 52.225-9 Buy American—Construction Materials (See page 25 of 42 of the IFB), FAR Clause 52.225-10 Notice of Buy American Requirement—Construction Materials and FAR Clause 52.225-22 Notice of Required Use of American Iron, Steel, and Manufactured Goods—Buy American Statute—Construction Materials are included in the Invitation for Bid (IFB) (See page 17 of 42 of the IFB). Also, see FAR Clause 52.225-21 Required Use of American Iron, Steel, and Manufactured Goods—Buy American Statute—Construction Materials (See page 28 of 42 of the IFB).

Q7.

Drawing MP101 tag a hot water supply line between VAV 3 and VAV 2 as both 2” and 1”, please confirm line size.

A7.

Pending