B8-Questions and Answers 8_29_22.docx
DOCX document 27 KB Posted
- Attached to
- Demo HEF
- Solicitation number
- W50S7L-22-R-0004
- Issued by
-
Department of the Army National Guard
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B25 FP 210 revised pdf.pdf | ||
| SOW - Demolish HEF System B25 and B76.pdf | ||
| B8-Questions and Answers 7_11_22.pdf | ||
| B8-Questions and Answers 7-7-22.pdf | ||
| B25 FP 210.pdf | ||
| SOW - Demolish HEF System B25 and B76.pdf | ||
| B25 FP 201.pdf | ||
| B25 Fire Suppression- Pull Boxes.pdf | ||
| B25 FP 000.pdf | ||
| B76 HEF System.pdf | ||
| B25 FP 211.pdf | ||
| B25 FP 200.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation W50S7L22R0004 – Demolish HEF System, B25 & B76 Question and Answers as of 29 August 2022
1. Question: Due to the short amount of time between award and construction can the contractors work at another set of dates?
Answer: Yes, the next available time to complete this work in B25 is October 17-21, 2022. At bid award the Contractors will need to tell the Government which timeframe they want to work the B25 portion of the project.
2. Question: The ceiling tiles are clipped into the grid. Do the replacement tiles need to be clipped in to prevent uplift from the wind.
Answer: Yes, the ceiling tiles will need to be clipped back into the grid.
3. Question: Does the ceiling grid around the foam generators need to be lowered to match the rest of the ceiling grid?
Answer: Yes, the ceiling grid will all need to be flush upon completion.
4. Question: Is a hazardous material survey available for this building? If not, please confirm only a hazardous materials survey is required as part of this contract. Should any items come back hot, confirm the abatement of these items will be treated as a differing site condition and a change order to the contract.
Answer: No hazardous material is anticipated to be encountered during this project work. The HEF system and all its components were installed in 2017.
5. Question: What are the staffing requirements for this project? Will a full time Super be required? Will a full time QC be required? Will dual hatting of the Super/QC be allowed?
Answer: No, fulltime Super nor QC will be required for the job. A dual hatting Super/QC/Craftsman will be allowed.
6. Question: Will the AF66 Submittal Schedule be issued, or is this something the Contractor is to generate after award?
Answer: No AF 66 will be issued for this job. The Contractor will still need to complete the EAL process and fill out all recycled material content forms.
7. Question: Please confirm that no Bid Schedule will be issued, and we are to submit pricing for the two CLIN’s in the Description section on sam.gov.
Answer: Yes, This job will be paid per the two CLINS list above.
8. Question: Do we need to demolish the fire piping from the fire riser room to the hangar floor over the office areas?
Answer: No this piping will be abandoned in place and capped with a fire proof cap at both ends. See revised drawing FP 210.
9. Question: Since the ACT is a clipped in system and will need to be sequentially removed to get to a tile that needs to be replaced, will the Contractor be allowed to remove just the tiles needing replacement, and install a new non-clipped in tile that is weighted to reduce uplift?
Answer: No, The new tiles need to be clipped back in to prevent them from becoming dislodged and falling on an aircraft.
10. Question: It was mentioned at the site visit that an alternate construction window is available later in the year. What are the dates for that window?
Answer: The new dates for the B25 Hangar area work are Oct 31 – Nov 4, Nov 7-11, or Jan 23-27, 2023
11. Question: Now that the project will be pushed into the winter months, will any temp heat be required by the Contractor?
Answer: No temp heat will be required.
image1.png
File details come from the government source that posted it. Updated .