B7- ULYB262003 AATTC Trailers Reconfigure and Removal_PP 1.pdf
PDF 157 KB Posted
- Attached to
- AATTC Trailer Reconfiguration Federal contract opportunity
- Solicitation number
- W50S7G26RA005
- Issued by
- Department of the Army National Guard
About this file
This is a Pre-Proposal Conference presentation for Solicitation W50S7G26RA005, issued by the 139th Airlift Wing, St. Joseph, Missouri for AATTC Trailer Reconfigurations. The procurement is a 100% Small Business Set-Aside with a construction magnitude between $25,000 and $100,000. Proposals are due January 27, 2026 at 1:00 p.m., and the project is tax-exempt.
The three-phase project involves interior and exterior facility upgrades to the Army Air Traffic Training Center (AATTC) South trailers and decommissioning of the North trailers. Phase 1 includes converting an existing room into a SIPR café by installing three quad SIPR ports, relocating a SIPR cabinet, installing external raceway with CAT6 cabling, redirecting in-floor power, and reconfiguring door access. Phase 2 focuses on exterior upgrades including a vapor barrier behind skirting, pipe insulation and heat tape for sewer lines, lockable access panel installation, building envelope sealing, and an awning over the entry door. Phase 3 involves decommissioning and removing the North trailer group, repairing the connecting deck, constructing new guardrails and stairs, and removing cameras and low-voltage wiring. All contractors must be SAM-registered, comply with OSHA requirements, undergo 14-day background checks, maintain REAL ID compliance by May 7, 2025, and submit proposals with a signed SF 1442, all line items priced, and a one-page capability statement demonstrating relevant experience. Key points of contact include the Contracting Officer (Capt Adam Danner), Contract Specialist (MSgt Amanda Glise), and Project Manager (Mr. Matt Long).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SignIn_27Jan2026_SiteVisit.pdf | ||
| ULYB262003_South_Trailer_Group_First_Floor_Plan.pdf | ||
| B8_Solicitation_W50S7G26RA0050002_Conformed.pdf | ||
| Decking-North trailer side.jpg | JPG image | |
| Additional Floor box.jpg | JPG image | |
| B8_Solicitation Amendment_W50S7G26RA0050002_SF 30.pdf | ||
| 5_SOW_ULYB262003_AATTC_Trailers_Reconfigure_and_Removal_REV2.pdf | ||
| Questions and Answers for AATTC Trailer Reconfiguration W50S7G26RA005.docx | DOCX document | |
| Decking-South trailer side.jpg | JPG image | |
| B8_SolicitationAmendmentW50S7G26RA005_0001_SF30.pdf | ||
| 5-SOW-ULYB262003 AATTC Trailers Reconfigure and Removal-REV1.pdf | ||
| Pre-Proposal SignIn Sheet.pdf | ||
| B8- Solicitation - W50S7G26RA005.pdf | ||
| 5-SOW-ULYB262003 AATTC Trailers Reconfigure and Removal.pdf | ||
| Police records check.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Conference
15 January 2026
CE RM 39 AATTC Trailer Reconfigurations
139th Airlift Wing, St. Joseph, MO
Solicitation W50S7G26RA005
Points of Contact
Contracting Officer (KO):Capt Adam Danner(816) 236-3256
Contract Specialist: MSgt Amanda Glise (816) 236-3032
BCE: Col Matthew Neil (816) 236-3230
Deputy BCE: Mr. Travis May (816) 236-3531
Project Manager: Mr. Matt Long (816) 236-3040
SUBMIT ALL QUESTIONS IN WRITING
100% Small Business Set-Aside (SB)
Magnitude of Construction is between $25,000.00 and $100,000.00
SAM Registered https://www.sam.gov/portal/public/SAM/
You must be SAM registered to do work with us.
Project Management
Safety
Environmental & Bio Environmental
Security Police
Fire Department
Real Property Worksheet
Base Operations/Airport
Communications Flight
Safety
Comply with any applicable OSHA requirements while on the job-site.
Motor Vehicle safety: seatbelts, speed limits, hands-free cell use.
Speed limit is 15 MPH on Base unless posted differently.
Confined Space entry requires confined space certified. Coordinate all confined space entries with Base Fire House (816-236-3301). Note: If the project includes confined space entry, the contractor will be required to sign a Statement of Understanding for Base Confined Space procedures.
Environmental & Bio-Environmental Off site dumping/removal – Contractor must use their own construction debris dumpsters.
Hazard Material usage/storage – see Hazardous Material Notification Form.
a. Review process for filling out and submitting forms.
b. Written approval must be obtained before any contractor is permitted to bring any LASER or radioactive source / equipment onto the installation.
If you find or suspect any soil contamination during the course of your work – notify the Environmental Management Office (236-3559/3604) or COTR immediately.
Appropriate hazardous material storage containers and/or cabinets (flammable, corrosive, etc.) must be used by any contractor/civilian entity who transports shall be used if storing HAZ-MAT on base.
Security Police
Police checks – allow 14 calendar days for approval.
a. Submit background checks by e-mail to;
i. Matt Long, matthew.long.49@us.af.mil
b. After a background check is approved, obtain an AF Form 75 at Security’s Visitor Center located in building 205 east of the main Base.
Visitor Center hours: M-W-F only 0700-1100
c. Present AF 75 at main gate for entry on Base and keep on your person at all times.
Contractor responsible for securing site material/tools.
Security Police
REAL ID
General Conditions: For contractors, this means ensuring all employees requiring base access possess a REAL ID-compliant driver's license or other acceptable form of identification. REAL ID criteria are outlined in DoDM 5200.08v3_DAFMAN31-101v3. You can verify REAL ID compliance and monitor for any changes to the enforcement date on the DHS website: https://www.dhs.gov/real-id Failure to present REAL ID-compliant identification after May 7, 2025, will result in denied access or individual must be escorted. Please take the necessary steps now to ensure compliance and avoid any access disruptions.
Fire Department
Burning/Welding Permit – will be required if any open flames or sparks will be generated by the contractor’s work – obtain at Base Fire Department (816- 236-3301).
Emergency Response: Dial 911 from any Base phone, or 911 from your cell phone.
Real Property Worksheet
Contractor is responsible for filling out the Real Property Worksheet 1354 and turn in to Base Real Property Manager at the end of the project (Part of Contract Close out in Base Standards).
Keep track of quantities of materials and all costs associated with each item.
Base Operation/Airport
FOD – Foreign object debris. Keep all FOD from the airfield.
Communications Flight
If radios are used, submit the frequency you will use for approval before operating on Base.
Project Specifics This will be a three-phase project.
Phase 1 involves interior facility upgrades to AATTC South trailers.
Phase 1 - Update an existing room in South trailer group into a SIPR café by installing three new quad SIPR ports, relocating the existing SIPR cabinet, providing an external raceway system with SIPR-appropriate CAT6 cabling, re-directing in-floor power, and reconfiguring existing door access to select doors.
Phase 2 focuses on exterior facility upgrades to the AATTC South trailers.
Phase 2 - Update South trailer group exterior, including installation of a continuous exterior-rated vapor barrier behind skirting, insulation of piping under trailers and heat tape for sewer lines, installation of a lockable access panel, sealing of the building envelope where needed, and placement of a new awning over the exposed entry door with reuse of existing components where feasible.
Phase 3 is the decommissioning and removal of the North AATTC trailers.
Part 3 - Decommission and remove North trailer group from base and repairs to the existing decking that joined North and South trailer groups, construction of new guardrail and stairs on decking, removal of cameras and low-voltage wiring from North trailers, removal of North trailer skirting and lockable access panel.
Completed proposal package
Offer, Standard Form (SF) 1442 signed (Blocks 20(a), 20(b), and 20(c))
Section 00010 Line Items- all items must be priced
One Page capability statement highlighting verifiable experience and past performance regarding its areas of specialty and overall capabilities to perform the project requirements in the Statement of Work. The Government may use the offeror’s capability statement to obtain additional past performance information. At a minimum, the capability statement must include a brief (e.g. 1 – 5 sentences) description of relevant work performed that demonstrates experience and corresponding list of points of contact for each experience listed. If any experience was performed as the prime contractor on a federal contract, please include the associated contract/task order number.
When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR
4.102. One copy of the SF1442 is required to have an original signature.
d. All amendments to the solicitation must be acknowledged.
e. Include the following in the subject line of the email: “Proposal No. W50S7G-26-R-A005”, and the Name of the contractor.
SF 1442 front and back
Block #17 – acceptance (look at #13D)
Acknowledge Amendments (Block #19)
Sign SF 1442 (back) (Block 20A and 20B)
RECAP
All information relating to this RFP, including pertinent changes/amendments and information will be posted on web site:
http://www.sam.gov.
Check SAM on a regular basis
Discuss receipt of proposal/getting on site/late is late
Bids due 27 Jan 2026 at 1:00 p.m.
Project is tax exempt http://www.sam.gov/
QUESTIONS????
| Pre-Proposal Conference |
| Points of Contact |
| SUBMIT ALL QUESTIONS IN WRITING � |
| 100% Small Business Set-Aside (SB) |
| SAM Registered |
| Project Management |
| Safety |
| Environmental & Bio-Environmental |
| Security Police |
| Security Police |
| Fire Department |
| Real Property Worksheet |
| Base Operation/Airport |
| Communications Flight |
| Project Specifics |
| Completed proposal package |
| SF 1442 front and back |
| RECAP |
| QUESTIONS???? |
File details come from the government source that posted it. Updated .