W50S7G20B00010001 Amendment 1.pdf

PDF 147 KB Posted

Attached to
C-130 Flight Simulator Facility
Solicitation number
W50S7G-20-B-0001-Solicitation
Issued by

About this file

This amendment modifies a solicitation for the construction of a C-130 Flight Simulator Facility. The amendment changes the bid due date from July 9, 2020 to July 14, 2020 at 1:00 PM local time. It revises specifications for sound absorbing wall units, protective technical barriers, door hardware, roof accessories, and insulated metal wall panels. It also revises sustainable design requirements and calls for 6x6 W2.9 x W.9 WWF at sidewalks. Drawing details are revised and exterior finish schedules and resinous flooring requirements are updated. The solicitation is for the Department of the Army National Guard to construct the facility in accordance with the solicitation and revised plans and specifications.

View the file

Other files

File Type Posted
C4 - Abstract of Offers SF1419.pdf PDF
B8 - Q and A 17 July 2020.docx DOCX document
Bid Opening Location Map.pdf PDF
B8 - Q and A 16 July 2020.docx DOCX document
W50S7G20B00010004 Amendment 4.pdf PDF
B8 - Q and A 15 July 2020.docx DOCX document
B8 - Q and A 14 July 2020.docx DOCX document
W50S7G20B00010003 Amendment 3.pdf PDF
B8 - Q and A 10 July 2020.docx DOCX document
W50S7G20B00010002 Amendment 2.pdf PDF
B8 - Q and A 09 July 2020.docx DOCX document
B8 - Q and A 08 July 2020.docx DOCX document
B8 - Q and A 02 July 2020.docx DOCX document
B8 - Q and A 26 June 2020.docx DOCX document
B7 - Q and A 19 June 2020.docx DOCX document
B7 - Pre-bid Conference Minutes.pdf PDF
B7 - Construct Simulator Pre-Bid SIGN IN SHEET.pdf PDF
B7-Pre-Bid Conference PP.pptx PPTX presentation
B7 - Q and A 18 June 2020.docx DOCX document
A3 - Construct Simulator Facility PWS 25 Mar 2020.pdf PDF
B8 - Att 6 JA Brandname (Schlage)_Redacted.pdf PDF
B8 - Att 5 JA Brandname (Monaco)_Redacted.pdf PDF
B8 - Att 8 Checklist for Bid Bonds.doc DOC document
B8 - Att 7 JA Brandname (Automated Logic)_Redacted.pdf PDF
W50S7G20B0001 Construct C-130 Flight Simulator Soliciation.pdf PDF
B8 - Att 4 JA Sole Source (Advantor)_Redacted.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ULYB169010

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The follow ing changes are hereby made to the project and/or specifications. Bid due date has changed to 14 July 2020 at 01:00 PM local time. See next pages for amendment changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Jul-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S7G20B0001

X 9B. DATED (SEE ITEM 11)

09-Jun-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Jul-2020

CODE

USPFO MO 139 MISSION SUPPORT CONTRACTING

705 MEMORIAL DRIVE

SAINT JOSEPH MO 64503-9307

W50S7G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S7G20B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001

This addendum forms a part of the Contract documents and modifies the Bidding Documents with amendment and additions noted below. Acknowledge receipt of this Addendum in the Bid form. Failure to do so may subject the Proposer to disqualification.

Amendment 0001 consists of descriptive changes and revised drawings listed below. Revised specifications and drawings are also provided with this amendment.

ALL REVISED SPECIFICATIONS AND DRAWINGS HAVE BEEN ATTACHED TO beta.SAM LABELED AS

“COMBINED REVISED SPECS, DRAWINGS & GEOTECH REPORT AMENDMENT 0001”.

CHANGES TO SPECIFICATIONS:

A. SECTION 098433 – SOUND ABSORBING WALL UNITS has been revised.

B. SECTION 132754 – PROTECTIVE TECHNICAL BARRIER has been revised.

C. SECTION 087100 – DOOR HARDWARE has been revised.

D. SECTION 077200 – ROOF ACCESSORIES has been revised.

E. SECTION 074213.19 – INSULATED METAL WALL PANELS has been revised.

F. SECTION 18113 – SUSTAINABLE DESIGN REQUIREMENTS has been revised. The project is pursuing GBCI Guiding Principles. LEED Credits are acceptable compliance paths for several of the principles and those are called out in the attachment to specification 01 81 13.13 GPA DoD Project Information Form. A LEED Accredited Professional is not a requirement, but previous GBCI Guiding Principles or LEED experience would be beneficial.

G. Use 6x6 W2.9 x W.9 WWF at sidewalks.

CHANGES TO DRAWINGS:

A. Details of A1/SK-A-542 and A2/SK-A-542 have been revised. See attached revision.

B. No corner guards are required at detail C4/A-712.

C. The 7 5/8” walls can be poured at 8” wide.

D. Details of SK-A-302 have been revised.

E. Wire mesh partitions at PART STORAGE 127 are to terminate at the bottom of roof deck.

F. EXTERIOR FINISH SCHEDULE on drawing A-201 has been revised.

G. For the resinous flooring provide 1/8” nominal thickness. At rooms 110, 111, 112 and 113 provide a resinous cover base on all partitions, ceramic tile will resume above the base where scheduled.

Department of Defense Guidance on the use of Cloth Face Coverings dated 05 April 2020 Effective immediately, to the extent practical, all individuals on DoD property, installations, and facilities will wear cloth face coverings when they cannot maintain six feet of social distance in public areas or work centers.

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 09-Jul-2020 01:00 PM to 14-Jul-2020 01:00 PM.

(End of Summary of Changes)

W50S7G20B0001

File details come from the government source that posted it. Updated .