B7 - Q and A 19 June 2020.docx

DOCX document 15 KB Posted

Attached to
C-130 Flight Simulator Facility
Solicitation number
W50S7G-20-B-0001-Solicitation
Issued by

About this file

This document contains questions and answers regarding a solicitation to construct a C-130 Flight Simulator Facility for the Department of the Army National Guard. Key details include that the solicitation involves constructing a facility in accordance with attached plans, specifications, and a performance work statement. Questions addressed project management software requirements, background check timeframes, fence requirements, the applicability of small business set-asides to subcontractors, flooring specifications, and preferred crane manufacturers. The solicitation number is W50S7G-20-B-0001 and is for a small business set-aside where the size standard for the applicable NAICS code of 236220 is average annual receipts of $39.5 million.

View the file

Other files

File Type Posted
C4 - Abstract of Offers SF1419.pdf PDF
B8 - Q and A 17 July 2020.docx DOCX document
B8 - Q and A 16 July 2020.docx DOCX document
Bid Opening Location Map.pdf PDF
W50S7G20B00010004 Amendment 4.pdf PDF
B8 - Q and A 15 July 2020.docx DOCX document
B8 - Q and A 14 July 2020.docx DOCX document
W50S7G20B00010003 Amendment 3.pdf PDF
B8 - Q and A 10 July 2020.docx DOCX document
W50S7G20B00010002 Amendment 2.pdf PDF
B8 - Q and A 09 July 2020.docx DOCX document
B8 - Q and A 08 July 2020.docx DOCX document
B8 - Q and A 02 July 2020.docx DOCX document
W50S7G20B00010001 Amendment 1.pdf PDF
B8 - Q and A 26 June 2020.docx DOCX document
B7 - Construct Simulator Pre-Bid SIGN IN SHEET.pdf PDF
B7 - Q and A 18 June 2020.docx DOCX document
B7 - Pre-bid Conference Minutes.pdf PDF
B7-Pre-Bid Conference PP.pptx PPTX presentation
W50S7G20B0001 Construct C-130 Flight Simulator Soliciation.pdf PDF
B8 - Att 4 JA Sole Source (Advantor)_Redacted.pdf PDF
A3 - Construct Simulator Facility PWS 25 Mar 2020.pdf PDF
B8 - Att 8 Checklist for Bid Bonds.doc DOC document
B8 - Att 7 JA Brandname (Automated Logic)_Redacted.pdf PDF
B8 - Att 5 JA Brandname (Monaco)_Redacted.pdf PDF
B8 - Att 6 JA Brandname (Schlage)_Redacted.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construct C-130 Flight Simulator Facility Question and Answer’s19 June 2020
1.Q: Be advised that the drawings do not reflect what the various colored locations means provide a key for the drawings that clearly calls out what is to be installed and where.
A: Pending with the A/E.
2.Q: Bridge Crane & Simulator Interlock Detail, can we ask the Simulator controls company if we can send a dry contact via remote I/O? We do this quite often and use two different styles but would prefer to do it this way.

1. Banner PM2 Kit as shown. Can be 900MHZ or 2.4 GHz – see attached for clarity.

2. One Gateway would be mounted on the crane and a Node on the Simulator Controls A: Answer pending with the A/E.

3. Q: Are we allowed to send an electronic link to the plans to potential subs and suppliers or do they have to go to SAMS and be registered and get their own link?

A: Please do not post on any sites for everyone to see. They can be given to subcontractors for bidding purposes only.

4.Q: In the specs it says that if awarded the job you would have to have background checks for anyone working on site as well as the “real id/passport”. Is this still going to be required for this project even though the project location is not inside the security fence?
A: Answer Pending
5.Q: Are you required to have a construction fence?
A: No, but you are responsible for your job site and securing any material you may have there.
6.Q: Is it still 14 days for the background checks to be run?
A: Yes, as of right now that has not changed to a longer timeframe due to the current circumstances.
7.Q: The pre-bid PowerPoint specified a pre-engineered metal building, is that correct?
A: No, this is not a pre-engineered metal building. Please follow the specifications and drawings
8.Q: Is there project management software like ProCore required on this project?
A: Not required but if you would like to propose to use something that is up to you.
9.Q: If this project is set aside for a small business, does this apply to the subs as well? What is the dollar amount considered for a small business?
A: The set aside is for the awardee of the Government Contract (Prime Contractor). For the NAICS related to this solicitation 236220 the dollar amount is $39,500,000.00 in average annual receipts.
10.Q: The resinous flooring spec calls for 100% solids epoxy primer and two coats of aliphatic urethane with a total of 20mils in one sections and for a troweled system in another section. The standard thin mil system would be 2 coats of 100% solids epoxy with one topcoat of aliphatic urethane with the oxide broadcast. The standard troweled system would be a nominal ¼” of epoxy mortar with the above system as the topcoats. Also the finish schedule calls out for a resinous cove/ceramic cove base in rooms 110,111,112,113 all of the drawings show ceramic base to the floor.
A: Answer Pending
11.Q: Is there a preferred bridge crane manufacturer?
A: Answer Pending