This document is a Standard Form 30 (SF 30) Amendment to Solicitation for a demolition project issued by the Georgia Army National Guard. The amendment modifies the original solicitation (W50S7025BA001) for demolition services at Hangar Building 199 located at the Savannah Combat Readiness Training Center (CRTC). Key changes include updating the Performance Work Statement (PWS) to version 2, extending the Q&A period, and adding several new contract documents such as a Base Environmental Guide and Wage Determination.
The solicitation requires a contractor to provide personnel, equipment, tools, materials, supervision, and quality control to remove Hangar Building 199 and adjacent support facilities. Critical dates include a mandatory site visit on 14 May 2025 at 9:30 AM, bid submission deadline of 18 June 2025 at 10:00 AM EST, and a bid guarantee requirement of 20% of the bid price or $3M, whichever is less. Potential bidders must complete online representations and certifications at SAM.gov, submit a completed Standard Form 1449, and follow specific pricing and documentation instructions outlined in the amendment.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Continuation of Supplies or Services and Prices/Costs
The following CLIN(s) / SLIN(s) / ELIN(s) were added:
Item Supplies / Services Quantity Unit Unit Price Amount
Option Line Item
Additional Demolition and Restoration of Site. See PWS 5.1.9 Product Service Code: P400 Pricing Arrangement: Firm Fixed Price
1 Job
Continuation of Inspection and Acceptance
The inspection and acceptance locations for the following CLIN(s) / SLIN(s) / ELIN
(s) were added:
Option Line Item 1001 Inspection and Acceptance Location - W50S70 - W7M3 USPFO ACTIVITY GAANG 165
INFORMATION VALUE
Action Both Location Destination
Acceptance Location
W50S70
W7M3 USPFO ACTIVITY GAANG 165
KO FOR GAANG DO NOT DELETE, 1401 ROBERT B MILLER JR DR
GARDEN CITY, GA 31408-9001
UNITED STATES
Instructions See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.
Continuation of Deliveries or Performance
The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were added:
Option Line Item 1001
INFORMATION VALUE
Period of Performance 30 Sep 2025 to 31 May 2026
Service Performance Site - W50S70 - W7M3 USPFO ACTIVITY GAANG 165
INFORMATION VALUE
Address
Service Performance Site W50S70
W7M3 USPFO ACTIVITY GAANG 165
KO FOR GAANG DO NOT DELETE, 1401 ROBERT B MILLER JR DR
GARDEN CITY, GA 31408-9001
UNITED STATES
W50S7025BA0010001
Delivery Delivery Period PeriodStart = 30 Sep 2025. PeriodEnd = 31 May 2026.
The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:
INFORMATION FROM TO
Period of Performance 30 Sep 2025 to 31 Mar 2026 30 Sep 2025 to 31 May 2026
Contract Clauses
Additional Information/Notes
The following clauses were deleted:
FAR Clauses Incorporated by Reference
Number Title Effective Date Alternate/ Deviation
Variation Effective Date
52.219-3 Notice of HUBZone Set-Aside or Sole-Source Award. Oct 2022
52.219-27 Notice of Set-Aside for, or Sole-Source Award to, Service- Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program.
Feb 2024
52.219-29 Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns.
Oct 2022
52.219-30 Notice of Set-Aside for, or Sole-Source Award to, Women- Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program.
Oct 2022
52.222-34 Project Labor Agreement. Jan 2024
Addendum to Contract Clauses
Additional Information/Notes
The following clauses were added:
FAR Clauses Incorporated by Reference
Number Title Effective Date Alternate/ Deviation
Variation Effective Date
52.232-18 Availability of Funds. Apr 1984
FAR Clauses Incorporated by Full Text
52.211-11 Liquidated Damages-Supplies, Services, or Research and Development.
(Sep 2000)
Liquidated Damages-Supplies, Services, or Research and Development (Sept 2000)
If the Contractor fails to deliver the supplies or perform the services within the time specified in this (a) contract, the Contractor shall, in place of actual damages, pay to the Government liquidated damages of $ per calendar day of delay.389.00
If the Government terminates this contract in whole or in part under the Default-Fixed-Price Supply (b) and Service clause, the Contractor is liable for liquidated damages accruing until the Government reasonably obtains delivery or performance of similar supplies or services. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
The Contractor will not be charged with liquidated damages when the delay in delivery or (c) performance is beyond the control and without the fault or negligence of the Contractor as defined in the Default-Fixed-Price Supply and Service clause in this contract.
(End of clause)
The following clauses were modified:
52.228-16Performance and Payment Bonds-Other Than Construction.Nov 2006 hereby reads as follows:
As prescribed in , insert a clause substantially as follows:28.103-4
Performance and Payment Bonds-Other Than Construction (Nov 2006)
. As used in this clause-(a) Definitions
"Original contract price" means the award price of the contract or, for requirements contracts, the price payable for the estimated quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
The Contractor shall furnish a performance bond (Standard Form 1418) for the protection of the (b) Government in an amount equal to percent of the original contract price and a payment bond _ _100%_ Standard Form 1416) in an amount equal to percent of the original contract price. ___100%_
The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to (c) the Contracting Officer, within days, but in any event, before starting work._10___
The Government may require additional performance and payment bond protection if the contract (d) price is increased. The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bonds or to obtain additional bonds.
The bonds shall be in the form of firm commitment, supported by corporate sureties whose names (e) appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the , or may be obtained from the:Federal Register
U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, 3700 East West Highway, Room 6 F01
Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
(End of clause)
The following clauses were deleted:
FAR Clauses Incorporated by Full Text 52.211-12 Liquidated Damages-Construction. (Sep 2000)
As prescribed in , insert the following clause in solicitations and contracts:11.503(b)
Liquidated Damages-Construction (Sept 2000)
If the Contractor fails to complete the work within the time specified in the contract, the Contractor (a) shall pay liquidated damages to the Government in the amount of [Contracting Officer insert 1121.37 amount] for each calendar day of delay until the work is completed or accepted.
If the Government terminates the Contractor's right to proceed, liquidated damages will continue to (b) accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.232-5 Payments under Fixed-Price Construction Contracts. (May 2014)
As prescribed in , insert the following clause:32.111(a)(5)
Payments under Fixed-Price Construction Contracts (May 2014)
. The Government shall pay the Contractor the contract price as provided in this (a) Payment of price contract.
. The Government shall make progress payments monthly as the work proceeds, or (b) Progress payments at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
The Contractor's request for progress payments shall include the following substantiation:(1)
An itemization of the amounts requested, related to the various elements of work required by the (i) contract covered by the payment requested.
A listing of the amount included for work performed by each subcontractor under the contract.(ii)
A listing of the total amount of each subcontract under the contract.(iii)
A listing of the amounts previously paid to each such subcontractor under the contract.(iv)
Additional supporting data in a form and detail required by the Contracting Officer.(v)
In the preparation of estimates, the Contracting Officer may authorize material delivered on the site (2) and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-
Consideration is specifically authorized by this contract; and(i)
The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the (ii) material will be used to perform this contract.
. Along with each request for progress payments, the Contractor shall furnish (c) Contractor certification the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that-
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
____ ( )Name
____ ( )Title
____ ( )Date
. If the Contractor, after making a certified request for progress (d) Refund of unearned amounts payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
Notify the Contracting Officer of such performance deficiency; and(1)
Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner (2) provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-
The date the Contractor notifies the Contracting Officer that the performance deficiency has been (i) corrected; or
The date the Contractor reduces the amount of any subsequent certified request for progress payments (ii) by an amount equal to the unearned amount.
. If the Contracting Officer finds that satisfactory progress was achieved during any period (e) Retainage for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
. All material and work covered by progress payments made (f) Title, liability, and reservation of rights shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
Relieving the Contractor from the sole responsibility for all material and work upon which payments (1) have been made or the restoration of any damaged work; or
Waiving the right of the Government to require the fulfillment of all of the terms of the contract.(2)
. In making these progress payments, the Government shall, upon (g) Reimbursement for bond premiums request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
. The Government shall pay the amount due the Contractor under this contract after-(h) Final payment
Completion and acceptance of all work;(1)
Presentation of a properly executed voucher; and(2)
Presentation of release of all claims against the Government arising by virtue of this contract, other (3) than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 (31 U.S.C.3727 and 41 U.S.
C.6305).
. Notwithstanding any provision of this contract, progress (i) Limitation because of undefinitized work payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
. In accordance with 31 U.S.C.3903(c)(1), the amount (j) Interest computation on unearned amounts payable under paragraph (d)(2) of this clause shall be-
Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most (1) recent auction of such bills prior to the date the Contractor receives the unearned amount; and
Deducted from the next available payment to the Contractor.(2)
(End of clause)
52.232-27 Prompt Payment for Construction Contracts. (Jan 2017)
As prescribed in , insert the following clause:32.908(b)
Prompt Payment for Construction Contracts (Jan 2017)
Notwithstanding any other payment terms in this contract, the Government will make invoice payments under the terms and conditions specified in this clause. The Government considers payment as being made on the day a check is dated or the date of an electronic funds transfer. Definitions of pertinent terms are set forth in sections 2.101, 32.001, and 32.902 of the Federal Acquisition Regulation. All days referred to in this clause are calendar days, unless otherwise specified. (However, see paragraph (a)(3) concerning payments due on Saturdays, Sundays, and legal holidays.)
Invoice payments-(a)
. For purposes of this clause, there are several types of invoice payments (1) Types of invoice payments that may occur under this contract, as follows:
Progress payments, if provided for elsewhere in this contract, based on Contracting Officer approval (i) of the estimated amount and value of work or services performed, including payments for reaching milestones in any project.
The due date for making such payments is 14 days after the designated billing office receives a (A) proper payment request. If the designated billing office fails to annotate the payment request with the actual date of receipt at the time of receipt, the payment due date is the 14 thday after the date of the Contractor's payment request, provided the designated billing office receives a proper payment request and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.
The due date for payment of any amounts retained by the Contracting Officer in accordance with the (B) clause at 52.232-5, Payments Under Fixed-Price Construction Contracts, is as specified in the contract or, if not specified, 30 days after approval by the Contracting Officer for release to the Contractor.
Final payments based on completion and acceptance of all work and presentation of release of all (ii) claims against the Government arising by virtue of the contract, and payments for partial deliveries that have been accepted by the Government ( each separate building, public work, or other division of the e.g., contract for which the price is stated separately in the contract).
The due date for making such payments is the later of the following two events:(A)
The 30 thday after the designated billing office receives a proper invoice from the Contractor.(1)
The 30 thday after Government acceptance of the work or services completed by the Contractor. For a (2) final invoice when the payment amount is subject to contract settlement actions ( release of claims), e.g., acceptance is deemed to occur on the effective date of the contract settlement.
If the designated billing office fails to annotate the invoice with the date of actual receipt at the time (B) of receipt, the invoice payment due date is the 30 thday after the date of the Contractor's invoice, provided the designated billing office receives a proper invoice and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.
. The Contractor shall prepare and submit invoices to the designated billing office (2) Contractor's invoice specified in the contract. A proper invoice must include the items listed in paragraphs (a)(2)(i) through (a) (2)(xi) of this clause. If the invoice does not comply with these requirements, the designated billing office must return it within 7 days after receipt, with the reasons why it is not a proper invoice. When computing any interest penalty owed the Contractor, the Government will take into account if the Government notifies the Contractor of an improper invoice in an untimely manner.
Name and address of the Contractor.(i)
Invoice date and invoice number. (The Contractor should date invoices as close as possible to the (ii) date of mailing or transmission.)
Contract number or other authorization for work or services performed (including order number and (iii) line item number).
Description of work or services performed.(iv)
Delivery and payment terms ( discount for prompt payment terms).(v) e.g., Name and address of Contractor official to whom payment is to be sent (must be the same as that in (vi) the contract or in a proper notice of assignment).
Name (where practicable), title, phone number, and mailing address of person to notify in the event (vii) of a defective invoice.
For payments described in paragraph (a)(1)(i) of this clause, substantiation of the amounts (viii) requested and certification in accordance with the requirements of the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts.
Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if (ix) required elsewhere in this contract.
Electronic funds transfer (EFT) banking information.(x)
The Contractor shall include EFT banking information on the invoice only if required elsewhere in (A) this contract.
If EFT banking information is not required to be on the invoice, in order for the invoice to be a (B) proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision ( 52.232-38, Submission of Electronic Funds Transfer e.g., Information with Offer), contract clause ( 52.232-33, Payment by Electronic Funds Transfer-System e.g., for Award Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.
EFT banking information is not required if the Government waived the requirement to pay by EFT.(C)
Any other information or documentation required by the contract.(xi)
. The designated payment office will pay an interest penalty automatically, without (3) Interest penalty request from the Contractor, if payment is not made by the due date and the conditions listed in paragraphs (a)(3)(i) through (a)(3)(iii) of this clause are met, if applicable. However, when the due date falls on a Saturday, Sunday, or legal holiday, the designated payment office may make payment on the following working day without incurring a late payment interest penalty.
The designated billing office received a proper invoice.(i)
The Government processed a receiving report or other Government documentation authorizing (ii) payment and there was no disagreement over quantity, quality, Contractor compliance with any contract term or condition, or requested progress payment amount.
In the case of a final invoice for any balance of funds due the Contractor for work or services (iii) performed, the amount was not subject to further contract settlement actions between the Government and the Contractor.
. The Government will compute the interest penalty in accordance with the (4) Computing penalty amount Office of Management and Budget prompt payment regulations at .5 CFR Part 1315
For the sole purpose of computing an interest penalty that might be due the Contractor for payments (i) described in paragraph (a)(1)(ii) of this clause, Government acceptance or approval is deemed to occur constructively on the 7 thday after the Contractor has completed the work or services in accordance with the terms and conditions of the contract. If actual acceptance or approval occurs within the constructive acceptance or approval period, the Government will base the determination of an interest penalty on the actual date of acceptance or approval. Constructive acceptance or constructive approval requirements do not apply if there is a disagreement over quantity, quality, or Contractor compliance with a contract provision. These requirements also do not compel Government officials to accept work or services, approve Contractor estimates, perform contract administration functions, or make payment prior to fulfilling their responsibilities.
The prompt payment regulations at 5 CFR1315.10(c) do not require the Government to pay interest (ii) penalties if payment delays are due to disagreement between the Government and the Contractor over the payment amount or other issues involving contract compliance, or on amounts temporarily withheld or retained in accordance with the terms of the contract. The Government and the Contractor shall resolve claims involving disputes, and any interest that may be payable in accordance with the clause at FAR 52.233-1, Disputes.
. The designated payment office will pay an interest penalty (5) Discounts for prompt payment automatically, without request from the Contractor, if the Government takes a discount for prompt payment improperly. The Government will calculate the interest penalty in accordance with the prompt payment regulations at .5 CFR Part 1315
Additional interest penalty.(6)
The designated payment office will pay a penalty amount, calculated in accordance with the prompt (i) payment regulations at in addition to the interest penalty amount only if-5 CFR Part 1315
The Government owes an interest penalty of $1 or more;(A)
The designated payment office does not pay the interest penalty within 10 days after the date the (B) invoice amount is paid; and
The Contractor makes a written demand to the designated payment office for additional penalty (C) payment, in accordance with paragraph (a)(6)(ii) of this clause, postmarked not later than 40 days after the date the invoice amount is paid.
(ii)
The Contractor shall support written demands for additional penalty payments with the following (A) data. The Government will not request any additional data. The Contractor shall-
Specifically assert that late payment interest is due under a specific invoice, and request payment of (1) all overdue late payment interest penalty and such additional penalty as may be required;
Attach a copy of the invoice on which the unpaid late payment interest was due; and(2)
State that payment of the principal has been received, including the date of receipt.(3)
If there is no postmark or the postmark is illegible-(B)
The designated payment office that receives the demand will annotate it with the date of receipt (1) provided the demand is received on or before the 40 thday after payment was made; or
If the designated payment office fails to make the required annotation, the Government will (2) determine the demand's validity based on the date the Contractor has placed on the demand, provided such date is no later than the 40 thday after payment was made.
. If this contract provides for contract financing, the Government will (b) Contract financing payments make contract financing payments in accordance with the applicable contract financing clause.
. The Contractor shall include in each subcontract for property or (c) Subcontract clause requirements services (including a material supplier) for the purpose of performing this contract the following:
. A payment clause that obligates the Contractor to pay the (1) Prompt payment for subcontractors subcontractor for satisfactory performance under its subcontract not later than 7 days from receipt of payment out of such amounts as are paid to the Contractor under this contract.
. An interest penalty clause that obligates the Contractor to pay to the (2) Interest for subcontractors subcontractor an interest penalty for each payment not made in accordance with the payment clause-
For the period beginning on the day after the required payment date and ending on the date on which (i) payment of the amount due is made; and
Computed at the rate of interest established by the Secretary of the Treasury, and published in the (ii) , for interest payments under 41 U.S.C. 7109 in effect at the time the Contractor accrues Federal Register the obligation to pay an interest penalty.
. A clause requiring each subcontractor to-(3) Subcontractor clause flowdown
Include a payment clause and an interest penalty clause conforming to the standards set forth in (i) paragraphs (c)(1) and (c)(2) of this clause in each of its subcontracts; and
Require each of its subcontractors to include such clauses in their subcontracts with each lower-tier (ii) subcontractor or supplier.
. The clauses required by paragraph (c) of this clause shall not be (d) Subcontract clause interpretation construed to impair the right of the Contractor or a subcontractor at any tier to negotiate, and to include in their subcontract, provisions that-
. Permit the Contractor or a subcontractor to retain (without cause) a specified (1) Retainage permitted percentage of each progress payment otherwise due to a subcontractor for satisfactory performance under the subcontract without incurring any obligation to pay a late payment interest penalty, in accordance with terms and conditions agreed to by the parties to the subcontract, giving such recognition as the parties deem appropriate to the ability of a subcontractor to furnish a performance bond and a payment bond;
. Permit the Contractor or subcontractor to make a determination that part or all (2) Withholding permitted of the subcontractor's request for payment may be withheld in accordance with the subcontract agreement; and
. Permit such withholding without incurring any obligation to pay a late (3) Withholding requirements payment penalty if-
A notice conforming to the standards of paragraph (g) of this clause previously has been furnished to (i) the subcontractor; and
The Contractor furnishes to the Contracting Officer a copy of any notice issued by a Contractor (ii) pursuant to paragraph (d)(3)(i) of this clause.
. If a Contractor, after making a request for payment to the (e) Subcontractor withholding procedures Government but before making a payment to a subcontractor for the subcontractor's performance covered by the payment request, discovers that all or a portion of the payment otherwise due such subcontractor is subject to withholding from the subcontractor in accordance with the subcontract agreement, then the Contractor shall-
. Furnish to the subcontractor a notice conforming to the standards of paragraph (1) Subcontractor notice
(g) of this clause as soon as practicable upon ascertaining the cause giving rise to a withholding, but prior to the due date for subcontractor payment;
. Furnish to the Contracting Officer, as soon as practicable, a copy of the (2) Contracting Officer notice notice furnished to the subcontractor pursuant to paragraph (e)(1) of this clause;
. Reduce the subcontractor's progress payment by an (3) Subcontractor progress payment reduction amount not to exceed the amount specified in the notice of withholding furnished under paragraph (e)(1) of this clause;
. Pay the subcontractor as soon as practicable after the correction (4) Subsequent subcontractor payment of the identified subcontract performance deficiency, and-
Make such payment within-(i)
Sevendays after correction of the identified subcontract performance deficiency (unless the funds (A) therefor must be recovered from the Government because of a reduction under paragraph (e)(5)(i)) of this clause; or
Sevendays after the Contractor recovers such funds from the Government; or(B)
Incur an obligation to pay a late payment interest penalty computed at the rate of interest established (ii) by the Secretary of the Treasury, and published in the , for interest payments under 41 U.Federal Register S.C. 7109 in effect at the time the Contractor accrues the obligation to pay an interest penalty;
. Notify the Contracting Officer upon-(5) Notice to Contracting Officer
Reduction of the amount of any subsequent certified application for payment; or(i)
Payment to the subcontractor of any withheld amounts of a progress payment, specifying-(ii)
The amounts withheld under paragraph (e)(1) of this clause; and(A)
The dates that such withholding began and ended; and(B)
. Be obligated to pay to the Government an amount equal to interest on the (6) Interest to Government withheld payments (computed in the manner provided in 31 U.S.C.3903(c)(1)), from the 8 thday after receipt of the withheld amounts from the Government until-
The day the identified subcontractor performance deficiency is corrected; or(i)
The date that any subsequent payment is reduced under paragraph (e)(5)(i) of this clause.(ii)
Third-party deficiency reports-(f)
. If a Contractor, after making payment to a first-tier subcontractor, (1) Withholding from subcontractor receives from a supplier or subcontractor of the first-tier subcontractor (hereafter referred to as a "second-tier subcontractor") a written notice in accordance with 40 U.S.C. 3133, asserting a deficiency in such first-tier subcontractor's performance under the contract for which the Contractor may be ultimately liable, and the Contractor determines that all or a portion of future payments otherwise due such first-tier subcontractor is subject to withholding in accordance with the subcontract agreement, the Contractor may, without incurring an obligation to pay an interest penalty under paragraph (e)(6) of this clause-
Furnish to the first-tier subcontractor a notice conforming to the standards of paragraph (g) of this (i) clause as soon as practicable upon making such determination; and
Withhold from the first-tier subcontractor's next available progress payment or payments an amount (ii) not to exceed the amount specified in the notice of withholding furnished under paragraph (f)(1)(i) of this clause.
. As soon as practicable, but not later than 7 days after receipt (2) Subsequent payment or interest charge of satisfactory written notification that the identified subcontract performance deficiency has been corrected, the Contractor shall-
Pay the amount withheld under paragraph (f)(1)(ii) of this clause to such first-tier subcontractor; or(i)
Incur an obligation to pay a late payment interest penalty to such first-tier subcontractor computed at (ii) the rate of interest established by the Secretary of the Treasury, and published in the , for Federal Register interest payments under 41 U.S.C. 7109 in effect at the time the Contractor accrues the obligation to pay an interest penalty.
. The Contractor shall issue a written notice of any (g) Written notice of subcontractor withholding withholding to a subcontractor (with a copy furnished to the Contracting Officer), specifying-
The amount to be withheld;(1)
The specific causes for the withholding under the terms of the subcontract; and(2)
The remedial actions to be taken by the subcontractor in order to receive payment of the amounts (3) withheld.
. The Contractor may not request payment from the Government (h) Subcontractor payment entitlement of any amount withheld or retained in accordance with paragraph (d) of this clause until such time as the Contractor has determined and certified to the Contracting Officer that the subcontractor is entitled to the payment of such amount.
. A dispute between the Contractor and subcontractor relating to the (i) Prime-subcontractor disputes amount or entitlement of a subcontractor to a payment or a late payment interest penalty under a clause included in the subcontract pursuant to paragraph (c) of this clause does not constitute a dispute to which the Government is a party. The Government may not be interpleaded in any judicial or administrative proceeding involving such a dispute.
. Except as provided in paragraph (i) of this clause, this (j) Preservation of prime-subcontractor rights clause shall not limit or impair any contractual, administrative, or judicial remedies otherwise available to the Contractor or a subcontractor in the event of a dispute involving late payment or nonpayment by the Contractor or deficient subcontract performance or nonperformance by a subcontractor.
. The Contractor's obligation to pay an interest (k) Non-recourse for prime contractor interest penalty penalty to a subcontractor pursuant to the clauses included in a subcontract under paragraph (c) of this clause shall not be construed to be an obligation of the Government for such interest penalty. A cost-reimbursement claim may not include any amount for reimbursement of such interest penalty.
. If the Contractor becomes aware of a duplicate contract financing or invoice payment (l) Overpayments or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-
Remit the overpayment amount to the payment office cited in the contract along with a description of (1) the overpayment including the-
Circumstances of the overpayment ( , duplicate payment, erroneous payment, liquidation errors, (i) e.g.
date(s) of overpayment);
Affected contract number and delivery order number if applicable;(ii)
Affected line item or subline item, if applicable; and(iii)
Contractor point of contact.(iv)
Provide a copy of the remittance and supporting documentation to the Contracting Officer.(2)
(End of clause)
52.236-26 Preconstruction Conference. (Feb 1995)
As prescribed in , insert the following clause:36.522
Preconstruction Conference (Feb 1995)
If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
(End of clause)
List of Contract Documents, Exhibits, or Attachments
The attachments table has changed from:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
01 PWS March 13 2025 Performance Work Statement 18 Dec 2024 27 Attachment No
Lead and Asbestos Survey - 05 Dec
LEAD AND ASBESTOS SURVEY 18 Dec 2024 Attachment No
Drawings HangarBuilding199
Drawings 14 Jan 2025 Attachment No
To:
Identifier Document Name Document Description Reference Identifier
Date Line Item Page Numbers
Document Type
Provided Under Separate Cover
01 PWS - 22 May 2025 Performance Work Statement 18 Dec 2024 27 Attachment No
Lead and Asbestos Survey - 05 Dec
LEAD AND ASBESTOS SURVEY 18 Dec 2024 165 Attachment No
Drawings HangarBuilding199
Drawings 14 Jan 2025 10 Attachment No
WD 2015-4491
REV 29
Wage Determination 22 May 2025 11 Attachment No
Base Environmental Guide - 18 Dec 2024
Supporting Technical Documentation 22 May 2025 60 Attachment No
Questions and Answer from Industry - 22 May
Questions and Answers from industry 22 May 2025 8 Attachment No
The following contract documents were added:
Base Environmental Guide - 18 Dec 2024 PWS - 22 May 2025 Questions and Answer from Industry - 22 May 2025
WD 2015-4491 REV 29
The following contract documents were deleted:
PWS March 13 2025
The following contract documents Page Counts were changed:
DOCUMENT PAGE COUNTS
DOCUMENT NAME FROM TO
WD 2015-4491 REV 29 none 11
Base Environmental Guide - 18 Dec 2024 none 60
Questions and Answer from Industry - 22 May 2025 none 8
Solicitation Provisions
Additional Information/Notes
The following clauses were deleted:
DFARS Clauses Incorporated by Reference
Number Title Effective Date Alternate/ Deviation
Variation Effective Date
252.226-7002 Representation for Demonstration Project for Contractors Employing Persons with Disabilities.
Dec 2019
Addendum to 52.212-1, Instructions to Offerors - Commercial Products and Commercial Services
Miscellaneous text in this section has been modified to:
ADDENDUM TO 52.212-1
Solicitation provision 52.212-1, Instruction to Offerors - Commercial Items, is tailored as follows:
Paragraph (b)(4), Submission of offers, is deleted.
Paragraph (b)(11), Submission of offers, is deleted.
Paragraph (c), Period for acceptance of offers, 30 calendar days is changed to 90 calendar days.
Paragraph (d), Product samples, is deleted.
Paragraph (g), Contract award, is deleted.
Paragraph (h), Multiple awards, is deleted.
Paragraph (i), Availability of requirements documents cited in the solicitation, is deleted.
The following paragraphs are added to provide specific instructions.
NOTE: In this solicitations "offer" and "offeror" are to be understood as "bid" and" bidder."
(m) Bid submittal and inquiries.
(1) Submission of Bid: See contract provision 52.214-5.
(2) Bonds: Bid Bond, Payment Bond, and Performance Bonds shall be required per contract clauses 52.228-1 and 52.228-16.
Site Visit: A site visit will be conducted at 10:00 AM on 14 MAY 2025. (3) Contractors will meet at 9:30 AM at the Pass & ID Visitor Center, 300 Davidson Drive, Savannah, GA 31408, and will be escorted to the main conference room in BLDG 302. Contractors will provide attendee names and company information no later than 1:00 PM on 12 MAY 2025, to Jack Waters at email address jack.waters@us.af.
mil. He can also be reached at (912) 966-8323 for other base access issues.
Bid opening will be conducted at 10:00AM on 18 June 2025, at the same location and (4) attendance procedures as specified for the site visit.
(5) Submission of bid: Submit all bids to the below address in time to arrive no later than 18 June 2025 @ 10:00am EST. An electronic copy of bids will be required 24 hours after bid opening to the below points of contact.
(6) Mailing address;
(7) ATTN: Contracting Office Tompkins/Smith
1401 Robert B. Miller Jr. Drive
Garden City Ga 31408
(6) Submit all questions to both Points of Contact listed below no later than 28 MAY 2025 :
(7) Points of Contact:
Jim Shuman Melvin F. Reid Jr.
Phone: 404-217-3908 Phone: 678-569-8432 james.e.shuman.civ@army.mil melvin.f.reid2.civ@army.mil
(n) Offer content.
(1) Invitation for Bids Documents: Offerors are required to submit a completed Standard Form (SF) 1449. Failure to follow the instructions below may cause your offer to be deemed unacceptable the Government. by
(i) SF 1449: This form must be fully completed and signed in block 20. The contractor shall amendments to the IFB in accordance with the instructions on the SF 1449 acknowledge any
(page 1of the SF30 amendment must be signed and return).
(ii) Price Schedule: Pricing shall Prices each unit price and be entered on the SF 1449. should show total amount for each line item. The offerors shall ensure the units prices are represented in two decimal positions only (example: $0.27, not 0.2745).
(iii) Representations and Certifications: The offerors shall ensure that they have completed their Online Representations and Certifications at SAM.gov.
(o) Protest Information:
NG Agency Protest Program is intended to encourage interested parties to seek resolution of their concerns with the National Guard (NG) as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum.
Contract award or performance is suspended during the protest to the same extent, and within the same time periods as if filed at the GAO. The NG protest decision goal is to resolve protests within 35 calendar days from filing. An agency protest may be filed with either the Contracting Officer or the NG Agency's Protest Decision Authority, but not both, in accordance with NG protest procedures.
To be timely, the protests must be filed with the periods specified in FAR 33.103. To file a protest under the NG Agency Protest Program, the protest must request resolution under that program and be sent to the address below:
National Guard Bureau
Office of the Director of Acquisitions/ Head of Contracting Activity
ATTN: NGB-AQ-O
111 S. George Mason Dr.
Arlington, VA 22204
Email:ng.ncr.ngb-arng.mbx.ngb-task-order-ombudsman@mail.mil
All other agency-level protests should be sent to the Contracting Officer for resolution at the address in the solicitation. See FAR clause 52.233-2.
(End of Addendum)
Addendum to Solicitation Provisions
Additional Information/Notes
The following clauses were modified:
52.228-1Bid Guarantee.Sep 1996 hereby reads as follows:
As prescribed in , insert a provision or clause substantially as follows:28.101-2
Bid Guarantee (Sept 1996)
Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, (a) may be cause for rejection of the bid.
The bidder shall furnish a bid guarantee in the form of a firm commitment, bid bond supported (b) e.g., by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
To unsuccessful bidders as soon as practicable after the opening of bids; and(1)
To the successful bidder upon execution of contractual documents and bonds (including any (2) necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
The amount of the bid guarantee shall be percent of the bid price or $ , whichever is (c) __20%__ __3M__ less.
If the successful bidder, upon acceptance of its bid by the Government within the period specified for (d) acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the (e) work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
The following clauses were deleted:
FAR Clauses Incorporated by Reference
Number Title Effective Date Alternate/ Deviation
Variation Effective Date
52.214-18 Preparation of Bids-Construction. Apr 1984 FAR Clauses Incorporated by Full Text 52.236-27 Site Visit (Construction). (Feb 1995)
As prescribed in , insert a provision substantially the same as the following:36.523
Site Visit (Construction) (Feb 1995)
The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions (a) Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
Site visits may be arranged during normal duty hours by contacting:(b)
Name: Melvin F. Reid
Address: ____ ____
Telephone: 6785698432
(End of Provision)
| IDCode: J |
| Page: 1 |
| Pages: 19 |
| AmendNo: 0001 |
| EffDate: 22 MAY 2025 |
| ReqNo: |
| ProjNo: |
| IssCode: W50S70 |
| AdmCode: |
| IssuedBy: W7M3 USPFO ACTIVITY GAANG 165 |
KO FOR GAANG DO NOT DELETE, 1401 ROBERT B MILLER JR DR
GARDEN CITY, GA 31408-9001
UNITED STATES
MELVIN REID, EMAIL: MELVIN.F.REID2.CIV@ARMY.MIL TELEPHONE: (678) 569-8432
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W50S7025BA001 |
| SolDate: 07 MAY 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE CONTINUATION |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: THIS MODIFICATION IS CREATED TO UPDATE THE PWS TO VERSION 2. IT ALSO POST QUESTIONS AND ANSWERS FOR THE SOLICITATION. IT EXTENDS THE Q&A PERIOD. |
| ContNameTitle: |
| CoNameTitle: |
| ContDate: |
| CODate: |