RFI Question and Answers for Bldg. 102,110, 1-11.pdf
PDF 145 KB Posted
- Attached to
- Paint and Lights Bldg 102 & Bldg 110
- Solicitation number
- W50S6T26QA027
- Issued by
-
Department of the Army National Guard
About this file
This file is a Request for Information (RFI) response document for federal contract W50S6T26QA026 addressing painting and lighting work for Buildings 102 and 110, current as of July 15, 2026.
The RFI responses clarify specifications for two primary work areas. For painting: Building 102 requires durable industrial-grade paint with semi-gloss or gloss finish for high-traffic areas in the shop (two colors) and low-volatile organic compound paint with eggshell or satin finish in the office (one color); Building 110 requires similar specifications with garage doors to be painted the same color scheme as shop walls. Bathroom walls in Building 102 are included in square footage calculations. Specific paint brand preferences are pending review, and contractors should assume appropriate paint types meeting the Statement of Work and list assumptions on quotes. For lighting: all fixtures operate at 120 volts and consist of approximately 4-foot fluorescent T8 standard tube lights, with approximately 18 fixtures containing 3 bulbs each in Building 102; contractors are responsible for verifying exact quantities, lengths, and types during site inspection and documenting assumptions on quotes. Government employees will relocate all furniture and wall items prior to work. The garage doors in Building 110 are confirmed as metal surfaces requiring paint.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI responses for Project:
W50S6T26QA026 – Paint and Lights Bldg. 102 & Bldg. 110, Questions 1 - 11
Current as of: 15 July 2026
QUESTION ANSWER
Bldg. 102 & 110
1. The Specs ask for durable, industrial grade w semi-gloss or gloss finish for high traffic environment, could you please provide a list of preferred manufacturers.
Specification details and brand example are still being reviewed. A post update may follow. If not provide, paint that will satisfy the SOW should be assumed and provide the assumed paint brand/type on/with your quote.
2. Please provide specs and/or please provide wattage for the LED lights. All lights are 120 volts.
3. Please confirm all fixtures are 4’ fluorescent fixtures with a T8 standard tube light in both Bldg.
102 & 110. If not, please provide.
Contractors had a chance to verify length of bulb during walk through. Provide assumed quantities, length, type to satisfy the SOW and list that assumption on/with your quote.
4. Please provide specs, tube light wattage, and count of how many fixtures are in the Office Bldg 102 (they were covered), and the Shop building 110.
Approximately 18 fixtures with 3 bulbs each.
Contractor to verify.
5. Please confirm everything will be moved by Gov’t employees, including all furniture and wall items.
Yes.
Bldg. 102 Shop / Office
6. In Bldg.102, Office, the specs ask for low-volatile organic compound paint with eggshell or satin finish, could you please provide a list of preferred manufacturers.
See 1 above.
7. In Bldg. 102 Shop, please confirm whether only one color will be used.
In the office space yes. In the shop areas two colors.
8. In Bldg. 102 Office, will there be 1 or 2 colors used, and specifics?
In the office space yes. In the shop areas two colors
9. In Bldg. 102, are the bathroom walls included in the square footage? Please provide if not. Included.
Bldg. 110
10. Bldg. 110, Please clarify – Since garage doors are not walls, are they to be painted, or are
Yes. Garage doors are to be painted same color scheme as the shop walls.
RFI responses for Project:
W50S6T26QA026 – Paint and Lights Bldg. 102 & Bldg. 110, Questions 1 - 11
Current as of: 15 July 2026 they not? If so, what are the specs for the paint and color? Are the garage doors included in the wall’s square footage? If not, please provide.
11. Bldg. 110, Please confirm if the garage doors are metal? Yes.