FAKZ182353 Addendum No. 1 SIGNED.pdf
PDF 7 MB Posted
- Attached to
- Renovation of Building 1407 to AGE
- Solicitation number
- W50S6N-23-B-0005
About this file
This is a solicitation for the renovation of Building 1407 to accommodate aircraft ground equipment (AGE) at Dannelly Field in Montgomery, Alabama. The solicitation is issued by the Department of the Army Alabama Army National Guard. It seeks offers for construction services to convert the building, including installing an epoxy floor system, replacing exterior roll up doors, and renovating bathrooms. The closing date for proposals is not provided in the document. The solicitation includes specifications for high-performance coatings, bid options, toilet accessories, and resilient tile flooring.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: 31 July 2023
To: Mr. Stephen Shanks
Subject: ADDENDUM NO. 1
Project: F-35: CONVERT BUILDING 1407 FOR AGE
Job #: ANG# FAKZ182353 / SSL# 18074
From: David Donovan
The plans and Specifications for the F-35 – Convert Building 1407 for AGE, dated February 2023 are amended as follows. (Where there are conflicts between the plans and specifications and the addendum, this addendum shall govern).
Item No. 1: Refer to specifications. Delete specification section 09 9600 “High
Performance Coatings” and replace it with the attached specification section 09 9600 with a revised date of 14 July 2023. Additions to the specification are noted in bold/italicized text and deletions are noted with strikethrough text. Revisions included, but are not limited to, the following:
- Remove references to matte finish.
- Add satin gloss finish.
- Add moisture resistant epoxy resin primer and revise calcium chloride and relative humidity testing limitations.
Item No. 2: Refer to specifications. Delete specification section 01 2300 “Bid
Options” and replace it with the attached specification section 01 2300 with a revised date of 14 July 2023. Additions to the specification are noted in bold/italicized text and deletions are noted with strikethrough text. Revisions included, but are not limited to, the following:
- Modify extents of high-performance coating in Bid Option 3 to match finish schedule and bid option floor pattern plan.
- Modify base bid description of floor finish if bid option is not awarded in bid option #5 to match finish schedule and base bid floor pattern plan.
F-35: CONVERT BUILDING 1407 FOR AGE FAKZ182353
ADDENDUM NO. 1 Page 2 of 4 Seay Seay & Litchfield, P.C. 31 July 2023
Item No. 3: Refer to specifications. Delete specification section 10 2800 “Toilet, Bath, and Laundry Accessories” and replace it with the attached specification section 10 2800 with a revised date of 14 July 2023. Additions to the specification are noted in bold/italicized text and deletions are noted with strikethrough text. Revisions included, but are not limited to, the following:
- Replace scheduled toilet paper dispenser, paper towel dispenser, and soap dispenser.
Item No. 4: Refer to drawings. Delete drawing sheet A3.1 “Finish Schedule” and replace it with the attached drawings sheet A3.1 with a revised date of 20 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Revise extents of polished/dyed concrete floor finish.
- Add luxury vinyl tile floor finish to various spaces.
- Add luxury vinyl tile floor finish to legend.
Item No. 5: Refer to drawings. Delete drawing sheet A9.1 “Floor Pattern Plan – Base
Bid” and replace it with the attached drawings sheet A9.1 with a revised date of 20 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Revise extent of polished/dyed concrete floor finish.
- Add luxury vinyl tile floor finish to various spaces.
Item No. 6: Refer to drawings. Delete drawing sheet A9.2 “Floor Pattern Plan – Bid
Option” and replace it with the attached drawings sheet A9.2 with a revised date of 20 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Delete polished/dyed concrete floor finish.
- Add luxury vinyl tile floor finish to various spaces.
- Correct legend to accurately depict restroom floor tile intended to be installed.
Item No. 7: Refer to specifications. Add the attached specification section 09 6519
“Resilient Tile Flooring” with a revised date of 14 July 2023 to the project specifications.
Item No. 8: Refer to drawings. Delete drawing sheet ED1.1 “Electrical Demolition
Plan” and replace it with the attached drawings sheet ED1.1 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Revise to accurately reflect location of ADVANTOR panel.
- Added notes to remove existing Fire Alarm / Mass Notification
Panel.
ADDENDUM NO. 1 Page 3 of 4 Seay Seay & Litchfield, P.C. 31 July 2023
Item No. 9: Refer to drawings. Delete drawing sheet E3.1 “Power Plan – Area A” and replace it with the attached drawings sheet E3.1 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Removed note regarding ADVANTOR panel in drawing 3.
Item No. 10: Refer to drawings. Delete drawing sheet E3.3 “Power Plan – Area C” and replace it with the attached drawings sheet E3.3 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Added ADVANTOR panel with note and circuit information within General Purpose Equipment and Repair Bay.
Item No. 11: Refer to drawings. Delete drawing sheet E4.1 “Auxiliary Plan” and replace it with the attached drawings sheet E4.1 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Added ADVANTOR panel within General Purpose Equipment and Repair Bay with note regarding maintaining telecommunications service to panel.
Item No. 12: Refer to drawings. Delete drawing sheet P1.3 “Plumbing Plan – New
Work – Waste & Air” and replace it with the attached drawings sheet P1.3 with a revised date of 10 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Add condensate drain line to hub drain for MSAHU-1.
- Add condensate pump, condensate drain line, and hub drain for
AHU-5.
Item No. 13: Refer to drawings. Delete drawing sheet P1.6 “Waste and Vent Riser
Diagram” and replace it with the attached drawings sheet P1.6 with a revised date of 10 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Add condensate drain line to hub drain for MSAHU-1.
- Add condensate pump, condensate drain line, and hub drain for
AHU-5.
Item No. 14: Refer to drawings. Delete drawing sheet M2.2 “Mechanical New Work
Floor Plan – Area B” and replace it with the attached drawings sheet M2.2 with a revised date of 10 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Delete drywell and revise condensate drain line to route to hub drain in room 106 for MSAHU-1.
- Revise sheet note 7.
ADDENDUM NO. 1 Page 4 of 4 Seay Seay & Litchfield, P.C. 31 July 2023
Item No. 15: Refer to drawings. Delete drawing sheet M2.3 “Mechanical New Work
Floor Plan – Area C” and replace it with the attached drawings sheet M2.3 with a revised date of 10 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Delete drywell and revise condensate drain line to route to hub drain in room 112 for AHU-5.
- Revise sheet notes 11 and 12.
Item No. 16: Refer to drawings. Delete drawing sheet M6.2 “Mechanical Schedules” and replace it with the attached drawings sheet M6.2 with a revised date of 10 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Revise MSAHU-1 to include manufacturer’s condensate pump.
Item No. 16: Refer to drawings. Delete drawing sheet E0.2 “Lighting Fixture Schedule
& General Notes” and replace it with the attached drawings sheet E0.2 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Fixture type EH and XE added to fixture schedule.
Item No. 17: Refer to drawings. Delete drawing sheet E1.1 “Site Electrical Plan” and replace it with the attached drawings sheet E1.1 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Remove note 6 regarding site sync lighting controls.
Item No. 18: Refer to drawings. Delete drawing sheet E2.1 “Lighting Plan” and replace it with the attached drawings sheet E2.1 with a revised date of 19 July 2023. Revisions to the drawing are clouded in the revised drawing and include, but are not limited to, the following:
- Change exit sign and emergency light designation in rooms 131 and 134.
- Add keyed note 7 to legend and rooms 131/134.
End of Addendum #1
F-35: Convert Bldg 1407 for AGE Facility FAKZ182353/18074 February 2023 187th Fighter Wing, Dannelly Field, ANG, Type B3 (100% Submittal) Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 1
SECTION 099600 - HIGH-PERFORMANCE COATINGS
PART 1 GENERAL
1.01 1.01 SECTION INCLUDES
A. High performance coatings where noted on the drawings.
B. Moisture resistant epoxy resin primer. (Added by Addendum No. 1)
C. Special preparation of surfaces.
D. Materials included in this section shall meet the requirements for High Performance Sustainable Buildings for New Construction points for the following Sections:
1. 2-5.3.2 - Reduce Volatile Organic Compounds (VOC) Low-Emitting Materials
2. The contractor is expected to understand the HPSB requirements for these sections and include all applicable overhead in their base bid for the necessary documentation to achieve the above listed credits.
1.02 RELATED REQUIREMENTS
A. Section 01 2300 - Bid Options.
B. Section 01 3325 - Project Sustainability Summary
C. Section 01 3329 - Sustainable Design Reporting
D. Section 01 6000 - Product Requirements
E. Section 01 7419 - Construction Waste Management and Disposal
F. Section 01 6116 - Volatile Organic Compound (VOC) Content Restrictions.
G. Section 09 9000 - Painting and Coating.
1.03 REFERENCE STANDARDS
A. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials; 2010.
B. SSPC-SP 2 - Hand Tool Cleaning; Society for Protective Coatings; 1982 (Ed. 2004).
C. SSPC-SP 3 - Power Tool Cleaning; Society for Protective Coatings; 1982 (Ed. 2004).
D. ASTM Standards
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 2
1. ASTM C 307 - Standard Test Method for Tensile Strength of Chemical-Resistant Mortar, Grouts, and Monolithic Surfacings.
2. ASTM C 579 - Standard Test Methods for Compressive Strength of Chemical- Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes.
3. ASTM C 580 - Standard Test Method for Flexural Strength and Modulus of Elasticity of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes.
4. ASTM D 635 - Standard Test Method for Rate of Burning and/or Extent and Time of Burning of Plastics in a Horizontal Position.
5. ASTM D 3960 - Standard Practice for Determining Volatile Organic Compound (VOC) Content of Paints and Related Coatings.
6. ASTM D 4226 - Standard Test Methods for Impact Resistance of Rigid Poly(Vinyl Chloride) (PVC) Building Products.
7. ASTM D 4541 - Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers.
8. ASTM F 1869 - Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride.
9. ASTM F 2170 - Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes.
10. ASTM G 21 - Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi.
E. National Floor Safety Institute (NFSI)
1. ANSI/NFSI B101.1 - Test Method for Measuring Wet SCOF of Common Hard- Surface Floor Materials.
1.04 SUBMITTALS
A. See Section 01 3001 - Submittals for Submittal procedures.
B. Product Data:
1. Manufacturer's data sheets on each product to be used, including properties, VOC content, wet static coefficient of friction, compressive strength, tensile strength, elongation and similar properties.
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 3
2. Preparation instructions and recommendations.
3. Storage and handling requirements and recommendations.
4. Typical installation methods.
C. Manufacturer's Installation Instructions: Indicate special procedures, perimeter conditions requiring special attention, and recommended cleaning procedures for preparing existing concrete floor slabs to receive new coating. .
D. Sample: Provide 12" x 12" sample of proposed epoxy floor finish to the Government for approval of color and gloss level.
E. Maintenance Data: Include cleaning procedures and repair and patching techniques.
F. Maintenance Materials: Furnish the following for the Government's use in maintenance of project.
1. Extra Coating Materials: 1 gallon (4 liters) of each type and color.
2. Label each container with manufacturer's name, product number, color number, and room names and numbers where used.
G. Sustainability Submittals, Product data for HPSB Compliance:
1. For products containing VOCs, documentation (material safety data sheets (MSDS), third-party certificates, or test reports) showing printed statement of VOC content.
2. VOC Content Limitations: For the specified products, submit documentation of conformance with Specification Section 01 6116 - Volatile Organic Compound (VOC) Content Restrictions.
1.05 QUALITY ASSURANCE
A. Maintain one copy of each referenced document that applies to application on site.
B. Manufacturer Qualifications: Company specializing in manufacturing the Products specified in this section with minimum three years documented experience.
C. Applicator Qualifications: Company specializing in performing the work of this section with minimum 3 years documented experience.
D. Source Limitations: Provide each type of product from a single manufacturing source to ensure uniformity.
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 4
1.06 MOCK-UP
A. Provide mock-up, 10 feet long by 10 feet wide, illustrating color and sheen for each specified coating.
B. Locate where directed.
C. Mock-up may remain as part of the Work.
1.07 FIELD CONDITIONS
A. Apply flooring system under the following ambient conditions.
1. Ambient and Concrete Floor Temperatures: Between 40 and 85 degrees F (4 and 29 degrees C).
2. Material Temperature: Between 50 and 80 degrees F (10 and 27 degrees C).
3. Relative Humidity: Maximum 80 percent.
4. Dew Point: Floor temperature more than 5 degrees over dew point.
B. Provide lighting level of 80 ft candles (860 lx) measured mid-height at substrate surface.
C. Restrict traffic from area where coating is being applied or is curing.
D. Do not apply flooring system under ambient conditions outside manufacturer’s limits.
1.08 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Correct defective Work within a five year period after Date of Beneficial Occupancy.
C. Warranty: Include coverage for bond to substrate and degradation of chemical resistance.
PART 2 PRODUCTS
2.01 HIGH-PERFORMANCE COATINGS
A. Provide coating systems that meet the following minimum performance criteria, unless more stringent criteria are specified:
1. Abrasion Resistance: 18 mg loss, when tested in accordance with ASTM D4060.
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 5
B. Moderate Exposure: All minimum criteria, plus:
2.02 MATERIALS
A. Coatings - General: Provide complete multi-coat systems formulated and recommended by manufacturer for the applications indicated, in the thicknesses indicated; number of coats specified does not include primer or filler coat.
B. Polyurethane Floor Coating: Three coats, moisture cure polyurethane, non-skid finish, matte finish. (Deleted by Addendum No. 1)
1. Product characteristics:
a. Percentage of solids by weight (ASTM D2369): 99.35 - Part A; 59.23 - Part B, 100 - Part C, minimum.
b. Dry film thickness, per coat: 3.0, minimum.
c. VOC Content per ASTM D3960 (Mixed): 86 g/L maximum A+B+C
d. Abrasion Resistance: mg loss ASTM D4060 = 18.0
e. Coefficient of Friction ASTM D2047 = 0.63
f. Tension Strength (psi) Resin Only - ASTM C2370= 6,250
2. Chemical Resistance Properties:
a. Product shall have excellent resistant (in both 1 day and 7 day tests) to the following materials:
1) Acids (Inorganic): 10% Hydrochloric Acid, 30% Hydrochloric Acid, 10% Nitric Acid, 37% Sulfuric Acid,
2) Acids (Organic): 10% Acetic Acid, 10% Citric Acid, Oleic Acid,
3) Alkalies: 10% Ammonium Hydroxide, 50% Sodium Hydroxide,
4) Solvents(Alcohols): Ethylene Glycol (Antifreeze), Isopropyl Alcohol, Methanol
5) Solvents (Aliphatic:) d-Limonene, Jet Fuel (JP-4), Gasoline, Mineral Spirits
6) Solvents (Aromatic) Xylene
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 6
7) Solvents (Ketones & Esters): Methyl Ethyl Ketone, Propylene Glycol Methyl, Ether Acetate
8) Miscellaneous: 20% Ammonium Nitrate, Chemicals Brake Fluid, Bleach, Motor Oil (SAE30), Skydrol® 500B, Skydrol® LD4, 20% Sodium Chloride, 1% Tide® Laundry Soap, 10% Trisodium Phosphate
3. Primer for concrete: Two component epoxy primer as recommended by the coating manufacturer. (Deleted by Addendum No. 1)
4. Colorant: Provide manufacturer's standard colorant for selected finished color.
5. Gloss: Satin (Added by Addendum No. 1)
6. Traction Grit: Provide aluminum oxide grit materials as recommended by the manufacturer.
7. Cleaners & Related Products: Provide Industrial Grease Remover, detergents, cleaners, and etchants as recommended by the manufacturer for applications indicated on the contract documents.
C. Epoxy Resin Base Coat / Primer (Added by Addendum No. 1)
1. Contractor shall provide and install 2-part epoxy resin primer as reccommended by the top coat manufacturer to ensure a successful and warrantable installation of specified topcoat.
2. Epoxy resin primer shall be designed and installed as recommended by the manufacturer to be moisture insensitive to 15lbs (as measured by ASTM F1869) or less up to 97% relative humidity (as measured by ASTM F2170). Refer to
3.01 below for slab moisture testing requirements.
3. Notify Contracting Officer prior to proceeding if slab moisture levels exceed 15lbs or 97% relative humidity.
4. Install epoxy resin primer as required to be moisture insensitive to 15 lbs or 97% relative humidity even if test results suggest moisture levels are below thresholds for alternative (less moisture insensitive) primer systems.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine concrete surfaces to receive flooring system. Verify concrete is structurally sound.
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 7
B. Moisture Testing of Concrete: Perform at least one of the following two tests to determine moisture in concrete. Type of test and frequency as recommended by manufacturer and installer.
1. Calcium Chloride Test:
a. Measure moisture vapor emission rate of concrete in accordance with ASTM F 1869.
b. Application of flooring system shall start only if test results are below 12 pounds per 1,000 sq.ft (1.5kg/93 sq.m) over a 24-hour period.(Deleted by Addendum No. 1)
c. Application of flooring system shall start only if test results are below 15 pounds per 1,000 sq.ft over a 24-hour period. (Added by Addendum No. 1)
d. If test results are above limits, notify Architect and flooring manufacturer in writing.
2. In-situ Probe Test:
a. Measure relative humidity in concrete in accordance with ASTM F 2170.
b. Application of flooring system shall start only if test results are below 85 percent relative concrete humidity. (Deleted by Addendum No. 1)
c. Application of flooring system shall start only if test results are below 97 percent relative concrete humidity. (Added by Addendum No. 1)
d. If test results are above limits, notify Architect and flooring manufacturer in writing.
C. Do not begin preparation or installation until satisfactory moisture test results are achieved. Provide flooring manufacturer's recommended moisture vapor control coating if required. epoxy resin base coat / primer as specified in part 2 above.
(Modified by Addendum No. 1)
3.02 PREPARATION
A. Clean surfaces thoroughly prior to installation.
B. Protection of In-Place Conditions: Protect adjacent surfaces and adjoining walls from contact with flooring system materials.
C. Surface Preparation:
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 8
1. Prepare concrete surface in accordance with manufacturer’s instructions.
2. Remove dirt, dust, debris, oil, grease, curing agents, bond breakers, paint, coatings, sealers, silicones, and other surface contaminants which could adversely affect application of flooring system.
3. Steel shot blast concrete to a minimum surface profile of ICRI 310.2R, CSP 5.
4. Key-cut termination points with 1/4-inch (6-mm) by 1/4-inch (6-mm) cut.
5. Patch depressions, divots, and cracks in concrete in accordance with manufacturer’s instructions.
6. Mechanically remove loose, delaminated, and damaged concrete and repair in accordance with manufacturer’s instructions.
7. Joints: Fill joints in accordance with manufacturer’s instructions.
3.03 INSTALLATION
A. Install flooring system in accordance with manufacturer’s instructions and approved submittals at locations indicated on the Drawings.
B. Ensure concrete is dry, clean, and prepared in accordance with manufacturer’s instructions.
C. Allow concrete to cure a minimum of 7 days before applying flooring system.
D. Mixing:
1. Mix material components together in accordance with manufacturer’s instructions.
2. Mix only enough material that can be applied within working time.
3. Add and mix colorants with materials in accordance with manufacturer’s instructions to achieve uniform color.
E. Apply flooring system materials to obtain consistent mil thickness and smooth, uniform appearance and texture.
F. Overlay: Apply overlay in accordance with manufacturer’s instructions. Apply overlay to prepared concrete surface.
G. Traction Aggregate: Broadcast traction aggregate in accordance with manufacturer’s instructions. Broadcast traction aggregate into wet overlay.
Montgomery, AL Revised 14 July 2023
HIGH-PERFORMANCE COATINGS 099600 - 9
H. Cove:
1. Apply cove primer and cove in accordance with manufacturer’s instructions at locations indicated on the Drawings.
2. Apply cove to height and shape as indicated on the Drawings.
3. Apply cove to create seamless, smooth transition between flooring and walls.
I. Seal Coat:
1. Apply seal coat in accordance with manufacturer’s instructions.
2. Apply seal coat over traction aggregate.
3.04 FIELD QUALITY CONTROL
A. Field Inspection: Coordinate field inspection in accordance with appropriate sections in Division 01.
B. Manufacturer’s Services: Coordinate manufacturer’s services in accordance with appropriate sections in Division 01.
3.05 CLEANING AND PROTECTION
A. Allow flooring system to dry in accordance with manufacturer’s instructions before opening to traffic.
B. Allow flooring system to dry a minimum of 1 week before cleaning by mechanical means.
C. Protect completed flooring system from damage during construction.
END OF SECTION
This page intentionally left blank
Montgomery, AL Revised 14 July 2023
BID OPTIONS 012300 - 1
SECTION 012300 - BID OPTIONS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Description of Bid Options .
B. Procedures for pricing Bid Options .
1.02 ACCEPTANCE OF Bid Options
A. Bid Options quoted on Bid Forms will be reviewed and accepted or rejected at the Government's option in accordance with the requirements of the Contract Documents.
Accepted Bid Options will be identified in the Construction Contract.
B. Coordinate related work and modify surrounding work to integrate the Work of each Bid Option .
1.03 SUMMARY
A. Definition: A Bid Option is an amount proposed by Bidders and stated on the Bid Form for certain construction activities defined in the Bidding Requirements that may be added to the Base Bid amount if the the Government decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems or installation methods described in Contract Documents. The Base Bid is all items shown on the the Contract Documents except items to be added back by below schedule of Bid Options.
B. Coordination: Coordinate related Work and modify or adjust adjacent Work as necessary to ensure that Work affected by each accepted Bid Option is complete and fully integrated into the project.
C. Schedule: A "Schedule of Bid Options" is included at the end of this Section.
Specification Sections referenced in the Schedule contain requirements for materials and methods necessary to achieve the Work described under each Bid Option.
D. Include as part of each Bid Option, miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation whether or not mentioned as part of the Bid Option.
Montgomery, AL Revised 14 July 2023
BID OPTIONS 012300 - 2
1.04 SCHEDULE OF Bid Options
A. Bid Option Item No. 1 (Additive): Wash Rack
1. This Bid Option shall include all plant, labor, and material for the following scope of work:
a. Remove and replace existing concrete pavement on the East side of the facility with the elevations/slopes indicated as required to create a new exterior wash rack for washing of AGE equipment.
b. Installation of new catch basin at the wash rack location and installation of new sub-grade piping required to connect the catch basin to the new oil/water separator indicated on the drawings.
c. If this Bid Option is not awarded, the existing cement concrete paving in the wash rack area will remain without change. No catch basin, underground piping, or overhead protection will be required. The oil/water separator indicated on the civil drawings shall be included within the scope of the base bid.
B. Bid Option Item No. 2 (Additive): Recover Roof:
1. This Bid Option shall include all plant, labor, and material for the following scope of work:
a. Installation of a new thermoplastic membrane roofing system as indicated on the drawings and specified in section 07 5400 over the entire facility.
b. If this Bid Option is awarded, the existing roof membrane shall remain in place. New cover board and new thermoplastic membrane roofing system will be applied over the new coverboard/existing roof assembly as indicated on the drawings. Removal of the existing roofing assembly is not required as a part of this Bid Option.
c. Also included within the scope of this bid option is removal of the existing lightning protection system and installation of a new UFC 3-575-01 compliant lighting protection system as indicated on the drawings. Bid Option shall include all testing and certification required by UFC 3-575-01, AFI 32-0165, and NFPA 780.
d. If this Bid Option is not awarded, the existing roofing systems and lightning protection systems shall remain without change. Contractor shall include in the base bid any patching and repairing of existing roofing systems that is
Montgomery, AL Revised 14 July 2023
BID OPTIONS 012300 - 3
required to coordinate with new roof penetrations and roof mounted equipment indicated on the drawings
C. Bid Option No. 3 (Additive): Epoxy Floor System:
1. This Bid Option shall include all plant, labor, and material required for the installation of high performance floor coatings in General Purpose Equipment and Repair Bay and Tool Room, Rooms 129 and 130, General Purpose Equpiment & Repair Room, Tool Crib, and Battery Shop & Storage, rooms 129, 130, and 134 in accordance with specification section 09 9600 - High Performance Coatings.
(Modified by Addendum No. 1)
2. If this Option is not awarded, the Base Bid shall include installation of Sealed Concrete Finish as specified in Section 09 9000 in these spaces.
D. Bid Option Item No. 4 (Additive): Replace Exterior Roll Up Doors:
1. This Bid Option shall include all plant, labor, and material for the following scope of work:
a. Removal and replacement of existing exterior roll up doors with new electrically operated and insulated coiling overhead doors as indicated on the drawings and specified in specification section 08 3323. Design intent is that the existing hollow metal frames at each existing opening shall remain.
Contractor shall include all cost associated with removing existing overhead coiling door channel frame from existing frame to remain. Existing frame to remain shall be patched, ground smooth, and painted. If required for successful installation of new overhead coiling door assemblies, the Contractor shall include the cost to remove and replace the existing hollow metal frames within this Bid Option.
b. If this Bid Option is not awarded, the existing overhead coiling doors will remain. Contractor shall include, as part of the base bid, all cost to scrape, sand, and re-paint existing coiling doors and frames intended to remain.
c. The Contractor shall also include in the base bid the cost to install new overhead door assembly in room 107 as indicated on the drawings.
E. Bid Option No. 5 (Additive): Bathroom Tile:
1. This Bid Option shall include all plant, labor, and material for the following scope of work :
Montgomery, AL Revised 14 July 2023
BID OPTIONS 012300 - 4
a. Installation of hard tile floor finishes in rooms 112 and 113 in lieu of sealed concrete flooring as indicated on the drawings.
b. Increased extent of hard tile wall applications in rooms 112 and 113 as indicated on drawing sheets A6.1, A6.2, and A6.3.
c. If the bid option is awarded, hard tile shall be installed in accordance with specification section 09 3000.
d. If the bid option is not awarded, the base bid shall consist of sealed polised and dyed concrete flooring and painted CMU walls in rooms 112 and 113.
Base bid shall include hard tile at shower applications as indicated n drawing sheets A6.1, A6.2, and A6.3. (Modified by Addendum No. 1)
F. Bid Option No. 6 (Additive): Telecommunications Systems Structured Cabling
1. This Bid Option shall include all plant, labor, and material for the following scope of work:
a. Provide and install new telecommunications systems wiring, devices, equipment, etc... as indicated on the drawings and specified in Division 27.
b. If this Bid Option is not awarded, Contractor to provide, within the base bid, all raceway, cable tray, sleeves, etc... required telecommunications system wiring. If the Bid Option is not awarded, installation of all cabling, outlet devices, racks, equipment, etc... indicated by the drawings will be provided by the Government following beneficial occupancy.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 1
SECTION 102800 - TOILET, BATH, AND LAUNDRY ACCESSORIES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Commercial toilet accessories.
B. Accessories for toilet rooms and utility rooms .
C. Grab bars.
1.02 RELATED REQUIREMENTS
A. Section 093000 - Tiling: Ceramic washroom accessories.
B. Section 10 2113 - Stainless Steel Toilet Compartments
1.03 REFERENCE STANDARDS
A. ADA Standards - Americans with Disabilities Act (ADA) Standards for Accessible Design 2010.
B. ASTM A269/A269M - Standard Specification for Seamless and Welded Austenitic Stainless Steel Tubing for General Service 2015a (Reapproved 2019).
C. ASTM A653/A653M - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process 2020.
D. ASTM A666 - Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel Sheet, Strip, Plate, and Flat Bar 2015.
E. ASTM B456 - Standard Specification for Electrodeposited Coatings of Copper Plus Nickel Plus Chromium and Nickel Plus Chromium 2017.
F. GSA CID A-A-3002 - Mirrors, Glass; U.S. General Services Administration ; 1996.
1.04 ADMINISTRATIVE REQUIREMENTS
A. Coordinate the work with the placement of internal wall reinforcement, concealed ceiling supports, and reinforcement of toilet partitions to receive anchor attachments.
1.05 SUBMITTALS
A. See Section 01 3001 - Submittals for Submittal procedures.
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 2
B. Product Data: Submit data on accessories describing size, finish, details of function, and attachment methods.
C. Manufacturer's Installation Instructions: Indicate special procedures and conditions requiring special attention.
PART 2 PRODUCTS
2.01 MATERIALS
A. Accessories - General: Shop assembled, free of dents and scratches and packaged complete with anchors and fittings, steel anchor plates, adapters, and anchor components for installation.
1. Grind welded joints smooth.
2. Fabricate units made of metal sheet of seamless sheets, with flat surfaces.
B. Keys: Provide keys for each accessory to the Contracting Officer Representative;
master key lockable accessories.
C. Stainless Steel Sheet: ASTM A666, Type 304.
D. Stainless Steel Tubing: ASTM A269/A269M, Grade TP304 or TP316.
E. Galvanized Sheet Steel: Hot-dipped galvanized steel sheet, ASTM A653/A653M, with G90/Z275 coating.
F. Adhesive: Two component epoxy type, waterproof.
G. Fasteners, Screws, and Bolts: Hot dip galvanized; tamper-proof; security type.
H. Expansion Shields: Fiber, lead, or rubber as recommended by accessory manufacturer for component and substrate.
2.02 FINISHES
A. Stainless Steel: Satin finish, unless otherwise noted.
B. Chrome/Nickel Plating: ASTM B456, SC 2, polished finish, unless otherwise noted.
C. Baked Enamel: Pretreat to clean condition, apply one coat primer and minimum two coats epoxy baked enamel.
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 3
2.03 TOILET ACCESSORIES:
A. Surface Mounted Towel Dispenser/ Waste Receptacle: MODIFIED BY ADDENDUM #1.
1. Cabinet — 18-8, type-304, heavy-gauge stainless steel. All-welded construction.
Exposed satin finish. Equipped with a tumbler lock.
2. Flange: 18-8, Type 304, 22-guage stainless steel, satin finish. Drawn and beveled, one-piece, seamless construction.
3. Skit: 18-8, Type 304, 22-guage stainless steel with satin finish.
4. Door: 18-8, Type 304, 20-gauge (0.9mm) stainless steel with satin-finish. Drawn, one-piece, seamless construction. Secured to cabinet with a full-length stainless steel piano-hinge. Equipped with a concealed tumbler lock.
5. Touch-Free Roll Towel Mechanism — Durable, high-impact resin materials.
Accepts standard-core rolls up to 8" (205mm) wide, 8" (205mm) diameter. 800 ft (244mm) long. Dispenses one 12" (300mm) length of towel paper per pull.
6. Door: 18-8, type-304, 18-gauge (1.2mm) stainless steel with satin finish. 9/16" (14mm) 90° return for maximum rigidity. Secured to cabinet with a full-length stainless steel piano-hinge. Equipped with a tumbler lock keyed like other washroom accessories.
7. Waste Receptacle — 18-8 Type 304, 22-gauge (0.8mm) stainless steel with satin finish. Front and sides of bottom and all top edges are hemmed for safe handling.
Secured to cabinet with a tumbler lock keyed like other Bobrick washroom accessories. Capacity: 12-gal. (45.5-L).
B. Toilet Paper Holder: MODIFIED BY ADDENDUM #1.
1. Door — 18-8, Type-304, 18-gauge (1.2mm) stainless steel with satin-finish.
Drawn, one-piece, seamless construction. Wide viewing slot reveals toilet tissue supply inside cabinet.
2. Cabinet — Surface-Mounted Twin Jumbo Roll Toilet Tissue Dispenser. 18-8, Type-304, 20-gauge (1.0mm) stainless steel with satin-finish. Equipped with a tumbler lock keyed like other washroom accessories.
3. Commercial Grade, High Capacity with lock.
4. Holds two rolls up to 9 inch diameter.
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 4
5. Size: 12.5 inches x 19.88 inches x 6 inches.
C. Electric Hand Dryer:
1. Electrical Characteristics:
a. Voltage: 120V
b. Standby Power Consumption: 0.5W
c. 1,000W digital brushless motor
d. Motor Switching Rate: 5,500 per second
e. Motor Speed 83,000 rpm
2. ADA Compliant Low Profile Configuration projecting less than 4" from face of wall.
3. Polycarbonate Fascia Construction:
4. Antibacterial Sprayed Nickel Coating Finish
5. Sealed HEPA filter constructed of glass fiber and fleece prelayer. Filter capable of removing 99.7% of bacteria, as small as 0.3 microns, including both bacteria and viruses.
6. Operation:
a. Touch free capacitive sensor activation
b. 12 second Hand dry time measurement based on NSF Proteocol P.335)
c. Sound Power Leve: 79dB(A)
d. Airspeed at Aperture: 420 mph
7. Manufacturer's 5 year parts and labor warranty.
D. L Shaped Grab Bar.
1. Grab Bar — 18-8, type-304, 18-gauge (1.2mm) stainless steel tubing with satin-finish. 1-1/4" (32mm) outside diameter. Ends are heliarc welded to concealed mounting flanges. Clearance between the grab bar and wall is 1-1/2" (38mm).
2. Concealed Mounting Flanges — 18-8, type-304, 11-gauge (3.2mm) thick, stainless steel plate; end flanges 2" x 3-1/8" (50 x 80mm) with holes for
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 5
attachment to wall. Intermediate flanges 2-5/8" x 3-1/8" (65 x 80mm) wide x 3-1/8" (80mm) diameter.
3. Snap Flange Covers — 18-8, type-304, 22-gauge (0.8mm) drawn stainless steel with satin-finish. 3-1/4" (85mm) diameter x 5/8" (16mm) deep. Each cover snaps over mounting flange to conceal mounting screws.
4. Strength - Bobrick grab bars that provide 1-1/2" (38mm) clearance from wall can support loads in excess of 900 pounds (408kg) if properly installed. Other grab bar configurations can support loads in excess of 250 pounds (113kg) if properly installed, complying with accessible design (including ADAAG in the U.S.A.) for structural strength.
E. Wall Mounted Soap Dispenser MODIFIED BY ADDENDUM #1.
1. Valve — Black molded plastic push button. Soap head-holding mushroom valve.
Stainless steel spring. U-packing seal and duckbill. Antibacterial-soap-resistant plastic cylinder.
2. Container — Body is 18-8, Type-304, 20-gauge (1.0mm) stainless steel with satin-finish. Drawn, one-piece, seamless construction. Front has same degree of arc as other washroom accessories. Radius on corners and edges complement other accessories. Back plate is 22-gauge (0.8mm) stainless steel with 20-gauge (1.0mm) stainless steel mounting bracket attached. Container body and back plate are epoxy-sealed to prevent warping and leakage. Concealed wall plate is 20-gauge (1.0mm) stainless steel. Equipped with a plastic soap refill-indicator window and a locked, hinged stainless steel lid for top filling. Capacity: 40-fl oz (1.2-L)
3. Manual pump soap dispenser with paddle. Compatible with 800 mL foam Refresh soap refills.
4. Dimensions: 5-3/8" x 9" x 5 3/8".
5. Material: Plastic.
F. 42" Grab Bar:
1. Grab Bar — 18-8 S, type-304, 18-gauge (1.2mm) stainless steel tubing with satin-finish. 1-1/2" (38mm) outside diameter. Ends are heliarc welded to flanges.
2. Clearance between the grab bar and wall is 1-1/2" (38mm).
3. Concealed Mounting Flanges — 18-8 S, type-304, 11-gauge (3.2mm) thick, stainless steel plate; end flanges 2" x 3-1/8" (50 x 80mm) with holes for
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 6
attachment to wall. Intermediate flanges 2-5/8" x 3-1/8" (65 x 80mm) wide x 3-1/8" (80mm) diameter.
4. Snap Flange Covers — 18-8 S, type-304, 22-gauge (0.8mm) drawn stainless steel with satin-finish. 3-1/4" (85mm) diameter x 1/2" (13mm) deep. Each cover snaps over mounting flange to conceal mounting screws.
5. Strength - capable of supporting loads in excess of 900 lbs (408 kg).
G. 36” Grab Bar:
1. Grab Bar — 18-8 S, type-304, 18-gauge (1.2mm) stainless steel tubing with satin-finish. 1-1/2" (38mm) outside diameter. Ends are heliarc welded to flanges.
2. Clearance between the grab bar and wall is 1-1/2" (38mm).
3. Concealed Mounting Flanges — 18-8 S, type-304, 11-gauge (3.2mm) thick, stainless steel plate; end flanges 2" x 3-1/8" (50 x 80mm) with holes for attachment to wall. Intermediate flanges 2-5/8" x 3-1/8" (65 x 80mm) wide x 3-1/8" (80mm) diameter.
4. Snap Flange Covers — 18-8 S, type-304, 22-gauge (0.8mm) drawn stainless steel with satin-finish. 3-1/4" (85mm) diameter x 1/2" (13mm) deep. Each cover snaps over mounting flange to conceal mounting screws.
5. Strength - capable of supporting loads in excess of 900 lbs (408 kg).
H. Omitted
I. 18” Grab Bar:
1. Grab Bar — 18-8 S, type-304, 18-gauge (1.2mm) stainless steel tubing with satin-finish. 1-1/2" (38mm) outside diameter. Ends are heliarc welded to flanges.
2. Clearance between the grab bar and wall is 1-1/2" (38mm).
3. Concealed Mounting Flanges — 18-8 S, type-304, 11-gauge (3.2mm) thick, stainless steel plate; end flanges 2" x 3-1/8" (50 x 80mm) with holes for attachment to wall. Intermediate flanges 2-5/8" x 3-1/8" (65 x 80mm) wide x 3-1/8" (80mm) diameter.
4. Snap Flange Covers — 18-8 S, type-304, 22-gauge (0.8mm) drawn stainless steel with satin-finish. 3-1/4" (85mm) diameter x 1/2" (13mm) deep. Each cover snaps over mounting flange to conceal mounting screws.
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 7
5. Strength - capable of supporting loads in excess of 900 lbs (408 kg).
J. Omitted
K. Mirror:
1. Size: 18" x 36"
2. Frame — 18-8, heavy-gauge stainless steel, 3/4" x 3/4" (19 x 19mm) angle with satin finish. One-piece, roll-formed construction forms continuous integral stiffener on all sides. Bevel design on front of angle holds frame tightly against mirror. Corners of mirror frame are heliarc welded, ground and polish smooth.
Galvanized steel back is fastened to frame with concealed screws and equipped with integral horizontal hanging brackets near the top and bottom of the mirror for hanging the mirror and to prevent the mirror from pulling away from the wall.
Locking devices secure mirror to concealed wall hanger.
3. Mirror — No. 1 quality, 1/4" (6mm) select float glass (standard glass): selected for silvering, electrolytically copper-plated by the galvanic process, and guaranteed for 15 years against silver spoilage. All edges protected by plastic filler strips; back is protected by full-size, shock-absorbing, water-resistant, nonabrasive, 3/16" (5mm) thick polyethylene padding.
4. Concealed Wall Hanger — Galvanized steel construction. Incorporates upper and lower support members, which engage lower backplate louvers to keep bottom of mirror against wall
L. Mirror 24' x 72"
1. Size: 24" x 72"
2. Frame — 18-8, heavy-gauge stainless steel, 3/4" x 3/4" (19 x 19mm) angle with satin finish. One-piece, roll-formed construction forms continuous integral stiffener on all sides. Bevel design on front of angle holds frame tightly against mirror. Corners of mirror frame are heliarc welded, ground and polish smooth.
Galvanized steel back is fastened to frame with concealed screws and equipped with integral horizontal hanging brackets near the top and bottom of the mirror for hanging the mirror and to prevent the mirror from pulling away from the wall.
Locking devices secure mirror to concealed wall hanger.
3. Mirror — No. 1 quality, 1/4" (6mm) select float glass (standard glass): selected for silvering, electrolytically copper-plated by the galvanic process, and guaranteed for 15 years against silver spoilage. All edges protected by plastic filler strips; back is protected by full-size, shock-absorbing, water-resistant, nonabrasive, 3/16"
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 8
(5mm) thick polyethylene padding.
4. Concealed Wall Hanger — Galvanized steel construction. Incorporates upper and lower support members, which engage lower backplate louvers to keep bottom of mirror against wall
M. Folding shower seat:
1. Provide seat width as required by all applicable codes.
2. Seat — One-piece, 5/16" (8mm) thick, solidly fused plastic laminate with matte-finish melamine surfaces, ivory-colored face sheets, and black phenolic-resin core that are integrally bonded — cannot delaminate. Integral slots for water drainage.
Secured to frame with stainless steel carriage bolts and acorn nuts.
3. Frame — 18-8, type-304, stainless steel with satin finish. 16-gauge (1.6mm), 1-1/4" (30mm) square tubing and 18 -gauge (1.2mm), 1" (25mm) diameter seamless tubing
4. Mounting Flanges (2) — 18-8, type-304, 3/16" (5mm) thick stainless steel with satin finish. 3" (75mm) diameter with three mounting screw holes.
5. Baseplate — 18-8, type-304, heavy-gauge stainless steel.
6. Spring — 17-7, type-301, 24-gauge (0.6mm) stainless steel. Spot-welded to baseplate.
7. Guide Bracket — 18-8, type-304, 16-gauge (1.6mm) stainless steel with satin finish.
8. Operation - Shower seat can be folded up against the wall when not in use. The spring at the top of baseplate locks seat into upright position until released by pulling the top of seat away from wall. Support system with guide bracket allows varying mounting heights and leaves floor clear for easier cleaning. Nonporous solid phenolic seat has slots to permit water to drain, does not splinter or require oiling, and will not support growth of bacteria. Slotless round-head carriage bolts and acorn nuts provide additional safety to user. Bobrick shower seats, when properly installed, have sufficient strength to support 500 lbs., (227 kg) complying with accessible design guidelines (including ADAAG in the U.S.A.).
N. Omitted
O. Shower Curtain & Accessories:
1. Curtain Rod:
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 9
a. Curtain Rod — 18-8, Type-304, 20-gauge (1.0mm) stainless steel tubing with satin finish. 1" (25mm) outside diameter. Available in lengths 36" (915mm) up to 72" (1830mm).
b. Flanges — 18-8, Type-304, 20-gauge (1.0mm) stainless steel with satin finish. Drawn, one-piece, seamless construction.
2. Shower Curtain:
a. Opaque, matte white vinyl 0.008" (0.2mm) thick, containing antibacterial and flame-retardant agents. Nickel-plated brass grommets along top, one every 6" (150mm). Bottom and sides are hemmed.
3. Curtain Hooks:
a. 18-8, Type-304, 0.09" (2mm) diameter stainless steel.
b. Provide hook quantity as required to install shower curtain.
P. Utility shelf / mop holder. One per each Janitors Closet.
1. Mounting Base and Shelf — 18-8, type-304, 18-gauge (1.2mm) stainless steel with satin finish. All-welded construction. Shelf is 8" (205mm) deep with 3/4" (19mm) return edge on all three sides. Front edge is hemmed for safety.
2. Shelf Support Brackets — 18-8, type-304, 16-gauge (1.6mm) stainless steel with satin finish. Welded to mounting base and shelf.
3. Mop/Broom Holders — Spring-loaded rubber cams with anti-slip coating. Plated steel retainers.
4. Hooks — 18-8, type-304, 12-gauge (2.8mm) stainless steel with satin finish. Each hook attached to mounting strip with two rivets.
5. Utility shelf / mop holder. Equal to B-239- 34 -one per each Janitors Closet.
Q. Hat & Coat Hook:
1. Flange and Support Arm — 18-8, type-304, 22-gauge (0.8mm) stainless steel.
Concealed, 16-gauge (1.6mm) stainless steel mounting bracket. All-welded construction. Secured to wall plate with a stainless steel setscrew.
2. Concealed Wall Plate — 18-8, type-304, 16-gauge (1.6mm) stainless steel.
3. Cap — 18-8, type-304, 10-gauge (3.6mm) stainless steel. Welded to the support arm.
Montgomery, AL Revised 14 July 2023
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 10
Provide concealed wood blocking for all toilet accessories to be installed in metal stud wall assemblies. Where toilet accessories are the located in CMU walls, comply with manufacturer's recommendations. Coordinate and provide filled CMU cells where applicable. Mount and locate per ADA. Coordinate with all other trades.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify existing conditions before starting work.
B. Verify exact location of accessories for installation.
3.02 INSTALLATION
A. Install accessories in accordance with manufacturers' instructions in locations indicated on drawings.
B. Install plumb and level, securely and rigidly anchored to substrate.
C. Mounting Heights: As required by accessibility regulations, unless otherwise indicated.
DOOR STAIN
PNT1: LIGHT WALL COLOR
Manufacturer: Sherwin Williams Color: Heron Plume SW 6070
PNT2: DOOR & CASING
Manufacturer: Sherwin Williams Color: Wall Street SW 7665
PNT3: MEDIUM WALL COLOR
Manufacturer: Sherwin Williams Color: Uncertain Gray SW 6234
PNT4: CEILING (DRY FALL)
Manufacturer: Sherwin Williams Color: Heron Plume SW 6070
QZ: Quartz Countertops Manufacturer: HanStone Quartz Color: Leaden - CC104 Edge Finish: Square
SS1: WINDOW SILLS & HANDDRYERS
Manufacturer: Corian Soild Surface Color: Cameo White Edge Finish: Square
PL1: Manufacturer: Formica Color: Winter Sky 8792-58
RB1: Manufacturer: Tarkett Type: Traditional Wall Base Color: Drizzle CG 262
HT1: Manufacturer: Daltile Style: Mesmerist Color: Whimsy MM34 Size: 3" x 12" Install Pattern: Orient Tiles vertically in a straight stack up the wall. See Bid Option Restroom Elevations
HT2: Manufacturer: Storka Style: Chelsea Color: Grey Size: 12" x 24" and 24" x 24" Install Pattern: See Bid Option
Floorpattern Plan
COUNTERTOPS
PLASTIC LAMINATE CASEWORK
RUBBER BASE
TILE
FINISH SCHEDULE LEGEND
ACT1: Manufacturer: Armstrong
Style: Ultima Texture: Fine Color: White Size: 24" x 24" x 7/8" thick Suspension System: Type 1 Edge: Beveled Tegular See Spec Section: 09 5100
ACT2: Manufacturer: Armstrong Style: Clean Room VL Size: 24" x 24" x 5/8" thick Suspension System: Type I See Spec Section: 09 5100
ACOUSTIC CEILING
PAINT
WDST1: To be selected from manufacturer's full range of colors
WALK OFF MAT
SC: Sealed Concrete See Spec Section: 09 9123
CONCRETE
PDC: Manufacturer: Scofield Stain: Soft Gray G388
POLISHED / DYED CONCRETE - SEE SPEC 09 9123
SUTP: Manufacturer: Tennant Company Product: ECO-HTS 100VOC Compliant Satine Urethane Topcoat
SATIN URETHANE TOP COAT FLOORING - SEE SPEC
09 9600
SSTP: Refer to Specification Section 10 2113 Stainless Steel Toilet Compartments Textured Finish
TOILET PARTITIONS
WINDOW SHADES
WS1: See Specification Section 12 2115 Manually Operated Shades Color to be selected from Manufacturer's full range of colors.
WM1: Manufacturer: Pawling Corporation Style: EM-650 Aluminum Abrasive Insert: 1 Black Maxi Tuft Long Wear Insert: 536 Black Granite Rigid Corrugated Vinyl Insert: 1 Black Rigid Back Nylon Carpet Insert: 519 Near Black
MOVEABLE WALL FINISH
MWF-1: Finish to be selected from Manufacturer's full range of colors.
LVT-1: Manufacturer: Tarkett Style: Method Color: 11130 Truth Told Size:…