PreBid Repair Refueler Parking and Allied Support Sun Shelters.ppt

PPT presentation 2 MB Posted

Attached to
Allied Support Sun Shelters
Solicitation number
W50S6N-21-B-0006
Issued by

About this file

This document summarizes two federal construction solicitations issued by the 187th Fighter Wing of the Alabama Army National Guard. The solicitations seek bids for repair and modification projects at the base, including repair of refueler parking areas under solicitation number W50S6N-21-B-0005 with a magnitude between $500,000 to $1,000,000, and construction of additional sun shelters under solicitation number W50S6N-21-B-0006 also with a magnitude between $500,000 to $1,000,000. Bids for both solicitations are due no later than September 9, 2021 at 2:00 PM Central Time. If awarded, the contracts will be fixed-price in nature and will require payment and performance bonds. The projects are subject to Davis Bacon wage rates and have liquidated damages clauses. The sun shelter project is set aside exclusively for small businesses with a size standard of $39.5 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

187th FIGHTER WING

PRE-BID CONFERENCE

Repair Refueler Parking Solicitation W50S6N-21-B-0005 Project FAKZ182104

And

Allied Support Aircraft Sunshade Solicitation W50S6N-21-0006 Project FAKZ182355

INTRODUCTIONS

Contracting Personnel CMSgt William Hall, Contracting Officer Mr. Phillip Bailey and Mr. Karey Elias, Contracting Specialists

Civil Engineering Maj. Adam Sanders, Base Civil Engineer Maj. William Sanford, Deputy Base Civil Engineer

Site Visit REMINDER THAT ALL QUESTIONS MUST BE SUBMITTED THROUGH THE APPROPRIATE PROCESS. DO NOT CONTACT THE INDIVIDUALS LISTED DIRECTLY

DISCLAIMER

The following is a brief overview of the IFB requirements

Contractors are cautioned to carefully read the requirements of the solicitation and comply accordingly

Projects W50S6N-21-B-0005

PROJECT TITLE: Repair Refueler Parking.

MAGNITUDE OF PROJECT: $500,000 - $1,000,000

LOCATION: Petroleum Oil and Lubricants (POL) yard

Base Bid and 6 Additive Bid Items

PROPOSAL DUE DATE

DATE: 14:00 on 09 September 2021

Documents must be received prior to or on this date Questions (Written Only) Deadline: 16:00 on 26 August

LOCATION: 187th Fighter Wing C/O Base Contracting 5187 Selma Highway Montgomery, AL 36108-4824

Hand carried bids, deliver to Building 1502 Classroom

All documents should have proper signatures

SUBMISSION REQUIREMENTS

Bid Guarantee’s are required

Performance Bond and Payment Bond: On Awarded IFB

Liquidated Damages: $870.10 plus a one-time charge of $153.00

Performance Period: 270 after NTP

Davis Bacon Wage Rates applicable: AL 20210093, dated 07/23/2021

Projects W50S6N-21-B-0006

PROJECT TITLE: Allied Support Sun Shelters

MAGNITUDE OF PROJECT: $500,000 - $1,000,000

LOCATION: Flight Line

Base Bid

PROPOSAL DUE DATE

DATE: 14:00 on 09 September 2021

Documents must be received prior to or on this date Questions (Written Only) Deadline: 16:00 on 26 August

LOCATION: 187th Fighter Wing C/O Base Contracting 5187 Selma Highway Montgomery, AL 36108-4824

Hand carried bids, deliver to Building 1502 Classroom

All documents should have proper signatures

SUBMISSION REQUIREMENTS

Bid Guarantee’s are required

Performance Bond and Payment Bond: On Awarded IFB

Liquidated Damages: $974.60 plus a one-time charge of $152.00

Performance Period: 270 after NTP

Davis Bacon Wage Rates applicable: AL 20210093, dated 07/23/2021

Questions Send to:

william.k.hall14.mil@mail.mil phillip.w.bailey4.civ@mail.mil karey.l.elias.mil@mail.mil

Award

Award will be a Firm Fixed Price

ANSWERS TO QUESTIONS

All questions, on a non-attribution basis, and the answers will be posted to the website https://www.Sam.com

If necessary Addendums, issued by an Amendment will also be posted

Check website regularly and don’t forget to REFRESH the web page.

SITE VISIT SECURITY AND SAFETY BRIEFING

You can have your cell phones, but no driving and talking / texting on your cell phone

You can take photo’s unless told otherwise

PROPOSALS ARE DUE

NO LATER THAN

Thursday 09 September 2021 14:00 P.M. Central Time

RFI’s – Do NOT submit to A/E, submit through Government

Thank You

We appreciate your interest in these project Office Open Tuesday - Friday 0700- 17:30