B08 Questions and Answers 1 through 4 3.2.21.pdf

PDF 93 KB Posted

Attached to
7-1/2 TON BRIDGE CRANE FOR BUILDING 3 BAY 1 FOR TOBYHANNA ARMY DEPOT (TYAD)
Solicitation number
W25G1V21R0020
Issued by

About this file

This document contains questions and answers pertaining to Solicitation W25G1V21R0020 for the supply and installation of a 7-1/2 ton bridge crane at the Tobyhanna Army Depot in Pennsylvania. The solicitation requires the installation of a new bridge crane in a 200 by 200 foot bay, as there is no existing crane. Bidders must hire an electrician to connect the crane electrically to the on-site substation located in the southwest corner of the bay. A CAD drawing of the bay layout and foundation details is provided to support proposal submissions.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for Solicitation W25G1V21R0020 Supply and Install of a 7-1/2 Ton Bridge Crane at Tobyhanna Army Depot

Q1: Is there an existing crane runway

A1: There is no existing bridge crane in the area.

Q2: What is the size and psi of the foundations?

A2: The foundation is 4000 psi.

Q3: Item 8 of statement of work states:

‘It shall be the contractor’s responsibility to install and connect all the electrical controls and utilities to place the crane in service. Source of power shall be from the electrical substation in the Southeast corner of the bay.’

How far is the electrical substation and what is our responsibility as far as this goes?

More detail on scope of requirements please such as TYAD electrical specifications/requirements and distances etc.

We have no idea currently of how to bid getting power from the substation, for example is power currently to a disconnect or distribution board external to the substation and we have to get power from that?

A3: There is a 12' w x 16'h cargo door entrance into the bay.

Refer to drawing, electrical substation is located in the Southwest corner of the 200' x 200' bay where the crane is being installed.

The CAD drawing shows the substation in the corner of the bay. Whoever installs the crane is going to have to have an electrician or hire an electrician to electrically connect the crane.

Q4: Please let us have the cad drawing of the foundation layout.

A4: The CAD drawing has been uploaded.