PA163-Bellefonte-B06-CSS-88786-SOO-Replace BAS and Chiller (1).docx
DOCX document 30 KB Posted
- Attached to
- CSS# 88786 – Replace BAS Controls, Chiller, Chiller Pumps & Glycol – Bellefonte, PA (PA163)
- Solicitation number
- W15QKN25RA074
About this file
This Statement of Objectives (SOO) details a replacement project for the 99th Readiness Division Directorate of Public Works at Fort Dix, New Jersey. The primary objective is to replace a 60-ton chiller unit, two chiller pumps, flow switch, glycol system components, and outdated building control systems. The project aims to upgrade aging, inefficient equipment that is currently causing maintenance challenges and potentially disrupting training missions.
The estimated project cost is $500,000, with an expected completion targeting new, more energy-efficient components. The pre-solicitation is associated with Solicitation Number W15QKN-25-R-A074, anticipated to be released around 14 July 2025 by the Department of the Army Materiel Command Contracting Command at Picatinny Arsenal. Key project contacts include Glenn Umberger (Center), Scott Henry (Field Engineering Tech), George Henry (AFOS), and Josh Rhinehart (Building Manager), with the project location identified as 405 E College Ave, Bellefonte, PA 16823.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers (in response to Synopsis).docx | DOCX document | |
| PA163 MECHANICAL SCHEDULE.pdf | ||
| Pre-Solicitation Synopsis (W15QKN-25-R-A074).docx | DOCX document | |
| PA163-Bellefonte-B06-CSS-88786-SOW-Replace BAS and Chiller (1).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives
99th Readiness Division Directorate of Public Works Fort Dix, New Jersey 08640
The Statement of Objectives (SOO) identifies the broad, basic, top-level objectives of an acquisition/procurement.
| Date: |
| 12-30-20 updated 10-2-2024 |
| Title: |
| Replace BAS controls, chiller, chiller pumps, glycol |
| CSS# |
| 25403-88786 |
| RFOS: |
| Glenn Umberger |
| Center: |
| PA163 BELLEFONTE |
| Field Eng. Tech.: |
| Scott Henry |
| Address: |
| 405 E COLLEGE AVE |
| AFOS: |
| George Henry |
| BELLEFONTE PA 16823 |
| BLDG MGR: |
| Josh Rhinehart |
Other POC:
Other POC:
1. Overall Objective:
Replace 60-ton chiller unit, 2 chiller pumps, flow switch, replace glycol in entire chilled water system loop, glycol feeder unit, air separator unit and it’s insulation, replace outdated building controls system with new EBCS integrated components.
2. General Requirements:
Replace existing components with same capacity but more efficient units
3. Impact of Deficiency:
Units break down or fail causing negative impact to training mission, control system is an old Delta system.
4. Rough Estimate(s):
500,000.00
5. Expected Results of Completed Project:
New efficient reliable components that keep the training space suitable to meet the mission.
6. Attachments:
Added to the ticket.
7. Executive Summary:
Chiller is almost 20 years old; pumps are aging, glycol air separator unit is noisy when in operation. Chiller requires constant maintenance and parts replacements (currently down awaiting parts). BAS controls are not EBCS standard controls and are outdated. The intent of this project is to replace the outdate failing equipment with new, more energy efficient equipment.
image1.png image2.png
File details come from the government source that posted it. Updated .