W15QKN-19-R-0008_Amendment_0003.pdf
PDF 16 KB Posted
- Attached to
- PA161 and PA103A2 Metal Containers
- Solicitation number
- W15QKN19R0008
About this file
This amendment modifies a solicitation for metal containers. The amendment responds to questions received about the technical data package and drawings. It clarifies that certain drawings were included inadvertently and provides missing information such as coating requirements and test methods. The response date for proposals is extended from March 14 to March 21, 2019 at 1600 EST to allow time to address the clarifications provided in the amendment.
Amendment 0003
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0003 2019MAR05
W15QKN
ARMY CONTRACTING COMMAND - NJ
PICATINNY ARSENAL, NJ 07806-5000
IRYNA MUDRA
EMAIL: IRYNA.MUDRA.CIV@MAIL.MIL
W15QKN-19-R-0008
2019FEB05
X
X
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 3
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: IRYNA MUDRA
Buyer Office Symbol/Telephone Number: ACC-NJ-CA/(973)724-6448
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
The purpose of Amendment 0003 under Solicitation W15QKN-19-R-0008 is to respond to the following questions that have been received (to date) under this Request for Proposal (RFP):
Question Set #3_______________
Note: Updates have been made to the Technical Data Package(TDP). Please refer to both questions below and the TDP in FBO.
Question #1:
The TDP for the PA1032A2 and PA161 includes PN 9331683 (Cover Assembly). Was this drawing inadvertently included? Section B in the
Solicitation references CLINs with two variant Cover Assemblies, PN 12960796 and PN 12989958 (not PN 9331683). Can the USG clarify whether PN 9331683 (Cover Assembly) is, or is not not being procured in this acquisition?
Response to Question #1:
Cover Assembly 9331683 is not being procured in this acquisition.
Question #2:
PN 9344039 (Screw) and PN 12972320 (Screw, Tapping High Performance, Zone Hardened, Structural Thread Rolling, Flat Countersunk Head) appear to be missing Quality Assurance Provision (QAP). Is the contractor to assume that these two components dont have QAPs?
Response to Question #2:
These components are commercial parts so no direct QAP is needed. However, per DTL12961080B, these are still required for First Article
Testing per paragraph 3.10.3 and Table II, and a material certification per paragraph 4.5.1.
#2a. Additionally, on PN 9344039 (Screw), Zone C2, the thread relief has no dimensional call-out. Can the Government provide some direction here?
Response to Question #2a:
This component is a commercial part. The thread relief should be 0.
Question #3:
PN 9331689 (Shaft) and PN 12992296 (Handle, Square) do not have coating requirements. Is the contractor to assume that coating requirements at the next level of assembly (PN 12960796, Cover Assembly) apply? If so, is the contractor required to apply the required coatings to individual components prior to final assembly?
Response to Question #3:
The protective finish on PN 12960796, Cover Assembly, note 4 also applies to PN 9331689 (Shaft) and PN 12992296 (Handle, Square). The protective finish on PN 12989958, Cover Assembly, note 4 also applies to PN 9331689 (Shaft) and PN 12960799 (Handle, Square, Solid).
2 3
W15QKN-19-R-0008
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Question #4:
PN 12961079 (Body Weldment), Note 11 requires a 1 ton shear load. Is this test considered non-destructive?
Response to Question #4:
This would depend on a contractors verification method; however, it is most likely a destructive test.
Question #5:
PN 12961079 (Body Weldment) appears to be missing a true position tolerance between the two Plug, Stacking (PN 12961079) components. Is the contractor to assume that if Note 2 is met, that mating MACs will properly interface together per the design and tolerances associated with the individual components?
Response to Question #5:
The Stacking, Plug is drawing 9331698. Note 2 states that Completed containers must interlock and stack for unitization. The stacking/interface requirement must be met; exactly how that is accomplished is up to each individual contractor.
Question #6:
RFP Table 1 on pages 75 and 76 list the drawings and revisions associated with the PA103A2 and PA161 containers. Several drawings provided in the TDP do not match the RFP.
Response to Question #6:
The changes to these drawings were included as Engineering Exceptions in the original PRON Request. Those changes were then incorporated verbatim into an Engineering Change Proposal (ECP) R18K2005. The Engineering Exceptions/ECP plus the older revisions are equivalent to the new revision. The Engineering Exceptions for both TDPs have been uploaded to FBO.
Question #7:
Drawing 12961079, Body Weldment, is not listed in either TDPL 12961080:19200, dated 11/13/2017 nor TDPL 12972583:19200, dated
11/13/2017.
Response to Question #7:
Drawing 12961079, Body Weldment should be part of both of these TDPLs. It was mentioned above in questions 5 and 6. A copy of revision
F has been posted to FBO.
Question #8:
In amendment 0002 to the RFP, you make reference to an ECP that has been incorporated into the TDP. Is it possible for us to download a copy of the complete ECP?
Response to Question #8:
See the answer to question 6 above. ECP R18K2005 has been uploaded to FBO.
All other terms and conditions of the RFP remain unchanged.