Question__2_Draft_RFP_M1061.docx

DOCX document 16 KB Posted

Attached to
DRAFT RFP Load, Assembly & Pack (LAP) of 60mm M1061 Federal contract opportunity
Solicitation number
W15QKN-17-R-0041
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

Question # 2 was asked about the date end date to submit questions and comments. Please see attached clarification.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Responses Draft RFP

Question #2:

The Draft Solicitation states that the draft document is released on 28 November 2016 and that comments and feedback will be accepted tentatively through 28 February 2017. The documents also states that all comments and questions sought from this notification must be provided within 60 days of the notice. What is the deadline for providing comments and questions regarding this draft RFP?

Response:

There was error made on the Draft RFP in which it stated February 2017 and 60 days. The draft RFP has been updated to read 28 February 2017 and the 60 days has since been deleted.