Attachment_0011_-_Performance_Requirements_Summary_(PRS)_Quality_Assurance_Surveillance_Plan_(QASP).pdf

PDF 152 KB Posted

Attached to
SUPPORT- PROFESSIONAL: ENGINEERING/TECHNICAL Federal contract opportunity
Solicitation number
W15QKN15R0162
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

Attachment 0011 - Performance Requirements Summary (PRS) Quality Assurance Surveillance Plan (QASP)

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 0012 – Performance Requirements Summary (PRS) / Quality Assurance Surveillance

Plan (QASP)

PERFORMANCE REQUIREMENTS SUMMARY (PRS)/ QUALITY ASSURANCE

SURVEILLANCE PLAN (QASP)

Performance

Requirement

Performance

Measure

Performance

Standard

Acceptance

Performance

Level (APL)

Method of

Surveillance

Compliance

(Exceeded, Met or

Partially

Met)

3. Software

Development

Timeliness

Completeness

Relevance

Quality

Work shall be performed no later than the completion date based on the agreement from the

Integrated Product

Team (IPT).

The Traceability between SW source code and requirements is established.

This is an ongoing software design/requirements management effort.

Work products are subject through comprehensive review by peers prior to completion.

No deviation from agreed-upon dates.

100% Traceable.

100% satisfactory compliance.

satisfactory compliance.

COR

Review

Project

Engineer

Monitoring

Monthly

Contractor

Status

Reports

IPT

meetings

3. Software

Testing

Accuracy

All contractor’s work shall be tested

IAW project schedule or as directed by the project leader.

All reviews completed as scheduled.

Provides pertinent and helpful technical solutions based on analyses

All tests are comprehensive, precise and thorough and are traced to a requirement

No deviation completion.

Compliance.

100% Traceable

Monitoring and IPT

Meeting

3. Field

Support

Accuracy

All contractor’s work shall be tested

IAW project schedule or as directed by the project leader.

All reviews completed as scheduled.

Provides pertinent and helpful technical solutions based on analyses

All tests are comprehensive, precise and thorough and are traced to a requirement

No deviation completion.

Compliance.

100% Traceable

Monitoring and IPT

Meeting

Part II, Section

I-Contract

Clauses;

52.222-50, Trafficking in

Persons

Completeness Validate that the contractor:

1: Conducted training or kept records with employee signature as understanding of

U.S. Zero

Tolerance policy.

2: Has a documented list of what the contractor cites as appropriate actions to violations.

3: Documented the number of violations to date (if any).

4: Documents actions taken.

100% compliance required due to

U.S. Zero

Tolerance policy.

Periodic inspection iaw COR surveillance schedule.

7.15

Development of an OPSEC

Standing

Operating

Procedure/Plan

OPSEC Plan from the Contractor.

Within 90 calendar days of contract award.

100%

Compliance

7.16 OPSEC

Training

Training report and certificates for all contractor employees

Within 30 calendar days of an employee reporting for duty and then annually thereafter.

100 % compliance

COR and

AR/OPSEC

Officer

7.19 Anti-

Terrorism (AT)

Level I

Training report and certificates from the

Contractor.

Within 45 calendar days of contract award and within

45 calendar days of new employees commencing performance.

100%

Compliance

7.21 iWATCH

Training report from the

Contractor.

Within 45 calendar days of contract award and within

45 calendar days of new employees commencing performance.

100%

Compliance

7.24

Employees

Who Require

Access to

Government

Information

Systems (IS)

Registration report for all Contractor employees with access to a

Government IS registered in the

Army Training

Certification

Tracking System

(ATCTS).

Prior to access to the IS and then annually thereafter.

100 % compliance

7.25

Information

Assurance

(IA)/

Information

Technology

(IT) training

Training report and certificates for all Contractor employees.

Within six months of employment and then annually thereafter.

Compliance