VOL 1_Specs-Tulsa-ConstructFuelFacilities-20200806.pdf

PDF 15 MB Posted

Attached to
Tulsa ANG Fuel Facility Federal contract opportunity
Solicitation number
W912BV20R0031
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

About this file

This document outlines a federal contract opportunity for the construction of fuel facilities for the Oklahoma Air National Guard in Tulsa County, Oklahoma. The U.S. Army Corps of Engineers - Tulsa District is seeking a contractor to construct three 50,000 gallon welded horizontal steel above-ground fuel storage tanks, two commercial truck unloading stands, two re-fueler loading stands, an enclosed Electrical Control House, an Open Shelter Filter house, a Fuel Operations Facility building with fuel testing laboratory, a Re-fueler Vehicle Parking area with cement concrete parking and secondary containment, and an R-11 maintenance building. Additionally, the project includes constructing a Military Service Station with 8,000 gallons each of diesel and motor gas storage and dispensing, equipment, an optional canopy, a control building, and secondary containment for tanks, offloading and dispensing. Site preparation work will include utility system extensions, site preparation for the improvements, local roads, a drainage retention and storm drainage system, and security fencing and gates. The estimated magnitude of construction is between $10-25 million, with an estimated project duration of 545 calendar days. This procurement is unrestricted with no set-aside requirements.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VOLUME I

Specifications Construct Fuel Facilities

PN DESC1912

FY20 MCP

HQ DLA/U.S. Air National Guard Project Tulsa International Airport, Oklahoma Submittal – August 2020

Prepared for

U.S. Army Corps of Engineers Omaha District

Prepared by

Argus Consulting, Inc

The Schemmer Associates

Jensen Hughes

Solicitation: W912BV20R0031 http://www.jensenhughes.com/

Fuels Storage Complex DESC1912 Tulsa ANG, Oklahoma

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 00 PRICING (CLIN) SCHEDULE

00 21 00 INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

00 22 11 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA,

AND BASIS OF AWARD

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00 SPECIAL CONTRACT REQUIREMENTS

00 73 46 WAGE DETERMINATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 04 00 COORDINATION, FIELD ENGINEERING, AND MEETINGS

01 14 00 WORK RESTRICTIONS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 30 01 ADDITIONAL ADMINISTRATIVE REQUIREMENTS

01 30 50 BASE SECURITY REQUIREMENTS - ANG

01 32 01.00 10 PROJECT SCHEDULE - TRO/ANG

01 33 00 SUBMITTAL PROCEDURES

01 33 29 LEED(TM) DOCUMENTATION

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 15 QUALITY CONTROL (DBB)

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS 3.0 CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 20 ENVIRONMENTAL PROTECTION

01 58 00 BULLETIN BOARD, PROJECT SIGN, AND SAFETY SIGN

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA - COAO

01 78 23.33 OPERATION AND MAINTENANCE MANUALS FOR AVIATION FUEL

SYSTEMS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 52 00 METAL RAILINGS

PROJECT TABLE OF CONTENTS Page 1

Volume 1 - Specifications

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 21 40 SPRAY-ON-FOAM THERMAL INSULATION

07 22 00 ROOF AND DECK INSULATION

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 41 13 METAL ROOF PANELS

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 36 13 SECTIONAL OVERHEAD DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

09 97 13.17 THREE COAT EPOXY INTERIOR COATING OF WELDED STEEL

PETROLEUM FUEL TANKS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 51 13 METAL LOCKERS

DIVISION 11 - EQUIPMENT

11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

12 31 00 MANUFACTURED METAL CASEWORK

12 34 00 MANUFACTURED PLASTIC CASEWORK

PROJECT TABLE OF CONTENTS Page 2

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 13 - SPECIAL CONSTRUCTION

13 12 00 METAL CANOPY SYSTEMS

13 34 19 METAL BUILDING SYSTEMS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 TULSA ANG FUEL CONTROL AND SUPPORT BUILDING WET PIPE

SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL

23 11 25 FACILITY GAS PIPING

23 23 00 REFRIGERANT PIPING

23 31 13.00 40 METAL DUCTS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS

23 54 19 BUILDING HEATING SYSTEMS, WARM AIR

23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS

23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS

25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - FIRE

ALARM

25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - MASS

NOTIFICATION

25 05 11.03 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -

UTILITY MONITORING

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 27 14.00 20 ELECTRICITY METERING

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 32 14.00 10 DIESEL-GENERATOR SET, STATIONARY 15-300 KW, STANDBY

APPLICATIONS

26 41 00 LIGHTNING PROTECTION SYSTEM

PROJECT TABLE OF CONTENTS Page 3

26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 63.00 TULSA ANG FUEL CONTROL BUILDING B ANALOG/ADDRESSABLE

INTERIOR FIRE ALARM SYSTEM

28 31 76.00 TULSA ANG FUEL CONTROL AND SUPPORT BUILDING INTERIOR FIRE

ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 00 01 GEOTECHNICAL REPORT

31 11 00 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID

PAVEMENTS

32 11 23 AGGREGATE BASE COURSES

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 13 73.19 COMPRESSION CONCRETE PAVING JOINT SEALANT

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 01 50.60 CLEANING OF PETROLEUM STORAGE TANKS

33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING

33 08 55 FUEL DISTRIBUTION SYSTEM START-UP (NON-HYDRANT)

33 09 52 FUEL PUMP CONTROL AND ANNUNCIATION SYSTEM (NON-HYDRANT)

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS

33 40 00 STORM DRAINAGE UTILITIES

33 52 10 FUEL SYSTEMS PIPING (SERVICE STATION)

33 52 23.15 POL SERVICE PIPING WELDING

33 52 40 FUEL SYSTEMS PIPING (NON-HYDRANT)

33 52 43.11 AVIATION FUEL MECHANICAL EQUIPMENT

33 52 43.12 AVIATION FUEL PANTOGRAPHS

33 52 43.14 AVIATION FUEL CONTROL VALVES

33 52 43.23 AVIATION FUEL PUMPS

33 52 43.28 FILTER SEPARATOR, AVIATION FUELING SYSTEM

33 52 80 LIQUID FUELS PIPELINE COATING SYSTEMS

33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS

33 57 55 FUEL SYSTEM COMPONENTS (NON-HYDRANT)

PROJECT TABLE OF CONTENTS Page 4

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

Volume 2 - Drawings (provided under separate cover)

SOLICITATION, OFFER, 1. SOLICITA TlON NO. 2. TYPE OF SOLICITA TlON 3. DA 1E ISSUED PAGE OF PAGES

AND AWARD □ SEALEDBID (FB) 1 0-Aug-2020 (Construction, Alteration, or Repair)

W912BV20R0031

� NEGOTIA 1ED

(RFP)

IMPORTANT-The "offer" section on the reverse must be fully completed by offerer.

4. CONTRACT NO. 5. REQUISITlON/PUROiASE REQUEST NO. 6. PROJECT NO.

7. ISSUEDBY CODE IW912BV 8. ADDRESS OFFER TO (If Other Than Item 7) CODE I

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT See Item 7

2488 E. 81ST STREET

TULSA OK 74137-4290

lEL: FAX: 918-669-7436 lEL: FAX:

9. FOR INFORMI\ TION A.NAIVE B. TB.EPHONE NO. (Include area code) (NO COLLECT CALLS)

CALL: JASON L FLOYD 918.669.7022

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMI\NCE OF THE WORK DESCRIBED IN THESE DOCl.M:NTS (Title, identifying no., date):

Tulsa ANG Fuels Storage

The NAICS code f or this project is 237120, Oil and Gas Apeline and Related Structures Construction. The size standard is $39.5M.

IA W DFAR 236.204, the cost magnitude of this project is between $10,000,000 and $25,000,000.

POC is the Contract Specialist; CPT Jason Floyd at jason.l.floyd@usace.arrny .rril@918-669-7720.

11. The Contractor shall begin performance within 10 calendar days and complete ii within 545 calendar days after receiving

Daw ard, 0 notice to proceed. This performance period is � mandatory, D negotiable. (See 52.210-11 .)

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMI\NCEAND PA YM:NT BONDS? 128. CALENDAR DAYS (If "YES," indicate v.nthin how many calendar days after award in Item 128.)

�YES □ NO

13. ADDITlONAL SOLIOTATION REQUIB.ENTS:

A. Sealed offers in original and 1 copies to perform the w ork required are due at the place specified in Item 8 by 02:00 PM (hour) local time 09 Sep 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee � is, D is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 90

NSN 7540-01-155-3212

calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(8)

W912BV20R0031

Section 00 11 00 - SF 1442 and CLIN Schedule

CLIN SCHEDULE

SECTION 00 11 00

CONSTRUCT FUEL FACILITIES, Tulsa ANG

PRICING (CLIN) SCHEDULE

CLIN Description of Item Quantity Unit Unit Price

Amount

BASE BID ITEMS

0001 All work complete for Bulk Fuel Storage - Jet Fuel

1 JOB - $_________

0002 All work complete for 2 Fuel Truck Offloads 1 JOB - $_________ 0003 All work complete for 2 Fuel Truck Fill Stands 1 JOB - $_________ 0004 All work complete for Fuel Separator Facility 1 JOB - $_________ 0005 All work complete for Fuel Systems & Piping 1 JOB - $_________ 0006 All work complete for POL Ops Building (Bldg A) 1 JOB - $_________ 0007 All work complete for Refueler Parking 1 JOB - $_________ 0008 All work complete for Military Service Station 1 JOB - $_________ 0009 Site Improvements (Excluding City of Tulsa Right-of-

Way) 1 JOB - $_________ 0010 Site Improvements (City of Tulsa Right-of-Way) 1 JOB - $_________ 0011 Site Utilities 1 JOB - $_________ 0012 As-Builts 1 JOB - $_________

TOTAL BASIC (ITEMS 1-12)

Quantity Unit Unit Price

Amount

OPTION ITEMS

0013 Option 1: Exit to Mingo Road for Truck Offloading

Traffic (CP215) 1 JOB - $_________ 0014 Option 2: Viper Road Area Improvements (CP216) 1 JOB - $_________ 0015 Option 3: Canopies for Military Service Station 1 JOB - $_________ 0016 Option 4: Canopies for Fill Stand Stations 1 JOB - $_________ 0017 Option 5: Canopies for Offload Stations 1 JOB - $_________ 0018 Option 6: Disposal of Petroleum Contaminated Soils

(Includes Stockpiling, Sampling, Transportation and Disposal to an Off-Site Facility) 100 CY $_____ $_________

Option 7: Disposal of Petroleum Contaminated Water (Includes Storage, Sampling, Transportation and Disposal to an Off-Site Facility) 50 GAL $_____ $_________

0020 Option 8: All Work for the Automatic Tank Gauging System (ATG) and Leak Detection (LD) Systems for the new fuel storage tanks and for leak detection systems for the Vehicle Fuel Station. To include but not limited to level gauges, cabling, ATG and LD field devices, ATG/ LD consoles and displays. All conduit required for ATG and LD systems shall be included in Basic Items 1 – Funded Separately 1 JOB - $_________

TOTAL OPTIONS (ITEMS 13-20) $_________

I TOTAL AMOUNT (BASE BID PLUS ALL OPTION ITEMS)

Contract Duration (See Note 8):

Notes:

W912BV20R0031

Page 4 of71

1. Offerors must insert a price on all numbered items of the CLIN pricing schedule. Prices include both design and construction. Failure to do so may result in the offer being unacceptable. Additions will be subject to verification by the Government. In case of variation between the lump-sum (L.S.) prices and the total amount, the lump-sum prices will be considered the price. In case of variation between the unit prices and the extensions, the unit prices will be considered the price submitted. Offerors must provide a cost breakdown of each lump sum price (management, labor hours, materials and other direct charges). The Government reserves the right to exercise the options from contract award to within 90 days after issuance of Notice to Proceed for CLINs 0015-0020 and within 180 days after issuance ofNotice to Proceed for CLINs 0013-0014. See FAR 52.217-5 Evaluation of Options.

2. The offeror agrees to perform the work required at the prices specified above in strict accordance with the terms of this scope of work, if this offer is accepted by the Government in writing within 60 calendar days after the date offers are due.

3. The Offeror shall submit pricing data on the latest Pricing Schedule as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

4. Offerors must insert a price on all numbered items of the Pricing Schedule. Failure to do so will disqualify the Offer.

5. All quantities are estimated except where the unit is given as Job. If a modification to a proposal is submitted and provides for a lump-sum adjustment to the total estimated cost, the application of the Job adjustment to each unit price and/or lump-sum price, in the Pricing Schedule must be stated or, ifit is not stated, the Offeror agrees that the lump-sum adjustment shall be applied on the prorated basis to every item in the Bidding Schedule.

6. All the extensions of the unit prices shown (if applicable) will be subject to verification by the Government.

In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

7. The Offeror shall propose total contract duration in number of calendar days after the notice to Proceed (NTP) is received by the Contractor, whether via electronic means or hard copy, whichever is the earliest method of delivery. The total number of proposed calendar days for construction through completion, ready for turnover shall not exceed the days shown at, SCR: 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means.

Day number 1 is the day after the date of the receipt of the NTP.

8. AWARD

Only one contract will be awarded under this solicitation.

--END SECTION 00 11 00--

Section 00 21 00 - Instructions, Conditions & Notices to Offerors

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS TO OFFERORS

SECTION 00 21 00

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

1.0 GENERAL INFORMATION

1.1 GENERAL DESCRIPTION OF WORK

1.2 GOVERNMENT SECURITY REQUIREMENTS

1.3 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

1.4 OFFEROR'S QUESTIONS AND COMMENTS

1.5 SMALL BUSINESS SIZE STANDARD/NAICS CODE

1.6 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

1.7 PRE-PROPOSAL CONFERENCE/SITE VISIT

1.8 ACCURACY IN PROPOSALS

1.9 PROPOSAL SUBMITTALS

1.10 PROPOSAL FORMAT

1.11 JOINT VENTURE PROPOSAL REQUIREMENTS

1.12 DEVIATIONS AND EXCEPTIONS

1.13 GENERAL INSTRUCTIONS

This construction project includes constructing three (3) 50,000 gal (each) welded horizontal steel above-ground fuel storage tanks complete with railings and associated necessary appurtenances, two commercial truck unloading stands with equipment canopies, two re-fueler loading stands with optional equipment canopies, enclosed Electrical Control House and Open Shelter Filter house, Fuel Operations Facility (building) with fuel testing laboratory, Re-fueler Vehicle Parking with cement concrete parking, secondary containment, and R-11 maintenance building. Additionally, the project includes constructing a Military Service Station (MSS) consisting of 8,000 gallons of diesel storage with two dispensing nozzles, 8,000 gallons of Motor Gas (MOGAS) storage with two dispensing nozzles, equipment, optional MSS dispensing area canopy, MSS Control Building, and secondary containment for tanks, offloading and dispensing. Site preparation will include extension of utility systems to site, preparation of site for above listed improvements, local streets and roads to support the above listed improvements, construction of site drainage retention and storm drainage systems; and construction of site security fencing and gates.

The project includes a base bid and eight (8) bid options for additional items.

The fuels storage complex site is located southwest of the intersection of 46th Street North and Mingo Road on the Tulsa Air National Guard Base, Tulsa County, Oklahoma.

1.2 GOVERNMENT SECURITY REQUIREMENTS

The Offeror(s) must ensure that ALL mail sent to the Tulsa District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc. ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to bids, modifications to bids, proposals, revised proposals, bonds, correspondence, etc., will be REJECTED by the U.S. Army Corps of Engineers mail room facility located at 2488 E. 81st Street, Tulsa, OK 74137- 4290, if it does not contain a return mailing address. There will be no exceptions.

USACE Tulsa District Point of Contact:

CPT Floyd 2488 E 81st St.

Tulsa, OK 74137 Phone: 918-669-7022 Email: Jason.L.Floyd@usace.army.mil

1.3 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

Copies of the solicitation and any amendments will be uploaded to BetaSAM.

The offeror shall submit in the proposal all requested information specified in this solicitation.

1.4 OFFEROR'S QUESTIONS AND COMMENTS

Questions and/or comments relative to the document should be submitted via Bidders Inquiry at:

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=HomePagePublic.

Instructions for registering in the ProjNet Bidder Inquiry system are available on the above web site.

The Bidder Inquiry Key for this project is: 98FX97-7M2NRV

Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

Note: All questions and/or comments should be entered in Bidder’s Inquiry no later than 01 September 2020 at 2:00PM CST so they may be given consideration or action taken prior to receipt of offers.

1.5 SMALL BUSINESS NAICS CODE/SIZE STANDARD

NAICS Code 236120 / $36.5M. Also see FAR 52.204-8

1.6 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This Request for Proposal (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.

1.7 PRE-PROPOSAL CONFERENCE/SITE VISIT

All vendors are highly encouraged to attend a pre-proposal site visit, which is scheduled for 20 August 2020 at 10:30 am CST at 9100 E. 46th St N., Tulsa, OK 74115. Submit names via email to Jason.L.Floyd@usace.army.mil and Kalli.Clark- Egan2@usace.army.mil NO LATER THAN 5:00 pm CT on 18 August 2020.

Vendors may be required to fill out a questionaire and complete a body temperature check at the security gate prior to the site visit.

1.8 ACCURACY IN PROPOSALS

Proposals must set forth full, accurate, and complete information as required by this RFP, (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.

1.9 PROPOSAL SUBMITTALS

The submittal method for proposals is electronic via email if each email with attachments is less than 10MB total, or via an alternative method of electronic delivery.

If an offeror has no alternative method of electronic delivery, the Contract Specialist

(POC identified above) can provide a method upon request. The following email address must be used to submit proposals: jason.l.floyd@usace.army.mil Proposals will only be accepted until 09 September 2020 at 2:00PM CST.

Mail original bid bonds to:

U.S. Army Corps of Engineers, Tulsa District ATTN: CPT Floyd

CESWT-CT-E (9-11)

2488 E 81st Street Tulsa, OK 74137-4290

The Packaging shall be marked: “Solicitation Number: W912BV20R0031”

1.10 PROPOSAL FORMAT

See Section 00 22 11 for Proposal requirements.

1.11 JOINT VENTURE PROPOSAL REQUIREMENTS

When proposing as a joint venture, all members of the joint venture shall sign the SF 1442 and the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration. If this is an 8(a) or HubZone joint venture, the offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 and 13 CFR Part 126, respectively.

1.12 DEVIATIONS AND EXCEPTIONS

Deviations and exceptions to the terms and conditions of the solicitation are neither encouraged nor desired. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined “unacceptable” and thus be ineligible for the award. Should the offeror have any questions related to specific terms and conditions, these must be resolved prior to submission of the offer.

Notwithstanding the above, if deviations and exceptions are included with the offer, the offeror shall list and describe in detail the deviations and/or exceptions. All deviations and exceptions shall be fully supported with the Offeror’s rationale and shall fully explain the impact, if any, on the performance and/or specific requirements of the RFP.

1.13 GENERAL INSTRUCTIONS

1.13.1 Offers will be evaluated using the criteria under Section 00 22 11, Proposal Submission Requirements, Evaluation Criteria, and Basis for Award and compliance with the RFP technical requirements. Noncompliance with the RFP requirements will raise serious questions regarding an offeror’s technical ability to perform the services and may be grounds to eliminate the proposal from further consideration for contract award.

1.13.2 The Offer. The submission of the documentation specified under Section 00 22 11, Proposal Submission Requirements, Evaluation Criteria, and Basis for Award, will constitute the offeror’s acceptance of the terms and conditions of the RFP, concurrence with the plans and specifications, and the proposed contract type.

1.13.3 It is the Government’s intention to award without discussions. Offerors are encouraged to present their best technical proposal and prices in their initial proposal submission. However, in accordance with FAR Part 15.306, the Government reserves the right to hold discussions if necessary. If this occurs, a competitive range will be determined and offerors notified. The competitive range may be limited for purposes of efficiency in accordance with (IAW) FAR Part 15.306(c)(2).

1.13.4 In accordance with FAR Subpart 4.8 (Government Contract Files), the Government will retain one copy of all unsuccessful proposals. Unless the offeror requests otherwise, the Government will destroy extra copies of such unsuccessful proposals.

If an offeror believes that the requirements in these instructions contain an error, an ambiguity, omission, or are otherwise unsound, the offeror shall immediately notify the contracting officer (KO) in writing with supporting rationale. The offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without discussion.

1.14.5 All referenced documents are available from the Contract Specialist, CPT Jason Floyd at Jason.L.Floyd@usace.army.mil.

1.14.6 Debriefings. The contracting officer will promptly notify offerors of any decision to exclude them from the competitive range, whereupon they may request and receive a debriefing in accordance with FAR 15.505. The contracting officer will notify unsuccessful offerors in the competitive range of the source selection decision in accordance with FAR 15.506. Upon such notification, unsuccessful offerors may request and receive a debriefing. Offerors desiring debriefing must make their request in accordance with the requirements of FAR 15.505 or 15.506, as applicable. All debriefings will be provided officially in writing.

-- End of Section 00 21 00 --

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0010 Destination Government Destination Government 0011 Destination Government Destination Government 0012 Destination Government Destination Government 0013 Destination Government Destination Government 0014 Destination Government Destination Government 0015 Destination Government Destination Government 0016 Destination Government Destination Government 0017 Destination Government Destination Government 0018 Destination Government Destination Government 0019 Destination Government Destination Government 0020 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

0003 N/A N/A N/A N/A

0004 N/A N/A N/A N/A

0005 N/A N/A N/A N/A

0006 N/A N/A N/A N/A

0007 N/A N/A N/A N/A

0008 N/A N/A N/A N/A

0009 N/A N/A N/A N/A

0010 N/A N/A N/A N/A

0011 N/A N/A N/A N/A

0012 N/A N/A N/A N/A

0013 N/A N/A N/A N/A

0014 N/A N/A N/A N/A

0015 N/A N/A N/A N/A

0016 N/A N/A N/A N/A

0017 N/A N/A N/A N/A

0018 N/A N/A N/A N/A

0019 N/A N/A N/A N/A

0020 N/A N/A N/A N/A

CLAUSES INCORPORATED BY REFERENCE

52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (Jan 2017) - Alternate I

OCT 1997

52.215-20 Requirements for Certified Cost or Pricing Data or Information Other Than Certified Cost or Pricing Data

OCT 2010

52.217-5 Evaluation Of Options JUL 1990 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.223-22 Public Disclosure of Greenhouse Gas Emissions and Reduction Goals -- Representation.

DEC 2016

52.225-10 Notice of Buy American Requirement--Construction Materials

MAY 2014

52.232-38 Submission of Electronic Funds Transfer Information with Offer

JUL 2013

52.233-2 Service Of Protest SEP 2006 52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7010 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data

JUL 2019

252.236-7008 Contract Prices-Bidding Schedules DEC 1991

CLAUSES INCORPORATED BY FULL TEXT

W9 l 2BV20R003 l

Page 13 of71

52.215-22 LIMITATIONS ON PASS-THROUGH CHARGES--IDENTIFICA TION OF SUBCONTRACT

EFFORT (OCT 2009)

(a) Defmitions. Added value, excessive pass-through charge, subcontract, and subcontractor, as used in this provision, are defined in the clause of this solicitation entitled "Limitations on Pass-Through Charges" (FAR 52.215-23).

(b) General. The offeror's proposal shall exclude excessive pass-through charges.

( c) Performance of work by the Contractor or a subcontractor. (1) The offeror shall identify in its proposal the total cost of the work to be performed by the offeror, and the total cost of the work to be performed by each subcontractor, under the contract, task order, or delivery order.

(2) If the offeror intends to subcontract more than 70 percent of the total cost of work to be performed under the contract, task order, or delivery order, the offeror shall identify in its proposal--

(i) The amount of the offeror's indirect costs and profit/fee applicable to the work to be performed by the subcontractor(s); and

(ii) A description of the added value provided by the offeror as related to the work to be performed by the subcontractor(s ).

(3) If any subcontractor proposed under the contract, task order, or delivery order intends to subcontract to a lower tier subcontractor more than 70 percent of the total cost of work to be performed under its subcontract, the offeror shall identify in its proposal--

(i) The amount of the subcontractor's indirect costs and profit/fee applicable to the work to be performed by the lower-tier subcontractor(s); and

(ii) A description of the added value provided by the subcontractor as related to the work to be performed by the lower-tier subcontractor(s).

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm fixed price contract resulting from this solicitation.

(End of provision)

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defmed in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment ofreceipt from

Rudolfo J. Morales Jr.

2488 E 81st St.

Tulsa, OK 74137

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far

(End of provision)

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of provision)

252.215-7012 REQUIREMENTS FOR SUBMISSION OF PROPOSALS VIA ELECTRONIC MEDIA (JAN 2018)

The Offeror shall submit the cost portion of the proposal via the following electronic media: https://safe.apps.mil/ or electronic mail.

(End of provision)

Section 00 22 11 - Proposal Submission Requirements, Evaluation Criteria, Basis of Award One-Step-Best Value, Design-Build (Single Award)

PROPOSAL SUBMISSION REQUIRED

SECTION 00 22 11

PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND

BASIS OF AWARD

1.0 OVERVIEW.

This is a competitive best value Lowest Price Technically Acceptable (LPTA) solicitation for a construction contract for the FY20 Fuels Storage Complex located at Tulsa Air National Guard, Tulsa County, Oklahoma.

1.1 WHO CAN SUBMIT

1.1.1 All firms registered in the System for Award Management are authorized to submit proposals.

1.1.2 Organization Conflicts of Interest (OCI) Disclosure: The Offeror shall provide a disclosure statement with its proposal which concisely describes all the relevant facts concerning the past or present organizational conflicts of interest relating to work on this project. In the same statement, and if applicable, the Offeror shall provide information to assure the Government that the conflicts of interest have been mitigated and/or neutralized to the maximum extent possible. If a conflict of interest is discovered after award of this contract, the Contracting Office will make a decision whether to terminate the contract.

2.0 BASIS OF AWARD.

Award will be made to the acceptable proposal meeting or exceeding the technical acceptability standards for non-cost factors and is the lowest price of all acceptable proposals and is found fair and reasonable by the Contracting Officer. Tradeoffs are not permitted. Proposals are evaluated for acceptability but not ranked using non-cost/price factors. The Government will not award a contract to a Firm whose proposal contains a deficiency, as defined in FAR 15.001. The Government reserves the right to reject any offer if the offer is not in the best interest of the Government.

3.0 PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS.

3.1 REQUIREMENTS FOR SEPARATE PRICE AND TECHNICAL PROPOSALS.

3.1.1 Each offeror must submit both a price proposal and a technical proposal. The price proposal and the technical proposal must be submitted as separate volumes.

Ensure that the outside of each separate volume is clearly marked to indicate its contents; and the identity of the offeror. Additionally, clearly identify the “original” price proposal and the “original” technical proposal on the outside cover.

3.1.2 Both the price proposal and the technical proposal must be received by the closing date and time set for receipt of proposals.

3.1.3 No dollar amounts from the price proposal are to be included in the technical proposal.

3.1.4 All information intended to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal (Volume 1). Do not merely cross-reference similar material in the Price Proposal, or vice versa. Also, do not include links to websites in lieu of incorporating information into your proposal.

3.1.5 Deviations, Exception and Assumptions

Deviations and exceptions to the terms and conditions of the solicitation are not allowed. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be deemed “unacceptable” and thus ineligible for award. Should the Offeror have any questions related to specific terms and conditions, these must be resolved prior to submission of the offer. If the Offeror must make any assumptions prior to submitting the proposal, the Offeror shall list and describe in detail the assumptions on the first page of each Tab. All assumptions shall be fully supported with the Offeror’s rationale and shall fully explain the impact, if any, on the performance and/or specific requirement of the RFP. The Offeror shall clearly describe on the Proposal Cover Sheet submitted with the Price Proposal any assumption to the contractual and/or technical terms and include the monetary impact on the solicitation with the price proposal. This information will not be evaluated separately but may impact the evaluation of other factors.

3.2 DISCUSSIONS.

The Government does not intend to enter into discussions with offerors prior to making an award. Offerors are encouraged to present their best technical proposal and prices in their initial proposal submission. However, in accordance with FAR Part 15.306, should discussions become necessary, the Government reserves the right to hold them. If this occurs, a competitive range will be determined and offerors notified. The competitive range may be limited for purposes of efficiency in accordance with (IAW) FAR Part 15.306(c)(2).

3.3 GENERAL INSTRUCTIONS.

3.3.1 Submit only the hard-copy paper documents and the electronic files specifically authorized and/or required elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. All pages should be numbered.

3.3.2 Use only 8.5” by 11” inch paper for submissions, unless another paper size is specifically authorized elsewhere in this section for a particular submission. Do not use larger paper sizes (e.g., 11” x 14” or 11” x 17” sheets) unless specifically authorized in this section for a particular submission. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide, but may include headers and footers.

3.3.3 “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data.”

3.3.4 For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, fold-out pages (11" x 14" or 11" x 17") will count as one page. Table of Contents, proposal cover letters, and tabs between proposal information do not count toward any page limitations in the proposal.

3.3.5 Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision, e.g., Error, Omission, or Clarification, or amendment shall be included and be annotated for each revision. Proposal replacement pages shall be numbered, shall be clearly marked “REVISED”, shall show the date of revision, shall be submitted in appropriate number of copies (e.g., if two (2) copies of the original page was required, then two (2) copies of the revised page will also be required, and shall be a different color than the original pages they are to replace).

3.4 SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL – FACTORS 1 – 4

(VOLUME 1).

3.4.1 Number of Sets of the Technical Proposal. Submit one (1) electronic copy of the Technical Proposal. Submission shall contain the entire proposal in .pdf format using Adobe Acrobat software to print to a .pdf file; do NOT scan the document(s) into a .pdf file. The text portion of the complete proposal shall be contained as a searchable single .pdf file. Sections of the proposal shall be bookmarked (linked to the index) in logical order with bookmarks clearly identifying the contents of each section.

3.4.2 Format and Contents of the Technical Proposal and List of Tabs The proposal shall be organized using the tabs specified in Section 4.0.

3.4.3 Page Limitations. The maximum number of pages for the Technical Proposal is 24 pages single sided or 12 pages double sided. The Organizational Chart and Summary Schedule can be up to 11” x 17”. The Table of Contents, Cover Sheets, Section Tabs, and the Past Performance Questionnaires (PPQs) will also not count against the page count. Each page shall be sequentially numbered for that section.

3.5 SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL – FACTOR 6 (VOLUME

2).

3.5.1 Number of Sets of the Price Proposal. Submit an ORIGINAL set of the price proposal electronically.

3.5.2 Format and Contents of the Price Proposal and List of Tabs. The price proposal shall be appropriately labeled as such and shall be organized as indicated in Section

4.0. Note: If the Offeror is not required to submit any information under a listed Tab in accordance with the instructions below, that tab can be omitted. However, do not renumber the subsequent tabs.

3.5.3 Size Restrictions and Page Limits. Use only 8.5” x 11” pages. There are no page limits set for the price proposal. However, limit your response to information required by this solicitation. Excess information will not be considered in the Government’s evaluation.

4.0 PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS.

VOLUME 1 – TECHNICAL PROPOSAL

FACTOR LOCATION DESCRIPTION RELATIVE IMPORTANCE

FACTOR

VOLUME 1,

TAB A

Experience on Similar Contracts

Acceptable/Unacceptable

FACTOR

VOLUME 1,

TAB B

Past Performance Acceptable/Unacceptable

FACTOR

VOLUME 1,

TAB C

Key Personnel Qualifications and Construction Experience

Acceptable/Unacceptable

FACTOR

VOLUME 1,

TAB D

Proposed Contract Duration and Summary Schedule

Acceptable/Unacceptable

VOLUME 2 – PRICE PROPOSAL

FACTOR LOCATION DESCRIPTION RELATIVE IMPORTANCE

N/A VOLUME 2,

TAB A

Proposal Cover Sheet Not Rated

N/A VOLUME 2,

TAB B

SF1442 and Acknowledgement of Amendments

Not Rated

FACTOR

VOLUME 2,

TAB C

Section 00 11 00, PRICING

SCHEDULE

Award will be made to the lowest price technically acceptable proposal

N/A VOLUME 2,

TAB D

Bid Guarantee (Bid Bond) Not Rated

N/A VOLUME 2,

TAB E

Representations and Certifications

Not Rated

N/A VOLUME 2,

TAB F

Joint Venture Agreement (if applicable)

Not Rated

N/A VOLUME 2,

TAB G

Small Business Subcontracting Plan

Not Rated

5.0 VOLUME 1 – TECHNICAL PROPOSAL.

Submit detailed responses to the evaluation factors under each of the tabs as follows.

5.1 VOLUME 1 – TAB A: FACTOR 1 – Experience on Similar Contracts.

This factor will evaluate the offeror for its experience in successful completion of design/bid/build projects of similar scope, magnitude and complexity completed in the USA within the past five years. Projects completed over five years ago may be submitted to demonstrate ability, but they will carry little weight in the evaluation and will not be used to meet the standard for acceptability.

5.1.1 Submission Requirements. For this factor, the offeror should submit three (3) examples of construction projects which best illustrate the experience of the construction contractor on projects of similar function, scope, complexity, and dollar value as the requirements for this solicitation. Each project summary should consist of a maximum two page narrative of the example project, discussing the project and providing specifics as noted herein. No more than three (3) projects may be submitted.

If more than three (3) projects are submitted, only the first three (3) listed in the proposal will be evaluated. Each project cited must have a construction dollar value greater than $10 million and have been completed in the USA within five (5) years from the date that the proposal for this solicitation is due. Indefinite-Delivery, Indefinite Quantity (IDIQ) Contracts, where numerous Task Orders are summed to meet the minimum construction dollar value identified herein, are not acceptable. Only those projects for which the offeror was the prime contractor or was a Subcontractor with a large percentage (50% or more) of the related work shall be submitted. All projects submitted must have been completed by the office that will be performing the work. The summaries should include project types that are similar to the Fuels Storage Complex at Tulsa ANG, Oklahoma. Similar project types are:

5.1.1.1 Fuels Storage Complex, to include above-ground fuel storage tanks, truck unloading stands, refueler loading stands, equipment canopies, administrative, control, and maintenance facilities, and military service station.

5.1.1.2 The Government requires that project examples submitted be of completed projects (i.e. construction complete). Projects still under construction will not be evaluated.

5.1.1.3 Each project summary must include the following for each project: a description/scope; picture/photo; firms on the proposed team that performed this project, construction contract award amount; final construction cost; location; date when the project was started; original contract finish date and actual finish date. Narratives of each project must include a brief overview of each project and its relevance to this solicitation. All summaries should contain the name, address, telephone number, and e-mail address of a representative of the owner (as well as one alternate individual not affiliated with your firm) familiar with your firm’s experience on the project that can verify the experience cited.

5.1.2 Standard for Acceptability. Evaluation will be based on the project summaries provided in the offeror’s proposal. To be rated acceptable, at least two of the project examples submitted must be similar in function, scope, complexity, and dollar value to this solicitation and clearly demonstrate the offeror’s abilities to execute the projects successfully while maintaining cost and schedule. Characteristics, such as size, complexity, dollar value, the number and types of trades employed, may be indicative of similarity. Projects that do not meet the similarity criterion identified above will be rated unacceptable for this factor. Projects that appear to have been performed by a Contractor’s office other than the regional office that will be performing the work will not be rated. Projects that are less than 75% complete will be not be rated. Projects cited which indicate the offeror was not the prime contractor or a subcontractor with more than 50% or more of the fuel related work will not count as one of the two required projects. Omission of requested information may result in an unacceptable rating.

5.2 VOLUME 1 – TAB B: FACTOR 2 – Past Performance.

This factor will evaluate each offeror’s demonstrated recent and relevant record of performance in completion of those projects identified in Tab A. The past performance is an indicator of the likelihood of the successful completion of the project by the offeror.

5.2.1 Submission Requirements. Submit information on the recent and relevant contracts identified in Factor 1, demonstrating your capability to perform the proposed effort in accordance with the RFP. The information submitted shall be in accordance with the following instructions:

5.2.1.1 The Past Performance Questionnaire (PPQ) included in the solicitation (Attachment 1) is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal. Ensure correct phone numbers and email addresses are provided for the client point of contact. Complete Past

Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contact and client information for the respective project(s).

Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government point of contract, CPT Jason Floyd via email at Jason.L.Floyd@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Also include performance recognition documents received within the last five (5) years, such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. The Past Performance Questionnaire (PPQ) will not be included in the page count. Format for Past Performance Questionnaire (PPQ) has been provided at the end of Section 00 22 11 titled: NAVFAC/USACE Past Performance Questionnaire (PPQ).

5.2.1.2 In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may be include, but are not limited to, CCASS, ACASS, past performance information retrieved through the Past performance Information retrieval System (PPIRS), including Contractor Performance Assessment Reporting Systems (CPARS), using all CAGE/DUNS number of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owners representatives(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.

5.2.1.3 While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate, and complete past performance information rests with the Offeror.

5.2.1.4 “Confidential” projects cannot be submitted unless all of the information required for evaluation purposes as specified herein can nonetheless be provided to the Government as part of the Offeror(s) technical proposal. Offeror(s) that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offeror(s)— Competitive Acquisition,” paragraph (e), “Restriction on disclosure and use of data.”

5.2.1.5 Past performance information pertaining to a proposed subcontractor cannot be…

This is the start of the file's text. The full file is on GovTribe.