Vendor_Questions_&_Responses.pdf
PDF 193 KB Posted
- Attached to
- 25-BG-15 -Riverside Park Pier Repair Project
- Solicitation number
- 25=BG-15
- Issued by
- Volusia County, Florida
About this file
This document is a Vendor Questions & Responses file for the City of Holly Hill, Florida's Riverside Park Pier Repair Project (25-BG-15). The project involves the removal and disposal of approximately 140 linear feet of damaged pier sections submerged in the Halifax River, followed by the installation of prefabricated dock sections supplied by the pier manufacturer. The work includes installing four fixed piers measuring 8' x 30' each and one fixed pier measuring 8' x 18', all equipped with composite timber decking, combination rail systems, and header kits. Additional scope includes shimming existing composite decking boards on remaining pier sections, replacing five LED bollard lights with electrical connections and testing, installing turbidity curtains and best management practices during construction, and restoring disturbed grounds upon completion. The project duration is 180 days for completion. No extension to the bid due date was granted despite vendor requests citing holiday scheduling conflicts.
The City of Holly Hill has already procured all fixed dock materials and will not consider alternate manufacturers or product substitution requests; bidding is for installation only in accordance with plans and specifications. All fasteners, including nails, screws, bolts, nuts, washers, and lags, must be grade 316 stainless steel, with dock washers measuring a minimum of 3-inch diameter for bolted connections. The contractor is responsible for removing and properly disposing of existing damaged pier sections, and liquidated damages of $500 per day apply if the project exceeds the 180-day completion timeline. Pier sections will be delivered with decking attached, while handrails will be shipped separately for on-site installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Audio_Bid_Opening_25-BG-15.mp3 | MP3 file | |
| Bid_Opening_Tabulation_Sheet.pdf | ||
| Riverside_Park_Pier_Repair__Pre-Bid_Sign-in.pdf | ||
| Pre-Bid_Meeting_Question_&_Answers_25-BG-15.docx | DOCX document | |
| Pre-Bid_Meeting_25-BG-15.mp3 | MP3 file | |
| Riverside_Park_Pier_Repair_Final_S.pdf | ||
| Addendum_2_-Riverside_Park_Pier_Repair_25-BG-15_.docx | DOCX document | |
| Addendum_1_Riverside_Park_Pier_Repair_.docx | DOCX document | |
| Riverside_Park_Pier_Repair_Plans.pdf | ||
| Riverside_Park_Pier_Repair_SJ.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VENDOR QUESTION/RESPONSES - 25-BG-15 - RIVERSIDE PARK PIER
November 25, 2025
1. Will the City of Holly Hill consider alternate manufactures for the fixed dock system? If so, and if they must be approved by the EOR prior to bidding can you provide a path to do so?
Response: The City has already ordered the fixed dock materials and will not accept alternate manufacturers for this project. The bidding is for installation only in accordance with the plans and specifications. Contractors are responsible for installation, and all incidental items noted in the bid documents. Product substitution requests will not be considered.
2. Due to the Thanksgiving Holiday and people taking vacations, Can you please extend the bid due date to Friday December 5, 2025?
Response: The City has reviewed the schedule and determined that the current bid opening date remains appropriate, as the solicitation period already offers adequate time for vendors to prepare and submit their bids.
3. Will the contractor be responsible for the cost of the pre-fab pier sections?
Response: The City has already ordered the fixed dock materials for this project. The bidding is for installation only in accordance with the plans and specifications. Contractors are responsible for installation, and all incidental items noted in the bid documents.
4. Will the pier sections include the decking and handrail attached?
Response: Yes, the pier section will delivered with decking attached, and the handrail will be shipped separately for on-site installation.
5. Are the existing pier sections to be demolished the property of the city or will they be disposed of at the proper landfill?
Response: It is contractor's responsibility to remove and replace the existing damaged pier sections and to be removed and properly disposed.
6. Please confirm the grade of all stainless hardware.
Response: All fasteners, including nails, screws, threaded rods, bolts, nuts, washers, plates, lags, etc. shall be grade 316 stainless steel (S.S.). Washers used with single-bolted or double bolted connections (for example: stringer to piling connection, cap board connections or cross-bracing) shall be minimum 3-inch diameter "dock washers". Standard washers for splice block and railings.
7. What is the duration of this project?
Response: The duration of the project will be 180 days for completion.
8. Will liquidated damages be applied to this project?
Response: Yes, $500 in liquidated damages over the past 180 days applied to this project.