Vendor Questions and Answers.pdf
PDF 91 KB Posted
- Attached to
- AML 2005 Cloverleaf No. 4 Shafts
- Solicitation number
- 21-422DNR-DIREC-B-20164
- Issued by
- Macon County, Illinois
About this file
This document is a Question and Answer document related to Bid #: 21-422DNR-DIREC-B-20164 for the AML 2005 Cloverleaf No. 4 Shafts project in the state of Illinois. The project involves remediation at the Clover Leaf No. 4 mine shaft located in Montgomery County. The document provides responses to two vendor questions - one regarding whether trees and brush can be forestry mowed in place (answer is no, they must be chipped or logged and hauled off) and another regarding whether the grass seed needs to be sampled and tested (answer is no, certification from the supplier indicating the grass seed meets specification will suffice).
The contract opportunity document indicates this is a state and local contract opportunity in the state of Illinois. No additional pricing terms, set asides, incumbents, funding requirements, or other salient information is provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2005 Cloverleaf Plan Set.pdf | ||
| AML2005 Bid Sheet 02.04.2021.pdf | ||
| Cloverleaf Specifications 02.04.21.pdf | ||
| Standard Business Terms and Conditions.pdf | ||
| Forms A Section V.18.1~10.docx | DOCX document | |
| Forms B V.20.1~43.docx | DOCX document | |
| Standard Certifications ~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTION AND ANSWERS
Bid #: 21-422DNR-DIREC-B-20164
Project Title: AML 2005 Cloverleaf No. 4 Shafts
• Question: Can we forestry mow/grind trees in place?
• Answer: Trees and brush are to be chipped or logged and hauled off site for disposal or recycling. Forestry mowing with material left in place will not be permitted.
• Question: Does the grass seed need sampled and tested? Or can we just provide the appropriate mix with tags?
• Answer: Sampling and testing of grass seed earmarked specifically for this project is not required. Certification from the supplier indicating the grass seed meets specification will suffice.