AML2005 Bid Sheet 02.04.2021.pdf

PDF 56 KB Posted

Attached to
AML 2005 Cloverleaf No. 4 Shafts
Solicitation number
21-422DNR-DIREC-B-20164
Issued by
Macon County, Illinois

About this file

This document is a bid sheet for the Clover Leaf No. 4 Mine Shaft Remediation project, a state and local contract opportunity in Illinois. The project entails various remediation activities, including special clearing, special excavation, concrete plug installation, seeding and mulching, and the installation of mine opening markers. The bid sheet lists the unit quantities and costs for these line items, as well as a lump sum item for mobilization/demobilization, which is capped at 15% of the total bid price. The bid due date is February 11, 2021, at 2:00 pm CST.

The bid sheet also includes notes indicating that quantities used will be paid according to the unit costs, and that the mobilization/demobilization item shall not exceed 15% of the total bid price. The contract opportunity is for the state of Illinois, with the project number AML-GMmE-2005.

View the file

Other files

File Type Posted
Standard Business Terms and Conditions.pdf PDF
Forms A Section V.18.1~10.docx DOCX document
2005 Cloverleaf Plan Set.pdf PDF
Cloverleaf Specifications 02.04.21.pdf PDF
Forms B V.20.1~43.docx DOCX document
Standard Certifications ~1.pdf PDF
Vendor Questions and Answers.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidsheet

A B C D E F

Item Bid Base Unit Cost

Num. Bid item Quantity Units per bid Subtotal

Quantity (CxE)

1 Special Clearing Lump Sum

2 Special Excavation 514 Cubic Yards

3 Class SI Concrete Plug 172 Cubic Yards

4 Seeding & Mulching 0.75 Acres

5 Mine Opening Marker 2 Each

6 Mobilization/Demobilization (See Note 2) Lump Sum

TOTAL

Firm Name:

Address:

Phone No.:

Project Name: Clover Leaf No. 4 Mine Shaft Remediation Project No.: AML-GMmE-2005

Date of Letting: February 11, 2021 at 2:00 pm CST

Notes:

1. Quantities used will be paid according to the unit costs.

2. Item 6 shall not exceed more than 15% of the total bid price.

Bidder's signature

File details come from the government source that posted it. Updated .