VA AMR Elec Bid Set Narrative.pdf
PDF 534 KB Posted
- Solicitation number
- 36C25723B0032
About this file
This design narrative describes the scope of work for a Department of Veterans Affairs project to provide a new primary electrical feed to Building 1 at the Thomas E. Creek VA Medical Center in Amarillo, Texas. The project involves designing and installing a new electrical service from the main switchgear to supply Building 1, including a new automatic transfer switch for generator power. It will also replace aging electrical equipment in Building 1, modernize the distribution voltage, and make the building electrically independent by removing its connections to Buildings 4, 7, and 8. The design will fully evaluate electrical loads and demands to size the new infrastructure accordingly. Minor architectural modifications and no structural changes are anticipated. The cost estimate for the base project is $2,329,006.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25723B0032 0003_1.docx | DOCX document | |
| 36C25723B0032 0003 VA Amarillo RFI Responses 040823.pdf | ||
| 36C25723B0032 0002_1.docx | DOCX document | |
| R311451 VA Amarillo - ADDENDUM A (RFI) 032923.pdf | ||
| 36C25723B0032 0001 Amendment.pdf | ||
| 36C25723B0032 0001_1.docx | DOCX document | |
| 36C25723B0032 Solicitation.pdf | ||
| VA AMR Elec Bid Set Drawings.pdf | ||
| VA AMR Elec Bid Set Specifications.pdf | ||
| 36C25723B0032_2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Design Narrative
A/E DESIGN PRIMARY ELECTRICAL FEED
TO BUILDING 1, AMARILLO, TX.
Prepared for
Department of Veterans Affairs
Thomas E. Creek VAMC
Amarillo, Texas
Project No. 504-21-120
Submittal Date: December 22, 2021
100% BID SET SUBMISSION
A/E DESIGN-PRIMARY ELECTRICAL FEED TO BLDG 1 100% BID SET SUBMISSION
THOMAS E. CREEK VAMC PROJECT NO. 504-21-120
AMARILLO, TX DECEMBER 22, 2021
THIS PAGE INTENTIONALLY LEFT BLANK
TABLE OF CONTENTS
GENERAL INFORMATION 1.0
Project Description 1.1
Design General Scope 1.2
BUILDING CODE & LIFE SAFETY REVIEW 2.0
Primary Applicable Codes & Standards 2.1
SITE DEVELOPMENT 3.0
Site Development Evaluation 3.1
ARCHITECTURAL 4.0
Building Exterior Evaluation 4.1
Building Interior Evaluation 4.2
INTERIOR DESIGN 5.0
Interior Design Development 5.1
STRUCTURAL 6.0
Overview 6.1
MECHANICAL 7.0
Overview 7.1
Codes and Standard 7.2
Mechanical Approach 7.3
PLUMBING 8.0
Codes and Standards 8.1
Existing Plumbing System 8.2
ELECTRICAL 9.0
Overview 9.1
Codes and Standards 9.2
Electrical Design Approach (Power) 9.3
Electrical Design Approach (Lighting) 9.4
TELECOM MUNICATIONS 10.0
Codes and Standards 10.1
Existing Conditions 10.2
Modifications to Existing Telecommunications 10.3
FIRE PROTECTION 11.0
Existing Conditions 11.1
Design Approach 11.2
Existing Egress Path 11.3
ASBESTOS ABATEMENT REPORT 12.0
Scope 12.1
CRITICAL PATH METHOD (CPM) 13.0
Phasing Narrative 13.1
COST ESTIMATE 14.0
Base Project 14.1
APPENDIX A1: QUALITY ASSURANCE / QUALITY CONTROL PLAN A1.0
Quality Assurance / Quality Control Overview A1.1
Section 1.0
GENERAL INFORMATION
1.1 PROJECT DESCRIPTION
A. CB Design Group, in collaboration with its consulting engineers, is providing professional services and documentation for schematic design, design development and construction documents for the
Thomas E. Creek VAMC Primary Electrical Feed to Building 1 (504-21-120) project at the
VAMC Amarillo (Amarillo, TX). Design for new electrical service to Building 1 and interior electrical modernization of Building 1 that can safely and efficiently handle the building’s foreseeable electrical demand and consumption. New electrical service to Building 1 and associated interior electrical distribution shall be designed and sized to meet VA and NEC standards. Evaluation of new infrastructure for design and construction shall include, but is not limited to, the following:
Verifying electrical demand and consumption requirements for all of Building 1 to include all existing electrical loads and the new AHU tower planned for future construction.
A new electrical service from the main switchgear to supply Building 1. Disconnecting electrical service from Building 4 to Building 1.
• A new ATS for generator power to Building 1.
• New panels, transformers, switches, conduit, wiring, etc. associated with the new electrical service inside Building 1. This includes all emergency panelboards and transformers in electrical room 1163. The panelboards are the old Westinghouse panelboards and CBs are very expensive and are not HACR rated. The equipment appears to be original and needs to be replaced. In room 1127 there are several old transformers that step down 480V to 120/240 3 phase. T.E.C. VAMC desires a uniform voltage in Building 1, instead of 120/208 3 Phase in parts of the building and 120/240 3 Phase in other parts.
• Removal of all panels, transformers, switches, conduit, wiring, etc. associated with demolition of the old electrical service inside Building 1.
• Removing any power to Building 7 from Building 1 and finding another source for this power. New generator power will be brought from Building 20 to Building 7 and an automatic transfer switch will be installed in Building 7. The UPS circuit from Building 1 to Building 7 will be removed and a new UPS will be installed in Building 7. Building 7 needs to be self-sufficient in all electrical aspects.
• Removing any power to Building 8 from Building 1 and finding another source for this power. Building 8 needs to be self-sufficient in all electrical aspects.
• This project will impact the entire building and shall be completed without adversely affecting hospital operations.
B. Submissions shall comply with the AE submission instruction for Minor and NRM Construction programs Program Guide PG-18-15, volume C, with respect to Schematic Design, Design
Development and Construction Documents.
1.2 DESIGN GENERAL SCOPE
A. CB Design Group has reviewed the requirements of this phase of work and has prepared 100% concept design narrative for review and approval by the West Texas VACHS in accordance with
Supplement B, Statement of work.
[END OF SECTION]
Section 2.0
BUILDING CODE & LIFE SAFETY REVIEW
2.1 PRIMARY APPLICABLE CODES AND STANDARDS
A. The Department of Veterans Affairs has adopted the latest edition of the following codes and standards as a minimum for all projects performed in the modernization, alteration, addition, or improvement of its real property and the construction of new structures. VA design Manuals and
Master Specifications specify other codes and standards that VA follows on its projects:
1. VA Directives, Design Manuals, Master Specifications, VA National CAD Standard
Application Guide, and other Guidance on the Technical Information Library (TIL)
(http://www.cfm.va.gov/til/) including but not limited to:
a. VA PG-18-01, Master Construction Specifications
b. VA PG-18-03, VA Design and Construction Procedures
c. VA PG-18-04, Standard Details
d. VA PG-18-05, Equipment Guide List
e. VA PG-18-09, Planning Criteria for Medical Facilities
f. VA PG-18-13, Barrier Free Design Handbook (2017)
g. VA PG-18-14, Room Finishes, Door & Hardware Schedule (2017)
h. VA PG-18-15, Minimum Requirements for A/E Submissions
2. International Building Code (IBC) (Only when specifically referenced in VA Design
Documents, see notes below).
3. NFPA 101 Life Safety Code, 2018 Edition.
4. NFPA National Fire Codes with the exception of NFPA 5000 and NFPA 900.
5. Occupational, Safety and Health Administration (OSHA) Standards.
6. National Electrical Code (NEC).
7. International Plumbing Code (IPC).
8. Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free Design Guide (PG-18-13).
9. Energy policy Act of 2005 (EP Act).
10. DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and Multi-Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435.
11. Federal Leadership in High Performance and Sustainable Buildings: Memorandum of
Understanding (MOU).
12. Executive Order 13423: Strengthening Federal Environmental, Energy, and
Transportation Management.
B. Local Codes: As an agency of the federal government, VA is not subject to local imposition of code enforcement procedures (drawing reviews, building permits, inspections, fees, etc.). VA must function as the Authority Having Jurisdiction (AHJ) and thus has the responsibility to guard public health and safety through enforcing its adopted codes. However, local authorities should be notified about planned projects and given opportunity to review drawings provided that VA does not pay for review or inspection fees.
Section 3.0
SITE DEVELOPMENT
3.1 SITE DEVELOPMENT EVALUATION
A. Analysis of Site:
1. The project site will be minimally impacted by the project. Trenching between Building #35 and building #7 will be necessary to run necessary and will partially occur on parking lot D parallel to N. Edman rd. (Alternate #1).
2. Trenching between Building #1 and Building #4 will be necessary to install the new 480V service feeds duct bank.
Section 4.0
ARCHITECTURAL
4.1 BUILDING EXTERIOR EVALUATION
1. Modifications to the building exterior is only expected to include closing a few of the windows on the first floor where they are within 10’-0” from the new transformer locations. This will involve demolition of existing windows and filling the window spaces using similar material as the existing adjacent construction. Windows openings in the interior side of Building #1
Physical Therapy room (#1115) will be infilled with metal studs and drywall and painted to match adjacent walls finishes.
4.2 BUILDING INTERIOR EVALUATION
1. Minor modifications will be required in the existing electrical rooms to accommodate new electrical service equipment. New finishes will be provided Patch and repair will be minimum but required and will match the finish on the existing walls.
Section 5.0
INTERIOR DESIGN
5.1 INTERIOR DESIGN DEVELOPMENT
A. General Description:
1. Room finishes, Doors, and Hardware shall be in accordance with VA Program Guide
PG18-14.
2. New finishes (wall, ceiling, and floor) will be added where existing windows are removed and infill placed, and where other spaces are modified to accommodate new electrical equipment run and/or installation.
B. Interior Walls:
1. New walls will be metal framing (using 3-5/8” studs) with 5/8-inch gypsum wallboard. Walls will be designed to meet rating requirements of applicable codes.
C. Ceilings:
1. Existing ceilings are primarily 2x4 acoustical tile. Ceiling systems in the project area will be modified / added to accommodate changes to existing spaces.
D. Floors:
1. New flooring are to match existing and will be added to provide a complete floor where and if needed.
2. Room Finishes anticipated to match existing condition:
a. Flooring / Base: vinyl base.
b. Wall Finish: Painted gypsum board
c. Doors: Wood
d. Door Frames: Painted Hollow Metal
e. Ceiling: Acoustical Ceiling Tiles
Section 6.0
STRUCTURAL
6.1 SCOPE
Modification of the existing structure is not anticipated at this time and structural engineering services are not currently anticipated as part of this project.
Section 7.0
MECHANICAL
7.1 OVERVIEW
Additions or alterations to the existing mechanical HVAC systems is not anticipated for this project nor it is part of the scope of work.
[End of Chapter]
Section 8.0
PLUMBING
8.1 OVERVIEW
Additions or alterations to the existing plumbing systems is not anticipated for this project nor it is part of the scope of work.
CHAPTER 9.0
ELECTRICAL
9.1 OVERVIEW
The project Scope of Work is to provide new electrical service to Building 1 from existing primary voltage distribution, separation of Building 1 electrical systems and Building 4 electrical systems.
Also, the separation of Building 1 service from services to buildings 7 and 8.
9.2 CODES AND STANDARDS
The following is a list of VA and other design and construction criteria that shall be utilized by the
A/E for the development of the design of this project:
• PG-18-1, Master Construction Specification Index
• PG-18-3, Design and Construction Procedures
• PG-18-10, VA Design Manuals
• UFC 3-600-01,
• ANSI C2, National Electrical Safety Code
• IEEE 141, Recommended Practice for Electrical Power and Distribution for Industrial
Plants
• IEEE 142, Recommended Practice for Grounding of Industrial and Commercial Power
Systems
• NFPA 70, National Electrical Code
9.3 ELECTRICAL DESIGN (POWER)
1. Building 1
a. The Building 1 existing electrical distribution is provided by several circuit breakers in two distribution panels located in Building 4.
b. Building 4 existing electrical distribution is provided by two exterior pad mounted transformers fed by medium voltage distribution circuits fed from metal clad switchboards located in Building 39.
c. The two medium voltage distribution circuits feeding Building 4 will be tapped in a nearby electrical manhole and the circuits will be extended to two new pad mounted transformers exclusively feeding new distribution for Building 1.
d. The new transformers will feed a new exterior switchboard with a main-tie-main configuration.
i. This switchboard will be sized and circuit breakers provided to accommodate existing Building 1 loads. Spaces will be provided for future Building 1 air handling tower.
e. All automatic transfer switches will be replaced. The fire pump controller/transfer switch will remain.
f. All older Westinghouse panels and transformers in Building 1, rooms 1127, 1129, and 1163 will be replaced.
g. All 240 VAC panels in building 1 and associated 480V- 240/120V transformers will be replaced with 480V-208/120V transformers and panels. All multipole loads on these panels will be evaluated to determine compatibility with 208
Volts.
2. Building 7
a. The Building 7 electrical service is fed from a single phase medium voltage distribution circuit fed from metal clad switchboards located in Building 39. The circuit breaker in the switchboard in Building 39 is three-phase with only on phase being used. The existing single phase cable will be removed from the existing underground raceway and replaced with a new three conductor medium voltage cable.
b. A new 150 KVA 13.2 KV to 480/277V, 3-phase, loop feed transformer will be provided for Building 7. The primary feeder will be extended to Building 8. A new 480/277V service will be provided for Building 7.
c. As an Additive Alternate, the service Building 7 will be provided with an automatic transfer switch and generator circuit from Building 20.
d. The existing UPS circuit from Building 1 to Building 7 will be removed and a new 30 KVA UPS will be installed in Building 7 and be connected to the existing
UPS panel in Building 7.
3. Building 8
a. Building 8 service is fed from a 480 volt, 3 phase circuit from Building 1. This circuit feeds an exterior dry type 150KVA transformer. This existing circuit from
Building 1 and transformer will be removed.
b. The new medium voltage circuit feeding Building 7 will be extended from the loop feed transformer and used to feed a new 13.2KV-208/120V, 150 KVA pad mounted transformer near Building 8. The secondary will be used to re-feed the existing Building 8 panels.
9.4 ELECTRICAL DESIGN (LIGHTING)
Existing lighting and control is adequate for the existing spaces and appears to meet requirements if the Lighting Design Manual. Modifications to the existing lighting and controls in the affected space is not anticipated.
CHAPTER 10.0
TELECOMMUNICATIONS
10.1 OVERVIEW
Modifications to existing telecommunications systems is not anticipated at this time.
CHAPTER 11.0
FIRE PROTECTION
11.1 EXISTING CONDITIONS
Modifications to existing fire protection systems is not anticipated for this project.
11.2 DESIGN APPROACH
Existing sprinkler heads will remain in place and be protected while work is completed.
11.3 EXISTING EGRESS PATHS
Existing egress path will not be disrupted during this project.
CHAPTER 12.0
ASBESTOS
12.1 SCOPE
The design team has requested but not yet received any HazMat survey information from the
VAMC and does not anticipate this to be within its scope of work.
CHAPTER 13.0
CRITICAL PATH METHOD (CPM)
13.1 PHASING NARRATIVE
1. It is currently anticipated that the work will proceed under four phases and sub-phases.
Refer to Sheet E-010 for details of project phasing
CHAPTER 14.0
COST ESTIMATE
14.1 BASE PROJECT
GENERAL DESCRIPTION: VA estimated the construction contract cost to be $1,5M.
OCMI cost estimates:
• 17 September 2021 - 95% CD Submission: $2,177,917 o Alternate #1: $334,239
• 11 November 2021 - 100% CD Submission: $2,329,006 o Alternate #1: $273,439
APPENDIX A1
QUALITY ASSURANCE / QUALITY CONTROL
PLAN
A1.1 QUALITY ASSURANCE / QUALITY CONTROL
OVERVIEW
The Construction Specifications Institute (CSI) defines quality assurance (QA) during design as “the procedures for guarding against defects before and during the execution of the work.” Quality Control
(QC) during design is defined by CSI as “the procedures for evaluating completed activities and elements of the design for conformance with requirements.” CB Design follows basic principles we have developed over many years of practicing architecture.
Do It Right the First Time
• Quality is achieved not by merely finding mistakes and correcting them, but by refining the process over time to prevent mistakes from happening in the first place. Our Quality Control committee meets regularly to discuss issues, procedures and guidelines to improve our process.
Never Make the Same Mistake Twice
• Before drawings are released, we use checklists composed of issues that have been addressed and resolved on similar projects. At the project kick off we gather your lessons learned and integrate them into our QA/QC checklist, so we don’t repeat mistakes of pervious teams.
Two Heads Are Better Than One
• At the completion of each phase of the work, the drawings and specifications are reviewed by our Design Review Committee. A fresh set of eye can uncover issues which need further clarification.
Execution
• All team members do internal QA/QC checks before sending their drawings and specifications to CBDG for overall coordination and final QC check.
• CBDG maintains and adds to a QC Manual that is shared between team members. This has been developed over our many years of experience.
QUALITY ASSURANCE
QA starts with hiring qualified staff and continually training staff to be current with the latest design and construction technologies. For project specific QA, the first step is to review and understand the owner’s program and seek clarification on any ambiguities.
Other QA processes include:
• Assigning a Project Manager/Architect throughout the lifecycle of the project
• Reviewing codes
• Reviewing regulatory agency regulations, ordinances, standards
• Reviewing owner’s design guidelines
• Participating in regular coordination and progress meetings
• Reviewing owner provided information
• Reviewing consultant provided information
• Teaming with qualified consultants
QUALITY CONTROL
CB Design implements several quality processes at each phase of the design that fall within the area of
QC, including:
• Principal level involvement throughout each phase of the project
• Reviewing cost estimates to ensure project design aligns with budget
• Internal reviews of design and design documents
• Code plan reviews by each discipline lead
• Using AIA Document D200 – Project Checklist
• Using project specific checklist based on owner’s requirements (Supplement B to SF 252)
[End of Appendix A1]