USMMA FACILITIES PAINTING ATTACHMENT B.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- DORMITORY BUILDINGS INTERIOR REPAINTING Federal contract opportunity
- Solicitation number
- 693JF724Q000002
About this file
This document provides details for a federal contract solicitation to re-paint interior spaces in two dormitory buildings at the United States Merchant Marine Academy totaling approximately 109,000 square feet. The solicitation seeks to re-paint all hallways, stairwells, dorm rooms, bathrooms, and designated basement areas in Jones Hall and Barry Hall. The solicitation was issued by the Department of Transportation Maritime Administration for the Dormitory Buildings Interior Repainting project. The solicitation includes re-painting of floors 1, 2 and 3 in both buildings, which contain approximately 26 to 34 dorm rooms per floor, as well as designated common areas and basement level spaces.
View the file
Other files for this federal contract opportunity
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet2
| Task Name | Duration | Start | Finish | Notes | |
| BARRY/JONES HALL PAINTING | 26 WEEKS | 12/21/23 | 6/28/24 | ||
| Acquisition | |||||
| Solicitation Close Out | 1 DAY | 12/8/23 | 12/8/23 | ||
| Contract Awarded | 8 DAYS | 12/11/23 | 12/20/23 | ||
| Kick-Of Meeting | 1 DAY | 12/20/23 | 12/20/23 | ||
| Mobilization | 1 DAY | 12/21/23 | 12/21/23 | ||
| Phase 1 (Main Deck) | Barry & Jones | ||||
| Furniture Move (21,26,27,28 DEC) | 4 DAYS | 12/21/23 | 12/28/23 | 27 Rooms each (Barry & Jones) | |
| Dorm Rooms only | 4 DAYS | 12/21/23 | 12/28/23 | 2 bunk beds, 2 sm dressers, 2 wardrobes | |
| Painting (21,26,27,28 DEC) | 4 DAYS | 12/21/23 | 12/28/23 | ||
| Dorm Rooms, showers & | |||||
| storage | 4 DAYS | 12/21/23 | 12/28/23 | 27 Rooms, 2 showers, 2 bathrooms ea |
(Barry & Jones)
| Phase 2 (2nd Deck) | Barry & Jones | ||||
| Furniture Move | 5 DAYS | 3/11/24 | 3/15/24 | Barry- 31 rooms, Jones- 32 rooms | |
| Dorm Rooms only | 5 DAYS | 3/11/24 | 3/15/24 | 2 bunk beds, 2 sm dressers, 2 wardrobes | |
| Painting | 5 DAYS | 3/11/24 | 3/15/24 | ||
| Dorm Rooms, showers & | |||||
| storage | 5 DAYS | 3/11/24 | 3/15/24 | Barry- 31 rooms, Jones- 32 rooms, |
2 showers, 2 bathrooms
| Phase 3 (3rd Deck) | Barry & Jones | ||||
| Furniture Move | 5 DAYS | 6/24/24 | 6/28/24 | ||
| Dorm Rooms only | 5 DAYS | 6/24/24 | 6/28/24 | 2 bunk beds, 2 sm dressers, 2 wardrobes | |
| Painting | 5 DAYS | 6/24/24 | 6/28/24 | ||
| Dorm Rooms, showers & | |||||
| storage | 5 DAYS | 6/24/24 | 6/28/24 | Barry- 33 rooms, Jones- 32 rooms, |
2 showers, 2 bathrooms
| Period of Performance | 40 DAYS | 3/15/24 | 6/28/24 | Barry & Jones |
| Jones Hallways- All Floors | 6 DAYS | |||
| Jones Stairwells- All Floors | 7 DAYS | |||
| Jones Zero Deck | 9 DAYS | |||
| Hallways | 3 DAYS | |||
| Laundry Room | 2 DAYS | |||
| IT Room | 2 DAYS | |||
| Post Office | 3 DAYS | |||
| Barry Hallways- All Floors | 6 DAYS | |||
| Barry Stairwells- All Floors | 7 DAYS | |||
| Barry Zero Deck | 5 DAYS |
| Punch List |
| Walk Through |
| Review |
| Close |