Attachment B Updated Amend1 USMMA FACILITIES PAINTING- BARRY JONES ATTACHMENT B.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
DORMITORY BUILDINGS INTERIOR REPAINTING
Solicitation number
693JF724Q000002
Issued by

About this file

This document includes an attachment to a solicitation for interior repainting services at two dormitory buildings on a maritime academy campus. The solicitation seeks repainting of approximately 109,000 square feet of interior space in Barry and Jones Halls, including 82 and 85 dorm rooms respectively across four floors, along with hallways, stairwells, shower rooms, bathrooms, and basement areas. The selected contractor will be responsible for furniture removal and reinstallation, painting, and a two-week punch list period following completion. The period of performance is 60 days from June 24 to August 23, 2024. The soliciting agency is the Department of Transportation Maritime Administration.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet2

Task NameDurationStartFinishNotesAmendment one
BARRY/JONES HALL PAINTING6/24/249/13/24(Punch List starts 08/26/2024)
MOBILIZATION
Phase 1 - JONES10 DAYS6/24/247/8/2482 Rooms
Furniture MoveNote: Wardrobes, bunk beds moved to center of room
Dorm Rooms only2 bunk beds, 2 sm dressers, 2 wardrobes
Painting
Dorm Rooms82 Rooms
Phase 2 - BARRY10 DAYS7/8/247/19/2485 Rooms
Furniture MoveNote: Wardrobes, bunk beds moved to center of room
Dorm Rooms only2 bunk beds, 2 sm dressers, 2 wardrobes each room
Painting
Dorm Rooms85 Rooms
Period of Performance60 days6/24/248/23/24
Jones Stairwells- All Floors(3) STAIRWELLS

Schedule to be Coordinated with COR

Jones Zero DeckUnrestricted Access
HallwaysUnrestricted Access
Laundry RoomUnrestricted Access
IT RoomSchedule to be Coordinated with COR
Post OfficeSchedule to be Coordinated with COR
Jones- Hallways, Shower Rooms, Bathrooms, Baggage Rooms- All Floors6 Shower Rooms, 6 Bathrooms
Barry Stairwells- All Floors(2) STAIRWELLS

Schedule to be Coordinated with COR

Barry Zero DeckUnrestricted Access
BARRY- Hallways, Shower Rooms, Bathrooms, Baggage Rooms- All Floors6 Shower Rooms, 6 Bathrooms
Punch List15 DAYSBARRY & JONES HALLS
Site Walk Through2 DAYS8/26/248/27/24
Review3 DAYS8/28/248/30/24
Close- Work Complete10 DAYS9/2/249/13/24Any corrective actions