This Request for Proposals (RFP) is issued by Universal EV LLC for a design-build DC fast charging (DCFC) station to be installed at Dover Inn Motel & Cabins located at 1545 Donelson Pkwy, Dover, Tennessee 37058, in Stewart County. The project requires the contractor to furnish two dual-port DC fast charging dispensers rated at minimum 180 kW each, with all four ports capable of simultaneous charging for a combined 360 kW total capacity. Equipment must include CCS1 connectors at minimum, OCPP 2.0.1 network protocol compatibility, UL 2202/CSA C22.2 No. 107.1 listing, open-access payment options (contactless credit/debit, RFID, and QR code), and four EV stalls (three standard and one ADA-accessible). The scope encompasses complete engineering design by a Tennessee-licensed professional engineer, site survey and geotechnical investigation, utility coordination with Cumberland Electric Membership Corporation, permitting and inspections with the local Authority Having Jurisdiction, civil work including foundations and paving, electrical infrastructure, commissioning, and five-year warranty and operations/maintenance services. The RFP was issued October 27, 2026, with a questions deadline of November 10, 2026, and proposal submission deadline of November 17, 2026. The anticipated award date is December 16, 2026, with construction scheduled to commence March 1, 2027, and substantial completion targeted for April 30, 2027. Pre-bid site visits are available upon request. The contract will be a fixed-price lump sum with progress payments based on verified completion and 10 percent retainage until final acceptance.

The pricing structure requires an itemized line-item cost proposal with a separate line item for all utility costs (application fees, make-ready, and any required upgrades), all of which are included within the lump-sum price. Contractor qualifications must include a valid Tennessee electrical contractor license, employment of a Tennessee-licensed professional engineer to seal design documents, EVITP Installer Certification for at least one lead electrician or superintendent, minimum two years of DCFC installation experience, minimum three completed DCFC projects with references, and demonstrated utility coordination experience. Required insurance includes commercial general liability of $2,000,000 per occurrence/$4,000,000 aggregate, workers compensation per Tennessee law, automobile liability of $1,000,000 combined single limit, and professional liability of $1,000,000 per claim/$2,000,000 aggregate, with Universal EV LLC named as additional insured. The evaluation criteria weigh price at 30 percent, design capability and utility coordination at 15 percent, DCFC experience and references at 15 percent, technical approach and construction methodology at 10 percent, five-year O&M plan quality at 10 percent, five-year SLA commitments at 10 percent, qualifications and certifications at 5 percent, and project schedule at 5 percent. The contractor must comply with incentive program requirements if the Owner pursues state or utility funding, maintain accessibility standards per ADA and U.S. Access Board recommendations, ensure open access with no membership requirements, and maintain the active motel operations by preserving guest and emergency vehicle access throughout construction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Universal EV LLC | DCFC Design-Build RFP | 1545 Donelson Pkwy, Dover, TN 37058

Confidential — For Bidding Purposes Only | Page 1 of 18

REQUEST FOR PROPOSALS

EV Charging Station — Design-Build, Turnkey Supply, Installation, Operations, Maintenance & Service Level Agreement

DC Fast Charging (DCFC) Project State and/or utility incentive program requirements may apply (see Section 8)

Dover Inn Motel & Cabins

1545 Donelson Pkwy, Dover, TN 37058

Issued by: Universal EV LLC 5600 Tennyson Parkway, Suite 140, Plano, TX 75024

Contact: proposal@universalgreengroup.com | (214) 989-4173

RFP Issue Date October 27, 2026

Questions Deadline November 10, 2026

Proposal Submission Deadline November 17, 2026

NOTICE

The Contractor — not the Owner — is responsible for the complete engineering design packet for this Project.

Confidential — For Bidding Purposes Only | Page 2 of 18

SECTION 1 — INTRODUCTION AND BACKGROUND

Universal EV LLC ("Owner") is issuing this Request for Proposals (RFP) to select a qualified General Contractor ("Contractor") to deliver a turnkey, design-build DC fast charging (DCFC) station at the Site described herein. The Contractor will provide charger placement and site layout, the complete engineering design packet, utility design coordination, permitting, procurement and installation of all equipment and materials, commissioning, and the 5-year warranty, operations and maintenance (O&M), and service level agreement (SLA) that follow energization.

Design responsibility. On prior Universal EV projects, the Owner furnished stamped engineering drawings. On this Project, the Contractor is responsible for the complete engineering design packet, sealed by a professional engineer licensed in the State of Tennessee. No engineering drawings have been prepared for this Site; the Owner's conceptual layout is described in Section 2.3 for information only and is not a construction document.

Universal EV LLC is committed to a fair and open competitive process. All qualified contractors are encouraged to submit proposals.

OWNER-FURNISHED ITEMS NOTICE

Owner provides network/OCPP services only, unless Tesla Supercharger equipment is proposed by the Contractor and approved by the Owner, in which case Tesla provides network/OCPP services.

ALL other design, engineering, equipment, materials, labor, permits, utility fees, and services are contractor-furnished.

Confidential — For Bidding Purposes Only | Page 3 of 18

SECTION 2 — PROJECT OVERVIEW

2.1 Site Information

Site Name Dover Inn Motel & Cabins

Site Address 1545 Donelson Pkwy, Dover, TN 37058

County Stewart County, Tennessee

Site Host Universal EV LLC

Permitting Jurisdiction The applicable local Authority Having Jurisdiction (AHJ)

Utility Company Cumberland Electric Membership Corporation

Existing Service Existing 3-phase utility pole at the edge of the property; new or upsized pad-mounted transformer and meter proposed in the Owner's conceptual layout

Project Delivery Method Design-Build — Contractor provides the engineering design packet

Reference Design None — Owner's conceptual layout only (Section 2.3)

2.2 Full Scope of Work (Design-Build)

The Contractor shall provide all design, engineering, labor, equipment, materials, permits, fees, and services required to deliver a complete, operational, code-compliant DCFC station, including without limitation:

A. Engineering Design Packet

• Site survey (as needed to locate existing improvements, utilities, property boundaries, and the service route) and geotechnical investigation (as needed to design foundations and paving), performed by the Contractor.

• Complete construction document set sealed by a professional engineer licensed in Tennessee, including: site and charger layout, accessible stall and route design, grading and drainage as needed, foundation and structural details, electrical one-line and three-line diagrams, load calculations, short-circuit and voltage-drop calculations, conduit and conductor schedules, grounding design, signage and striping plan, lighting evaluation, and equipment data sheets.

• Incorporation of Cumberland Electric Membership Corporation service requirements and AHJ plan-review comments.

• Submittals per the milestones in Section 2.6; Owner written approval of the final design is required before construction begins.

• Final as-built redline drawings (civil and electrical) at close-out.

B. Utility Design Coordination

• Contractor is the single point of contact with Cumberland Electric Membership Corporation

(CEMC) for the service application, load information, transformer sizing and pad requirements, primary extension from the nearest 3-phase pole, metering requirements, easements, make-ready, and energization scheduling.

Confidential — For Bidding Purposes Only | Page 4 of 18

• Service arrangement and capacity: the Owner's conceptual layout contemplates a new or upsized pad-mounted transformer and meter near the charger area, fed from the existing 3-phase utility pole. Contractor must confirm the actual arrangement and capacity with CEMC (reference charger input is approximately 192 kVA per charger, about 384 kVA combined). Any transformer, pole, primary extension, conductor, or service upgrade required is included in the lump-sum price.

• All utility application fees, charges, contributions, and make-ready costs are included in the lump-sum price and must be shown as a separate line item in the itemized cost proposal (see Section 6).

C. Permitting and Approvals

• All permits, plan review, inspections, and approvals required by the applicable local AHJ and any other authority having jurisdiction; Owner will sign as applicant where required.

• Underground utility locates (Tennessee 811) and protection of existing utilities and site improvements.

D. Civil Work

• Per the Contractor's final design; expected to include concrete charger slab foundations, steel pipe bollards on concrete footings, transformer and equipment pads, trenching and backfill, new paving or surface preparation as needed, EV stall striping, and an accessible EV stall with access aisle and accessible route. All paving, grading, and striping needed for a compliant installation are included in the lump-sum price.

• Site restoration to pre-construction condition or better.

E. Electrical Infrastructure

• Service equipment and metering per CEMC requirements (transformer, meter, main service disconnect), charger disconnects and overcurrent protection, feeders, conduit, wireway, grounding, and all charger power connections.

• Required labeling, emergency disconnect or shutoff provisions as required by code or the final design, and any site lighting required by the design or AHJ.

F. EVSE Equipment

• Furnish, install, configure, and commission all charging equipment meeting the performance minimums in Section 2.4, including connection to Owner's network/OCPP services.

G. Signage, Striping, and Site Finishing

• EV parking and "no parking except for electric vehicle charging" signage, accessible EV charging ("Use Last") signage, electrical hazard and caution labeling, pricing and payment signage as required, pavement striping, and bollards.

H. Commissioning, Testing, and Close-Out

• Functional testing of every port, network connectivity verification, utility energization, Owner acceptance walk-through, and delivery of all close-out documents listed in Section 10.

I. Warranty, O&M, and SLA

• 5-year warranty, O&M plan, and SLA per Section 3, beginning at Owner's written acceptance of commissioning.

Confidential — For Bidding Purposes Only | Page 5 of 18

2.3 Owner's Conceptual Layout (No Reference Drawings)

NO ENGINEERING DRAWINGS PROVIDED — CONCEPTUAL LAYOUT ONLY

No engineering drawings or design packet have been prepared for this Site. The Owner has prepared a conceptual site plan, summarized below, solely to communicate its general intent. It is not to scale, is not an engineering document, and is not a substitute for the Contractor's design.

The Contractor is solely responsible for the site survey, all engineering, and the accuracy, completeness, and code compliance of its design packet. The Contractor may propose a different layout, provided the performance minimums in Section 2.4 are met and the Owner approves. Owner review or approval of any submittal does not relieve the Contractor of design responsibility.

Conceptual Layout Summary

EVSE (2) dual-port DC fast charging dispensers, located as described below

Charger location At the edge of the motel parking area, adjacent to open ground on the highway-frontage side of the main building

Transformer and meter Pad-mounted transformer (new or upsized per the utility) and meter proposed beside the charger area, on the side nearest the utility pole

Utility service Existing 3-phase utility pole at the edge of the property, set back from the charger area. The primary service route between the pole and the transformer is to be determined by the Contractor and CEMC

Stalls (4) EV stalls: (3) standard and (1) accessible with access aisle; layout by the Contractor

Surface conditions Existing surface at the charger location is to be verified by the Contractor. All paving, grading, striping, and accessible route required for a compliant installation are included in the lump-sum price

Engineering data None provided. The Contractor performs the survey, geotechnical investigation as needed, load calculations, and complete design

Confidential — For Bidding Purposes Only | Page 6 of 18

2.4 Equipment Requirements — Performance Minimums

The reference model is not a mandatory brand. Contractor proposes equipment that meets or exceeds the minimums below; Owner approves the equipment at design review.

Item Minimum Requirement

Dispensers Minimum (2) dual-port DC fast charging dispensers; each dispenser rated at least 180 kW (power sharing between its two ports is permitted)

Simultaneous charging All 4 ports must be able to charge vehicles at the same time; minimum 360 kW total station capacity (2 x 180 kW)

Reference model ABB Terra 184 dual-port (180 kW). ABB Terra 184 or an approved equal is acceptable. Tesla equipment is not required but may be proposed

Connectors CCS1 on every port at minimum. NACS-capable equipment may be proposed, provided CCS1 is also supplied

Listings and standards UL 2202 / CSA C22.2 No. 107.1 listed; UL 2231-1 and 2231-2 personnel protection; outdoor rated, NEMA 3R minimum

Network protocol OCPP 2.0.1; compatible with Owner's network/OCPP services

Payment and access Open access — no membership or app required; contactless credit/debit (EMV/NFC) and RFID; QR code payment; pricing displayed prior to session start

Electrical service 277/480 V, 3-phase

EV stalls Minimum (4) EV stalls: (3) standard and (1) accessible with access aisle, per ADA and applicable Tennessee accessibility requirements; final layout per Contractor's design and Owner approval

Serviceability Manufacturer parts and support available in the U.S.; remote monitoring and diagnostics

A proposal that offers equipment other than the reference model must include the manufacturer data sheet and a written comparison showing equal or better power, listings, warranty, and serviceability.

Owner decides on equipment acceptability in its sole discretion at or before design review.

2.5 Owner-Furnished Items

• Network services and OCPP connectivity — provided by Universal EV LLC, unless Tesla

Supercharger equipment is proposed and approved, in which case Tesla provides network/OCPP services. The Contractor configures and commissions the chargers to connect to the network at no additional cost.

• Everything else — all design, equipment, materials, labor, permits, utility fees, and services — is contractor-furnished.

Confidential — For Bidding Purposes Only | Page 7 of 18

2.6 Design Submittal Milestones

Milestone Requirement Timing

Design kickoff, site survey, and site verification

Site survey and geotechnical investigation as needed; confirm existing conditions, utility service point, loads, and equipment selection

Within 10 business days of Notice to Proceed

Utility application Submit application and load information to CEMC; provide copy to Owner

Within 10 business days of Notice to Proceed

60% design submittal Layout, single-line, equipment data sheets, utility correspondence

Per Contractor schedule;

Owner review within 5 business days

Final stamped design packet

PE-sealed set for permit; Owner written approval required

Owner review within 5 business days; no construction before approval

Permit submission Submit to AHJ; provide permit status to Owner weekly

Upon Owner approval of final design

2.7 Site Verification and Bidder Diligence

• Each proposer is responsible for examining the Site and verifying existing conditions before submitting a proposal, including surface and subsurface conditions, access, available space, utility locations and service points, and local permitting and utility requirements. A pre-bid site visit is available on request (Section 9.4).

• Each proposal is deemed to be based on the proposer's own verification. The Owner makes no representation that the conceptual layout fully describes site conditions.

• The lump-sum price includes all costs of existing and concealed conditions, including rock, unsuitable soil, groundwater, buried or abandoned utilities and structures, and changes in utility requirements identified during design. No additional compensation or schedule relief will be granted for such conditions, except where the Owner changes the scope of work.

• The Contractor performs, at its own cost and within the lump sum, the site survey, geotechnical investigation as needed, Tennessee 811 locates, and private utility locating needed to complete the design.

• Questions about site conditions must be submitted in writing by the questions deadline in Section 11.

This RFP is based on the Owner's conceptual site plan only; no engineering drawings have been prepared for this Site. All bidders are responsible for verifying all site conditions before submitting a proposal.

Confidential — For Bidding Purposes Only | Page 8 of 18

SECTION 3 — WARRANTY, O&M, AND SERVICE LEVEL

AGREEMENT

The 5-year warranty, O&M, and SLA terms begin on the date of Owner's written acceptance of commissioning.

3.1 5-Year Equipment, Design, and Installation Warranty

• All EVSE equipment: minimum 5-year warranty

• All electrical infrastructure and civil work: minimum 5-year warranty

• Design warranty: Contractor warrants that its engineering design is free of errors and omissions and complies with applicable codes

• 24/7 warranty service, with critical fault response within 4 hours

3.2 5-Year O&M Plan

• Quarterly scheduled preventive maintenance, minimum

• 24/7 remote monitoring

• Software and firmware updates included

• Monthly O&M reporting to Owner, including uptime by port, faults, and maintenance performed

3.3 5-Year Service Level Agreement (SLA)

SLA Metric Minimum Requirement

Station uptime per port per month 97%

Critical fault — remote response Within 30 minutes

On-site technician dispatch Within 24 hours

Fault resolution Within 72 hours

Preventive maintenance Quarterly minimum

Help desk / driver support 24/7/365 — English and Spanish

Software/firmware updates Included

Monthly uptime reporting Required

Confidential — For Bidding Purposes Only | Page 9 of 18

SECTION 4 — APPLICABLE CODES AND STANDARDS

The Contractor's design and construction must comply with the following, in the edition in force at the time of permit application. Where the State of Tennessee and the local AHJ have adopted different editions, the more stringent requirement applies. The Contractor must confirm the editions currently adopted by the State of Tennessee and the AHJ.

• Building, fire, and existing building codes adopted by the State of Tennessee and the applicable local AHJ, including all amendments

• National Electrical Code (NFPA 70) as adopted in Tennessee and by the AHJ, including Article 625 (Electric Vehicle Power Transfer System)

• Cumberland Electric Membership Corporation service and metering requirements

• OSHA Construction Standards (29 CFR Part 1926)

• ADA Standards for Accessible Design and applicable Tennessee accessibility requirements;

U.S. Access Board Design Recommendations for Accessible Electric Vehicle Charging Stations (July 2022) as recommended guidance

• IESNA RP-20 (Parking Lot Lighting)

• UL 2202 / CSA C22.2 No. 107.1 (DC Charging Equipment)

• UL 2231-1 and UL 2231-2 (Personnel Protection Systems)

• OCPP 2.0.1

• Tennessee 811 underground utility damage prevention requirements

• All applicable local jurisdiction requirements

Confidential — For Bidding Purposes Only | Page 10 of 18

SECTION 5 — CONTRACTOR QUALIFICATIONS

• Valid Tennessee contractor license(s) in good standing, including the electrical classification required for the work, and all applicable local licenses

• Professional engineer licensed in Tennessee (employed or subcontracted) who will seal the design packet — provide name, firm, and license number

• EVITP Installer Certification — minimum one lead electrician or superintendent — provide certificate number and expiration

• Minimum 2 years installing DC Fast Charging (DCFC) stations

• Minimum 3 completed DCFC projects with references

• Demonstrated experience coordinating DCFC service design and energization with an electric utility or cooperative

• Ability to provide the 5-year O&M and SLA described in Section 3

Insurance

• Commercial General Liability: $2,000,000 per occurrence / $4,000,000 aggregate

• Workers Compensation: per applicable Tennessee state law

• Automobile Liability: $1,000,000 combined single limit

• Professional Liability (design services): $1,000,000 per claim / $2,000,000 aggregate

• Universal EV LLC named as additional insured

Confidential — For Bidding Purposes Only | Page 11 of 18

SECTION 6 — PROPOSAL REQUIREMENTS

Each proposal must include the following:

• Company information (legal name, address, UEI/SAM.gov, EIN)

• Copies of all licenses and certifications, including the Tennessee contractor license(s)

• Design team information: engineer of record, firm, Tennessee PE license number, and relevant

DCFC design experience

• EVITP certification documentation

• Insurance certificates (including professional liability)

• Minimum 3 DCFC project references

• Design approach and engineering deliverables plan, including how the Owner's conceptual layout will be developed into a stamped packet

• Utility coordination plan for Cumberland Electric Membership Corporation, including anticipated lead times for transformer, pole, and metering equipment

• Proposed charging equipment: manufacturer, model, quantity, connector types, listings, and data sheets

• Permitting plan

• Technical approach and construction methodology

• Signed site-verification statement confirming that the proposer has examined or otherwise verified the Site and has priced the work on that basis (Section 2.7)

• Subcontractor list with qualifications

• Detailed project schedule covering design, utility, permitting, procurement, construction, and commissioning, showing how the March 1, 2027 construction start and April 30, 2027 substantial completion will be met

• Itemized line-item cost proposal, including a separate line item for all utility costs (application, fees, make-ready, and any upgrades)

• 5-Year Warranty description

• 5-Year O&M Plan

• 5-Year SLA with specific commitments

• 24/7 driver support capability description (English and Spanish)

• Signed Debarment/Suspension certification and Incentive Program Compliance acknowledgment (Section 8)

• Acknowledgment of all addenda received

Confidential — For Bidding Purposes Only | Page 12 of 18

SECTION 7 — EVALUATION CRITERIA

Criterion Weight

Price / Total Cost (installation + 5-yr O&M/SLA) 30%

Design Capability & Utility Coordination Approach 15%

Relevant DCFC Experience & References 15%

Technical Approach & Construction Methodology 10%

5-Year O&M Plan Quality 10%

5-Year SLA Commitments 10%

Qualifications & Certifications 5%

Project Schedule 5%

Total 100%

Universal EV LLC reserves the right to reject any or all proposals, cancel this solicitation, request additional information, and award to the proposer deemed most advantageous. Lowest price is not guaranteed to be selected.

Confidential — For Bidding Purposes Only | Page 13 of 18

SECTION 8 — COMPLIANCE REQUIREMENTS

8.1 Charging Station Technical and Operating Requirements

• Open access — no membership or subscription required

• Credit/debit card (contactless) and RFID, plus QR code payment

• OCPP 2.0.1 network protocol

• 97% uptime per port per month

• Real-time port status and pricing made available through the network

• Pricing clearly displayed at the charger before a session starts

8.2 Incentive Program Compliance

The Owner may apply for state and/or utility incentive funding for this Site. The Contractor must support that effort as follows:

• Provide documentation required by an incentive program, including itemized invoices, proof of payment, as-built drawings, photographs, equipment model and serial numbers, commissioning results, permit and inspection records, the energization date, and uptime and usage data for the period the program requires.

• Comply with incentive-program requirements (for example, eligible-equipment lists, reporting, signage, data sharing, or labor requirements) that are issued by written addendum before the proposal deadline. Requirements identified after award that materially change the scope will be handled by change order.

• Owner will notify the Contractor in writing if any incentive-program pre-approval must be obtained before equipment procurement or construction. The Contractor shall not take actions that jeopardize incentive eligibility.

• Maintain all project records for the longer of 3 years after final payment or the period required by the applicable incentive program, and provide audit access to the Owner and to incentive-program administrators and auditors on request.

8.3 Equal Employment Opportunity and Non-Discrimination

• Compliance with all applicable federal and state equal employment opportunity and anti-discrimination laws

• No discrimination in employment or in the provision of charging services on the basis of race, color, national origin, sex, age, disability, or income

8.4 Accessibility

• ADA accessibility compliance, including the U.S. Access Board's Design Recommendations for

Accessible Electric Vehicle Charging Stations (July 2022) as recommended guidance

• Minimum one ADA-accessible charging stall at the Site

8.5 Debarment and Suspension

• Contractor must not appear on the SAM.gov excluded parties list

• Contractor must verify all subcontractors

Confidential — For Bidding Purposes Only | Page 14 of 18

8.6 Drug-Free Workplace

• Drug-free workplace policy required

8.7 Subcontracting Requirements

• All requirements of this Section 8 flow to subcontractors at every tier

• Subcontractor list must be submitted to Owner for approval before execution

8.8 Safety and Site Conditions

• Contractor is solely responsible for jobsite safety and for compliance with OSHA Construction

Standards (29 CFR Part 1926)

• The Site is an operating motel and cabins property. Contractor must maintain guest access, emergency vehicle access, and as much parking as practical, and must coordinate work hours and staging with the Site host.

• Contractor must call Tennessee 811 before excavation and protect all existing utilities and site improvements

COMPLIANCE CERTIFICATION REQUIRED

By submitting a proposal, the contractor certifies that it has read, understands, and agrees to comply with all requirements in Section 8. The Debarment/Suspension certification and the Incentive Program Compliance acknowledgment must be submitted with the proposal as separate signed attachments.

Confidential — For Bidding Purposes Only | Page 15 of 18

SECTION 9 — SUBMISSION INSTRUCTIONS

9.1 Deadline

Proposals are due no later than November 17, 2026.

9.2 Submission Method

Submit proposals by email to proposal@universalgreengroup.com. Subject line format: "RFP Response — Dover Inn Motel & Cabins, Dover, TN DCFC — [Company Name]."

9.3 Questions

All questions must be submitted in writing to proposal@universalgreengroup.com no later than November 10, 2026. Answers will be issued to all bidders by written addendum.

9.4 Pre-Bid Site Visit

Available upon request — contact proposal@universalgreengroup.com to schedule.

9.5 Proposal Validity

Proposals must remain valid for a minimum of 90 days from the proposal submission deadline.

Confidential — For Bidding Purposes Only | Page 16 of 18

SECTION 10 — CONTRACT TERMS

• Fixed-price lump sum inclusive of all design, engineering, utility fees and make-ready, permits, equipment, installation, commissioning, 5-year warranty, O&M, and SLA

• Itemized breakdown required, including a separate line for utility costs (included within the lump sum)

• Contractor retains responsibility for the design; Owner review or approval does not relieve Contractor of that responsibility

• Applicable incentive-program requirements (Section 8.2) will be incorporated into the contract

• Progress payments based on verified completion, 10% retainage until final acceptance

Deliverables at Close-Out

• Final PE-sealed design packet and as-built redline drawings (civil and electrical)

• Equipment warranties and manufacturer registrations

• O&M manuals

• Commissioning test results

• All permits and inspection certificates

• Utility energization and metering documentation

• Executed 5-Year O&M and SLA agreements

Confidential — For Bidding Purposes Only | Page 17 of 18

SECTION 11 — KEY DATES TABLE

Milestone Date

RFP Issue Date October 27, 2026

Questions Deadline November 10, 2026

Proposal Submission Deadline November 17, 2026

Anticipated Award December 16, 2026

Anticipated Construction Start March 1, 2027

Substantial Completion April 30, 2027

Design, utility coordination, and permitting occur after award and before construction. Proposers must show how utility and equipment lead times will be managed to meet the construction start and substantial completion dates.

Confidential — For Bidding Purposes Only | Page 18 of 18

SECTION 12 — NOTICES

• Universal EV LLC is committed to a fair and open competitive process in which all qualified contractors may participate

• Universal EV LLC reserves the right to reject any or all proposals

• No cost incurred by Universal EV LLC for proposal preparation

• Anti-collusion notice: by submitting a proposal, the proposer certifies that the proposal was arrived at independently, without collusion with any other proposer

• Addenda will be issued in writing to all bidders; proposers must acknowledge all addenda in their proposal

Complaints regarding this solicitation may be directed to evsupport@universalgreengroup.com.

SECTION 1 — INTRODUCTION AND BACKGROUND
SECTION 2 — PROJECT OVERVIEW
2.1 Site Information
2.2 Full Scope of Work (Design-Build)
2.3 Owner's Conceptual Layout (No Reference Drawings)
2.4 Equipment Requirements — Performance Minimums
2.5 Owner-Furnished Items
2.6 Design Submittal Milestones
2.7 Site Verification and Bidder Diligence
SECTION 3 — WARRANTY, O&M, AND SERVICE LEVEL AGREEMENT
3.1 5-Year Equipment, Design, and Installation Warranty
3.2 5-Year O&M Plan
3.3 5-Year Service Level Agreement (SLA)
SECTION 4 — APPLICABLE CODES AND STANDARDS
SECTION 5 — CONTRACTOR QUALIFICATIONS
SECTION 6 — PROPOSAL REQUIREMENTS
SECTION 7 — EVALUATION CRITERIA
SECTION 8 — COMPLIANCE REQUIREMENTS
8.1 Charging Station Technical and Operating Requirements
8.2 Incentive Program Compliance
8.3 Equal Employment Opportunity and Non-Discrimination
8.4 Accessibility
8.5 Debarment and Suspension
8.6 Drug-Free Workplace
8.7 Subcontracting Requirements
8.8 Safety and Site Conditions
SECTION 9 — SUBMISSION INSTRUCTIONS
9.1 Deadline
9.2 Submission Method
9.3 Questions
9.4 Pre-Bid Site Visit
9.5 Proposal Validity
SECTION 10 — CONTRACT TERMS
Deliverables at Close-Out
SECTION 11 — KEY DATES TABLE
SECTION 12 — NOTICES