UFGS 01 14 00 WORK RESTRICTIONS.pdf

PDF 34 KB Posted

Attached to
Construct Pad & Sit-Up Bars at North Gate Track
Solicitation number
FA442726Q1149
Issued by

About this file

SECTION 01 14 00: WORK RESTRICTIONS

This document is a contract specification section outlining work restrictions and site access requirements for a construction project at Travis Air Force Base. The contractor must comply with special scheduling requirements, including providing a minimum of 15 calendar days' written notice prior to interrupting any activity roads, railroads, or utility services. Regular working hours are established as an 8.5-hour period between 7:30 a.m. and 4:30 p.m., Monday through Friday, excluding Government holidays, with any work outside these hours requiring Contracting Officer approval submitted 15 calendar days in advance. Material deliveries must occur outside peak traffic hours (6:30–8:00 a.m. and 3:30–5:00 p.m.) unless otherwise approved.

Contractor personnel must comply with Travis Air Force Base regulations, including wearing hard hats in designated areas and maintaining restricted area access limitations until security clearance is obtained. The contractor must provide the Contracting Officer with names of two designated representatives authorized to request personnel and vehicle passes, and must adhere to Air Force Background Check requirements for the contract's duration. Additional requirements include restricting employees to the work site, restoring traffic and security markings if defaced, maintaining equipment and material security with immediate reporting of missing property to Base Police, and coordinating with Base Security Office at least 72 hours before making any area penetrations. For airfield work, the contractor must contact Airfield Management Operations Desk at 707-424-2836 at least 72 hours prior to commence work for approval and Notice-to-Airman (NOTAM) publication. Utility cutovers and interruptions to water, sanitary sewer, storm sewer, telephone, electric, air conditioning, heating, fire alarm, and compressed air services must be scheduled after normal working hours or on weekends/holidays and must follow procedures outlined for work outside regular hours.

View the file

Other files

File Type Posted
FA442726Q1149 - Combined Synopsis Solicitation Construct Pad Sit Up Bars at North Gate Track Amended 2.pdf PDF
FA442726Q1149 - Construct Pad Sit Up Bars at North Gate Track - Amendment 0001.pdf PDF
FA442726Q1149 - Combined Synopsis Solicitation Construct Pad Sit-Up Bars at North Gate Track - Amended.pdf PDF
FA442726Q1149 - Combined Synopsis Solicitation (Construct Pad Sit-Up Bars at North Gate Track).pdf PDF
Attachment 1 - Price Schedule.xlsx XLSX spreadsheet
Attachment 2 - Request for Information.xlsx XLSX spreadsheet
Attachment 4 -Davis Bacon Act Wage Determination.pdf PDF
ufc_1_300_08_2023.pdf_safe.pdf PDF
Travis AFB BMP Construction Site Documents feb2025.pdf PDF
UFGS 01 33 16.00 10.pdf_safe.pdf PDF
Attachment 5 - TAFB Security Requirements.pdf PDF
Attachment 6 - Solicitation Provisions and Contract Clauses.pdf PDF
ufc_3_410_02_2018_c2.pdf PDF
Travis AFB Spec - 01 00 01 - General Spec_Sep 2024.pdf PDF
UFGS 01 33 00 SUBMITTAL PROCEDURES (002).pdf PDF
Travis AFB Spec - SECTION 01 56 00_Environmental Specs_April 2019.pdf PDF
Location and Vicinity Map - Construct Pad and Sit-Up Bars at North Gate Track.docx DOCX document
Maint_DurList_Distribution Copy - 2025-07-16.pdf PDF
Travis Facilities Excellence Guide 2022-08-15.pdf PDF
01 56 00 2026- Engineering Enviornmental Specs-01 56 00.pdf PDF
Travis AFB Spec 01000 Word DocWithHyperlinks 1-04-23.pdf PDF
UFGS 01 78 00 Closeout Submittals.pdf PDF
UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
Attachement 3 - Statement of Work Construct Pad North Gate Track B1887.pdf PDF
mutcd11thedition.pdf PDF
Travis Design Guide FEG.pdf PDF
Travis AFB Spec - 01 00 00 - General Spec_Sep 2024 -.pdf PDF
UFGS 01 35 26-GOVERNMENTAL SAFETY REQUIREMENTS.pdf PDF
Travis AFB Spec - 01 00 00 - General Spec_Jan 2022.pdf PDF
UFGS 01 45 00.00 40 QUALITY CONTROL.pdf PDF
SECTION 01 03 00 PROJECT CLOSEOUT AUG 13.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 14 00, Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SPECIAL SCHEDULING REQUIREMENTS

a. Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Project become familiar with and obey Project regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.2.1.1 Employee List

The Contractor shall provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor shall adhere to the requirements of the Air Force Background Checks requirements in obtaining access to Travis Air Force Base for the life of the contract. A copy of these requirements will be provided at the preconstruction conference.

1.2.2 Travis Air Force Base

Ensure that Contractor personnel employed on the Project become familiar with and obey Travis Air Force Base regulations. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification. Comply with the following conditions:

a. Restrict employees/representatives to the work site and control travel directly to and from the work site.

b. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.

c. Be responsible for control and security of Contractor-owned equipment and materials at the work site. Report immediately

SECTION 01 14 00, Page 2 missing/lost/stolen property to the Travis Air Force Base Police Department as each case occurs.

d. Seventy-two hours prior to making any penetrations (such as tunneling under, cutting through a fence or building) in a restricted area, contact the Travis Air Force Base Security Office to make arrangements for a security guard or other measures required to meet all security requirements. Cost of security guard will be charged to the Contractor.

e. Seventy-two hours prior to performing any work on the airfield, contact the Travis Air Force Base Airfield Management Operations Desk at 707-424-2836 for prior approval and publishing of the Notice-to-Airman (NOTAM) prior to any work commencing.

1.2.3 Working Hours

Regular working hours shall consist of an 8-1/2 hour period, established by the Contractor Officer, between 7:30 a.m. and 4:30 p.m., Monday through Friday, excluding Government holidays.

1.2.4 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --