Attachement 3 - Statement of Work Construct Pad North Gate Track B1887.pdf
PDF 159 KB Posted
- Attached to
- Construct Pad & Sit-Up Bars at North Gate Track
- Solicitation number
- FA442726Q1149
About this file
This is a Statement of Work (SOW) for design-build construction of an outdoor fitness pad at Travis Air Force Base in California (Base Project Number XDAT 26-1027, dated August 19, 2026).
The project requires construction of a continuous 150-foot by 50-foot fitness pad on the east side of the North Track, divided into two functional zones. The northern section (60' x 50') is a sit-up gathering area featuring a 4-inch rubber sandwich system with 2.5 inches of Styrene-Butadiene Rubber (SBR) over 2 inches of hot-mix asphalt, topped with six outdoor sit-up stations anchored to concrete pier footings. The southern section (90' x 50') serves as a shuttle run and track zone with a 4-inch running surface, featuring precision-striped white bars 20 meters apart for shuttle run lanes, with "HAMR" stenciled lettering, all compliant with DAFMAN 36-2905. Base construction includes scarified and compacted native subgrade to 95% Maximum Dry Density, a 4-inch aggregate base layer, and 2-inch hot-mix asphalt underlayment. Concrete curbs must be installed on three edges, flush with existing track curbing, with lateral stormwater drainage sloped at less than 1.0% and an adjacent open drainage ditch connection.
Contractor submittals required after award and before construction include an Activity Hazard Analysis, Design Quality Control Plan, Contractor's Quality Control Plan, Accident Prevention Plan, construction schedule, and detailed design construction documents (60% design at 14 days, pre-final at 65 days, and final ready-for-construction at 14 days following government review comments). All drawings must be prepared in AutoCAD 2024 format on ANSI D sheets with Travis AFB title blocks, accompanied by sealed and signed basis of design, specifications in CSI 2010 format, and deliverables on CDs with native files and PDF bookmarks. Closeout requirements include record drawings, GIS-compliant site maps with all utilities and features accurately noted, and Periodic Maintenance Inspection plans.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Construct Pad & Sit-Up Bars at North Gate Track B1887
TRAVIS AFB CALIFORNIA
Base Project Number: XDAT 26-1027
DATE: 19 August 2026
1. INTRODUCTION
This Statement of Work (SOW) defines the requirements for the complete design-build construction of a new outdoor fitness pad located on the east side of the North Track at Travis AFB. This project addresses the need to enhance base athletic infrastructure, support physical readiness, and improve service member well-being. The contractor shall provide all design, engineering, labor, materials, equipment, and supervision necessary to deliver a complete, turn-key, and fully usable facility in accordance with applicable Unified Facilities Criteria (UFC) standards.
2. SCOPE OF WORK
2.1. GENERAL REQUIREMENTS
01 00 00 Special provisions 01 00 01 Special provisions 01 14 00 Work Restriction 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 45 00 Contractor Quality Control
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 56 00 ENVIRONMENTAL GENERAL REQUIREMENTS
01 78 00 Closeout Submittals Maintenance and Durability NEPA coordination/comments (Env 202514- Renovate Softball fields 2025-v8 + Env softball Memo Final) Travis Facilities Excellence Guide 2022-08-15 Travis AFB BMP Construction Site Documents feb2025
DAFMAN 36-2905
2.2. APPLICABLE CODES & STANDARDS
UFC 3-201-01 (Civil Engineering): Civil design, site grading, trench drain placement, and sheet-flow stormwater controls.
UFC 3-220-01 (Geotechnical Engineering): Subgrade scarification, moisture conditioning, and compaction requirements.
UFC 3-250-01: Pavement Design for Roads, Streets, Walkways, and Open Storage Areas UFC 4-750-02: Outdoor Sports and Recreational Facilities
2.3. Construct Fitness Pad (150’ x 50’): Contractor shall construct one continuous fitness pad with dimensions of 150 feet in height (parallel to existing track, east side) and 50 feet in width. The track will consist of two sections. The northern section will be 60 feet in length for sit-up gathering, and the southern section will be 90 feet in length as running track. The surface shall be sloped at <=1.0% for lateral stormwater drainage. Concrete curb required on the new 3 edges. Curb must sit flush with new pad and existing concrete curb that lines the existing track.
2.3.1. Subgrade: Native subgrade shall be scarified, moisture-conditioned, and compacted to 95% Maximum Dry Density (MDD) per ASTM D1557 / UFC 3-220-01.
2.3.2. Aggregate Base (AB): Furnish and place a 4" AB layer compacted to 95% on top of subgrade
2.3.3. Hot-Mix Asphalt (HMA): Furnish and place a 2" HMA layer on top of AB.
2.3.4. North Pad (60’ x 50’): Sit-Up Zone
2.3.4.1. Construct Rubber Surfacing: Furnish and install a 4” rubber sandwich system that includes a top wear layer above a minimum of 2.5” of Styrene-Butadiene Rubber (SBR). This sandwich will sit on top of the 2” of HMA.
2.3.4.2. Sit-Up Equipment: Furnish and install six outdoor sit-up stations.
Station posts shall be anchored into concrete pier footings penetrating through the asphalt sub-slab into native soil.
2.3.5. South Pad (90’ x 50’): Shuttle Run & Track Zone
2.3.5.1. Construct Track Surfacing: Construct south pad for shuttle run and track zone. This material composite must be 4” in thickness to be flush with the existing track, curb, and north pad. This material must be purposed for running. This pad will sit on top of the 2” of HMA.
2.3.5.2. Shuttle Run Striping: Precision-stripe one set of white bars, 20 meters apart for shuttle run lanes in compliance with DAFMAN 36-2905.
Lines shall be 40 feet long horizontally (leaving 5 feet on either side between the lines and the edges of the track pad). Lines shall be 2-inch-wide using 100% acrylic/polyurethane elastomeric traffic-marking paint compatible with the top layer. The length requirement between the lines (20 meters apart) shall be measured from the outside-to-outside ends of the lines. The stripes shall be centered vertically along the south pad (leaving 12.5’ between the line and the vertical edges of the pad). Middle-centered on the outsides of each line, the word “HAMR” shall be stenciled in white. Letters shall be roughly 1 foot by 1 foot in size.
2.3.6. Drainage: Excavate an adjacent open drainage ditch along the low edge of the pad to connect with existing one for continuous stormwater runoff.
2.4. SUBMITTAL REQUIREMENTS (After award and before construction start)
2.4.1. Activity Hazard Analysis (AHA)
2.4.2. Design Quality Control Plan (DQC)
2.4.3. Contractor’s Quality Control Plan (CQC)
2.4.4. Accident Prevention Plan (APP)
2.4.5. Construction Schedule
2.4.6. Design Construction Documents: Prepare, organize, and present Design
Construction Documents in accordance with the requirements of UFC 1-200-01 (DoD Building code), the A/E/C CAD Standard (Release 6.2), and the A/E/C Graphics Standard (Release 2.2). Contractor will not be allowed to start construction without the Government-approved documents listed below.
2.4.6.1. Design Drawings: Prepare using AutoCAD 2024 formatted for ANSI D (22” x 34”) sheets and shall include the standard Travis AFB title block on each sheet.
2.4.6.2. The Ready for Construction submission shall be stamped and signed by the Designer of Record (DOR).
2.4.6.3. Prepare, organize, and present design drawings in accordance with the requirements of UFC 1-300-09 (Design Procedures), the Air Force Corporate Facilities Standards (AFCFS), and the Travis AFB Facilities Excellence Guide.
2.4.6.4. Submit all CAD files for the final drawings on CDs or DVDs in
AutoCAD 2024 format. Drawing files must be full files, uncompressed and unzipped.
2.4.6.5. Basis of Design: Each submission shall include a basis of design with all proposed materials including Design Analyses and Calculations to substantiate the design meets the RFP and all applicable codes. Prepare, organize, and present basis of design in accordance with the requirements of UFC 1-300-09 (Design Procedures), the Air Force Corporate Facilities Standards (AFCFS), and the Travis AFB Facilities Excellence Guide.
2.4.6.6. Specifications: Shall be Unified Facilities Guide specifications submitted in Construction Specification Institute (CSI) 2010 format edit with SpecIntact software or equivalent in accordance with UFC 1- 300-02 Unified Facilities Guide Specifications (UFGS) Format Standard.
2.4.6.7. Contractor shall submit the number of copies defined under each required submission identified below. The basis of design, design drawings and specifications shall be included on a CD in addition to the required hard copy for each submission. Each submission shall be submitted to the Contracting Officer or their representative for Government review and RFP concurrence.
2.4.6.8. The Contractor shall submit a copy of the Government reviewed comments from each prior submission with each subsequent submission. This document shall indicate the corrective action taken for each comment and other proposed solutions. Incomplete submissions will be returned to the Contractor with no additional time added to the performance period.
2.4.6.9. Electronically seal and sign all Acrobat PDF drawings, specifications, and other documents in accordance with UFC 1-300-09 (Design Procedures), the Air Force Corporate Facilities Standards (AFCFS), and the Travis AFB Facilities Excellence Guide. The electronic signatures shall be printable and viewable in Adobe Acrobat Reader with no additional software.
2.4.7. Provide the following Design Submittal Packages:
2.4.7.1. Provide 60% design submittal: Submit two (2) hard copies and two (2) electronic PDF format copies on two (2) CDs of the following: 11” x 17” half-scale drawing sets, completed specifications with cleared Section and Bracket Verification reports, Construction Schedule, Basis of Design, annotated review comments, and submittal register. Allow 14 calendar days for Government review.
2.4.7.2. Pre-Final Design Documents Submittal: 65 calendar days following receipt of Government reviewed comments on the 60% design submittal. Submit two (2) hard copies and two (2) electronic PDF format copies on two (2) CDs of the following: 11” x 17” half-scale drawing sets, completed specifications with cleared Section and Bracket Verification reports, Construction Schedule, Basis of Design, annotated review comments, and submittal register. Allow 14 calendar days for Government review.
2.4.7.3. FINAL “Ready for Construction” (RFC) Documents: 14 calendar days following receipt of Government reviewed comments on the 100% design and notice to proceed with Ready for Construction documents.
The RFC documents include all documents required for the Final Design Documents. Submit electronic PDF format copies and AutoCAD 2024 native files on three (3) CDs of the following: Sealed and Signed 11” x 17” half-scale Drawings, Sealed and Signed Specifications, Construction Schedule, Sealed and Signed Basis of Design, annotated Review Comments, and submittal register. Allow 7 calendar days for Government review.
2.4.7.4. The following requirements apply to the CD: Provide native files including AutoCAD 2024 DWG files, GIS files, and PDF files for all applicable documents included on the CD. A PDF file(s) of the final documents shall be provided in the following formats: The entire document shall be provided as a single combined PDF file. The PDF file shall have bookmarks for each item identified in the document's table of contents, including tables, figures, captioned photos, and appendices. The bookmark shall use the same description as provided in the table of contents. If the bookmark is lengthy, abbreviate as needed. Bookmark to the second level (i.e. 1.1, 1.2, 1.3, etc.). Do not bookmark signature page or the list of acronyms. Each appendix, regardless of size, shall be provided as an individual PDF file. All maps, figures, and pictures shall be provided at a useable resolution.
All color maps, figures, and pictures shall be provided in color. DD- 1354 Transfer and Acceptance of Military Real Property: Submit Interim DD Form 1354 to the Government for approval a minimum of 60 calendar days prior to the Beneficial Occupancy Date (BOD) or at red zone (70% construction completion), whichever is earlier. If modifications to the Interim DD-1354 are required by the Government, the corrected version must be submitted prior to the BOD.
2.5. Closeout Submittal Requirements:
2.5.1. Submit Record Drawings to the Contracting Officer or their representative in ANSI D (22” x 34”) size sheets and on two CDs containing native CAD files, electronically stamped and signed PDF of drawings, specifications, calculations, basis of design, submittal register, Periodic Maintenance Inspection (PMI) plan and other (photos, support files, etc.) as applicable.
2.5.2. GIS Requirements: Site Map record drawings must comply with specs 01 00 00. All new and existing utilities, driveways, concrete curbs, sidewalks, roads, paved and unpaved surfaces, buildings, structures, poles, signs, and primary features including supporting facilities of the project within the project’s limit must be accurately noted, both in AutoCAD 2024 and GIS format. Comply with A/E/C CAD Standard (latest and greatest release) and the A/E/C Graphics Standard (latest and greatest release) requirements.
2.6. ATTACHMENTS
2.6.1 Location and Vicinity Map - Construct Pad & Sit-Up Bars at North Gate Track
// END OF STATEMENT OF WORK //