This is a technical procedures document from the U.S. Fire Administration providing guidance on securing temporarily vacant buildings, in support of the Hawaii District Land Office's bid solicitation to secure an unoccupied residential structure at 521 Ocean View Drive, Hilo, Hawaii. The procedures detail comprehensive "hardening the target" boarding up methods to prevent unauthorized entry, arson, and illegal use of vacant properties. The document specifies required preparation steps including disconnecting all utilities at the street, removing all flammables and combustibles from interior and exterior areas, and conducting a thorough search to ensure the building is unoccupied before proceeding with security measures.

The technical specifications require specific materials and installation methods for boarding windows and doors, including 1/2-inch CDX plywood, 2-inch by 4-inch construction-grade lumber, 3/8-inch by 12-inch carriage bolts with rounded heads, construction-grade nuts, and galvanized or stainless steel ring-shank nails. The procedures prescribe detailed placement of plywood sheets fitted flush to exterior frames, positioning of 2x4 braces with specific spacing requirements (one-third distances from edges for windows and centered placement for doors), pre-drilling of holes at designated locations, and secure fastening using carriage bolts with washers and nuts. Additional security measures include removing shrubbery and vegetation that could support fire spread, and periodic patrols to monitor building security. The document references the National Arson Prevention Clearinghouse as a resource for additional arson prevention materials and support.

View the file

Other files

File Type Posted
Scope of Work .pdf PDF
Exhibit A Map and Pictures.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Fire Administration

STOP the use of empty buildings as targets for arsonists, as crack houses, as hang outs for gangs, as garbage dumps, and as temporary shelters for the homeless.

These procedures are intended to protect buildings that are temporarily vacant pending rehabilitation and use.

“HARDENING THE TARGET”

BOARD UP PROCEDURES

Protecting valuable buildings from the weather and from illegal entry can be accomplished by improving security, organizing block watches, improving lighting, periodic patrols, and by following these directions.

BOARDING UP

DETERMINING HOW MUCH

PROTECTION IS NEEDED

1. DISCONNECT ALL UTILITIES AT THE

STREET

A. Turn off water at the street and drain the system to its lowest point. Leave faucets open and put anti-freeze in all traps containing water.

B. Have the utility company disconnect electricity at the street and remove and cap meters.

C. Shut off LNG supply at the street.

Disconnect and remove LPG and heating oil tanks.

2. REMOVE ALL FLAMMABLES AND

COMBUSTIBLES FROM INSIDE AND

OUTSIDE THE BUILDING

After all entrances are secured, the interior worker should exit the building, using a ladder, through a window, if such exists, at least 10 feet above the ground.

Nail or screw a plywood sheet over the worker's exit. Patrol the building periodically to check the security.

A. Remove all upholstered furniture, combustible materials and trash from the building, including the basement and attic.

B. Remove trash and trash containers and combustible furniture from exterior stairwells, porches, fire escapes and outbuildings.

3. SECURE THE BUILDING TO PREVENT

ENTRY

A. Search the entire building to ensure that it is unoccupied.

B. Remove doors and storm windows and place in storage.

1. Openings in the basement, first floor doors and windows and any point of entry accessible from a porch, fire escape or other potential climbing point require additional security measures. These openings should be barricaded with plywood, 2x4s, bolts and nails.

2. Openings that are at least 10' from ground level which are not accessible from a porch, fire escape, roof, or other climbing point can be secured with nails in each brace, and every 12" around the perimeter. For these openings the plywood should be fitted so that it rests snugly against the exterior frame, butting up to the siding on wood frame buildings and up to the brickwork on brick buildings. It may be necessary to remove the staff bead so this fit can be flush and tight.

NOTE: USE ROUNDED HEAD

1. Cut plywood to fit over the window and door openings, flush with outside of the molding.

Note: For buildings with metal door and window frames the alternative is to cut the plywood and 2x4s to fit the inside of the door frame buffed up against the band molding.

2. Cut the 2x4s to fit the horizontal dimension of the plywood. You will need two 2x4 exterior and two interior braces for each window and three sets for each door.

For buildings with metal doors and window frames the 2x4s for the outside will be cut to the dimensions of the plywood, fitting inside the door frame, against the band molding. For the inside the 2x4s will be cut to the outside dimension of the door or window frame.

3. Pre drill 3/8th inch holes in the plywood and the braces.

4. The holes will be placed approximately 1/3 of the length of the brace from each outside edge of the door and window jam.

5. The two window braces will be placed 1/3 of the distance from the top and the bottom of the window.

6.The three door braces will be placed; one in the center of the doorway, and one half the distance from the center to the top and to the bottom of the doorway.

7. Place the plywood over the exterior opening and nail to the frame.

For metal frames place the plywood and braces inside the frame against the band molding.

8. Place the 2x4 braces over the interior and exterior of the door or window.

9. Place the large washer over the carriage bolt and place the bolt through the holes.

10.Place washer and nut inside and tighten securely. Torque the nut so that it slightly compresses the interior 2x4.

3/8" CARRIAGE BOLT 12" LONG (COURSE THREAD)

C. Remove shrubbery and vegetation that could support or spread a fire.

WRENCH NECK WASHER &

1/2" STANDARD FLAT WASHER 3/8" COURSE CONSTRUCTlON GRADE NUT

MATERIALS NEEDED

A . 1/2” plywood, grade CDX and 2” x 4” by 8’ construction grade lumber.

B . 3/8” by 12” carriage bolts (rounded head on weather side).

C. 3/8” construction grade nuts.

D . Flat washers with an inside diameter large enough to bypass the wrench neck inside the carriage bolt head so no lift edge is available beneath an installed carriage bolt head.

E. 1/2” diameter flat washers for installation beneath the nut inside the building.

F . 1-5/8” (6d) galvanized or stainless steel ring-shank nails or comparable deck nails.

WINDOWS

Windows raised and lowered to center of the frame

View from inside bldg.

Note: Outside view of window is same as view from outside door except with two 2x4 braces instead of three.

DOORS

Nut & Washer

OPTIONAL

screw an additional 2x4 to the threshold butting against the inside of the plywood

View from inside bldg.

Bolt’s to inside 2x4

View from outside bldg

2x4’s cut to fit inside

Plywood cut to size and 2x4’s cut to fit against inside door band molding Alternate Method:

cut plywood and 2x4s to cover the outside of the door frame.

To request arson prevention materials:

National Arson Prevention Clearinghouse 16825 South Seton Avenue, Emmitsburg, Maryland 21727 1-888-603-3100

Materials available include:

l General Arson Prevention Literature l Video: Fighting Church Arson l Church Arson Prevention Literature l Arson Prevention Brochures l Juvenile Firesetter Brochures l Coalition Building Handbook l Arson Threat Assessment Guides for:

Communities, Churches, Buildings l Information on Arson Classes and

Courses delivered by the National Fire Academy

File details come from the government source that posted it. Updated .