This is a change log dated August 2022 documenting updates to the Tinker General Requirements Specifications. The primary change appears throughout multiple sections (01 33 00 and 01 78 00) where "Contracting Officer" was replaced with "Contracting Officers Representative" and added "and/or Contracting Officer's Representative" to various subsections.

Notable specific changes include: adding DOD Safe as a means for submittal transmittal, changing the requirement for Contractor's Submittal Register to be submitted with final design submittal, requiring monthly updates to the Submittal Register, replacing AF Form 3000 with new TAFB Form 3000, updating file naming convention requirements, allowing COR to modify PDF submittal requirements, and changing "Interim DD Form 1354" to "DD Form 1354." Multiple sections (00 70 00, 00 71 00, 00 72 00, 00 80 00, 00 80 05, 01 32 16.00 20, 01 33 16.00 10, 01 42 00, 01 45 00.00 10, 01 50 00, and 01 78 23) had no changes.

View the file

Other files

File Type Posted
210380 Prebid RFI_GOVT RESPONSE.pdf PDF
WWYK210380 Solicitation Amend 02- FA813725R0011-0002.pdf PDF
WWYK210380 Solicitation Amend 01- FA813725R0011-0001.pdf PDF
WWYK210380 - Solicitation Amendment FA813725R00110001 SF 30.pdf PDF
00 72 00.pdf PDF
00 71 00.pdf PDF
02_Base Facility Stds.zip ZIP file
01 50 00.pdf PDF
01 78 00.pdf PDF
WWYK210380-19November2024 Drawings.pdf PDF
00 80 05.pdf PDF
03_As-Built Info.zip ZIP file
WWYK210380 Solicitation - FA813725R0011.pdf PDF
01 33 16.00 10.pdf PDF
01 78 23.pdf PDF
00 80 00.pdf PDF
Wage Determination Davis-bacon 3 jan 25.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
SOW Att 01_Appointment of Security Representative Template 496.docx DOCX document
210380_SOW_MACB V2.pdf PDF
210380_Submittal Register.pdf PDF
01 33 00.pdf PDF
1 EAL List - BLANK to Contractors.xlsx XLSX spreadsheet
01 32 16.00 20.pdf PDF
00 70 00.pdf PDF
01 45 00.00 10.pdf PDF
01 42 00.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker General Requirements Change Log – Aug 2022

00 70 00 No Changes

00 71 00 No Changes

00 72 00 No Changes

00 80 00 No Changes

00 80 05 No Changes

01 32 16.00 20 No Changes

01 33 00 Throughout document, changed ‘Contracting Officer’ to ‘Contracting Officers Representative.’

Section 1.2.3. Added definition of ‘Contracting Officers Representative.’

Section 1.4.2.1. Added ‘and/or Contracting Officer’s Representative.’

Section 1.5.1. First sentence revised for clarity.

Section 1.5.3.3.2. Added ‘and/or Contracting Officer’s Representative.’

Section 1.5.3.3.2. Added ‘and/or Contracting Officer’s Representative.’

Section 1.5.3.8.1. Added ‘and/or the Contracting Officer or designated alternate.’

Section 1.5.5. Multiple Changes

- Added Language specifying that file naming convention are specified in contract documents.

- Added language specifying that the COR can change requirement for submittals in PDF format.

- Added DOD Safe as means for transmittal of submittals.

Section 1.8.2. Changed requirement that Contractor’s Submittal Register must be submitted with final design submittal.

Section 1.8.7. Changed requirement that updated Submittal Register must be submitted monthly.

Section 1.14. Added ‘and/or Contracting Officer’s Representative.’

Attachment 1. Replaced AF Form 3000 with new TAFB Form 3000.

01 33 16.00 10 No Changes.

01 42 00 No Changes.

01 45 00.00 10 No Changes.

01 50 00 No Changes

01 78 00 Throughout document, changed ‘Contracting Officer’ to ‘Contracting Officers Representative.’

Section 1.1. Updated references as required to reflect most current.

Section 1.2.1. Added ‘and/or Contracting Officer’s Representative.’

Section 1.4. Changed ‘Interim DD Form 1354’ to ‘DD Form 1354.’

Section 1.7.1. Added ‘and/or Contracting Officer’s Representative.’

Section 1.7.2. Added ‘and/or Contracting Officer’s Representative.’

Section 1.7.3. Added ‘and/or Contracting Officer’s Representative.’

Section 3.6. Added ‘attachment’ references.

01 78 23 No Changes