Tinker General Requirements Specifications_Nov 2022_Change Log.pdf
PDF 94 KB Posted
- Solicitation number
- FA813725R0011
About this file
This is a change log dated August 2022 documenting updates to the Tinker General Requirements Specifications. The primary change appears throughout multiple sections (01 33 00 and 01 78 00) where "Contracting Officer" was replaced with "Contracting Officers Representative" and added "and/or Contracting Officer's Representative" to various subsections.
Notable specific changes include: adding DOD Safe as a means for submittal transmittal, changing the requirement for Contractor's Submittal Register to be submitted with final design submittal, requiring monthly updates to the Submittal Register, replacing AF Form 3000 with new TAFB Form 3000, updating file naming convention requirements, allowing COR to modify PDF submittal requirements, and changing "Interim DD Form 1354" to "DD Form 1354." Multiple sections (00 70 00, 00 71 00, 00 72 00, 00 80 00, 00 80 05, 01 32 16.00 20, 01 33 16.00 10, 01 42 00, 01 45 00.00 10, 01 50 00, and 01 78 23) had no changes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 210380 Prebid RFI_GOVT RESPONSE.pdf | ||
| WWYK210380 Solicitation Amend 02- FA813725R0011-0002.pdf | ||
| WWYK210380 Solicitation Amend 01- FA813725R0011-0001.pdf | ||
| WWYK210380 - Solicitation Amendment FA813725R00110001 SF 30.pdf | ||
| 00 72 00.pdf | ||
| 00 71 00.pdf | ||
| 02_Base Facility Stds.zip | ZIP file | |
| 01 50 00.pdf | ||
| 01 78 00.pdf | ||
| WWYK210380-19November2024 Drawings.pdf | ||
| 00 80 05.pdf | ||
| 03_As-Built Info.zip | ZIP file | |
| WWYK210380 Solicitation - FA813725R0011.pdf | ||
| 01 33 16.00 10.pdf | ||
| 01 78 23.pdf | ||
| 00 80 00.pdf | ||
| Wage Determination Davis-bacon 3 jan 25.pdf | ||
| 000_TABLE OF CONTENTS.pdf | ||
| SOW Att 01_Appointment of Security Representative Template 496.docx | DOCX document | |
| 210380_SOW_MACB V2.pdf | ||
| 210380_Submittal Register.pdf | ||
| 01 33 00.pdf | ||
| 1 EAL List - BLANK to Contractors.xlsx | XLSX spreadsheet | |
| 01 32 16.00 20.pdf | ||
| 00 70 00.pdf | ||
| 01 45 00.00 10.pdf | ||
| 01 42 00.pdf |
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tinker General Requirements Change Log – Aug 2022
00 70 00 No Changes
00 71 00 No Changes
00 72 00 No Changes
00 80 00 No Changes
00 80 05 No Changes
01 32 16.00 20 No Changes
01 33 00 Throughout document, changed ‘Contracting Officer’ to ‘Contracting Officers Representative.’
Section 1.2.3. Added definition of ‘Contracting Officers Representative.’
Section 1.4.2.1. Added ‘and/or Contracting Officer’s Representative.’
Section 1.5.1. First sentence revised for clarity.
Section 1.5.3.3.2. Added ‘and/or Contracting Officer’s Representative.’
Section 1.5.3.3.2. Added ‘and/or Contracting Officer’s Representative.’
Section 1.5.3.8.1. Added ‘and/or the Contracting Officer or designated alternate.’
Section 1.5.5. Multiple Changes
- Added Language specifying that file naming convention are specified in contract documents.
- Added language specifying that the COR can change requirement for submittals in PDF format.
- Added DOD Safe as means for transmittal of submittals.
Section 1.8.2. Changed requirement that Contractor’s Submittal Register must be submitted with final design submittal.
Section 1.8.7. Changed requirement that updated Submittal Register must be submitted monthly.
Section 1.14. Added ‘and/or Contracting Officer’s Representative.’
Attachment 1. Replaced AF Form 3000 with new TAFB Form 3000.
01 33 16.00 10 No Changes.
01 42 00 No Changes.
01 45 00.00 10 No Changes.
01 50 00 No Changes
01 78 00 Throughout document, changed ‘Contracting Officer’ to ‘Contracting Officers Representative.’
Section 1.1. Updated references as required to reflect most current.
Section 1.2.1. Added ‘and/or Contracting Officer’s Representative.’
Section 1.4. Changed ‘Interim DD Form 1354’ to ‘DD Form 1354.’
Section 1.7.1. Added ‘and/or Contracting Officer’s Representative.’
Section 1.7.2. Added ‘and/or Contracting Officer’s Representative.’
Section 1.7.3. Added ‘and/or Contracting Officer’s Representative.’
Section 3.6. Added ‘attachment’ references.
01 78 23 No Changes
File details come from the government source that posted it. Updated .