This is a submittal register for a ductwork replacement project at Tinker Air Force Base, contract number WWYK210380, to replace ductwork at Post P39 and Post P37 to T37 in Building B3001.

The register details 79 required submittals across various specification sections, including preconstruction submittals, product data, test reports, certificates, and closeout documentation. Key submittals include health and safety plans, environmental management documentation, quality control plans, construction schedules, and technical submittals related to ductwork materials and components (metal duct, flexible duct connectors, sealants, dampers, access doors, smoke detectors, insulation, and air devices). Notable timing requirements include baseline construction and design schedules due within 10 days of Notice to Proceed, monthly hazardous material usage reports, monthly debris management reports, weekly 3-week look ahead schedules, and weekly QC documentation. Many submittals require government (G) review and approval, particularly those related to safety procedures, abatement work, and technical specifications.

View the file

Other files

File Type Posted
210380 Prebid RFI_GOVT RESPONSE.pdf PDF
WWYK210380 Solicitation Amend 02- FA813725R0011-0002.pdf PDF
WWYK210380 Solicitation Amend 01- FA813725R0011-0001.pdf PDF
WWYK210380 - Solicitation Amendment FA813725R00110001 SF 30.pdf PDF
00 72 00.pdf PDF
00 71 00.pdf PDF
02_Base Facility Stds.zip ZIP file
Tinker General Requirements Specifications_Nov 2022_Change Log.pdf PDF
01 50 00.pdf PDF
01 78 00.pdf PDF
WWYK210380-19November2024 Drawings.pdf PDF
00 80 05.pdf PDF
03_As-Built Info.zip ZIP file
WWYK210380 Solicitation - FA813725R0011.pdf PDF
01 33 16.00 10.pdf PDF
01 78 23.pdf PDF
00 80 00.pdf PDF
Wage Determination Davis-bacon 3 jan 25.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
SOW Att 01_Appointment of Security Representative Template 496.docx DOCX document
210380_SOW_MACB V2.pdf PDF
01 33 00.pdf PDF
1 EAL List - BLANK to Contractors.xlsx XLSX spreadsheet
01 32 16.00 20.pdf PDF
00 70 00.pdf PDF
01 45 00.00 10.pdf PDF
01 42 00.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Trans mittal #

Specification Section

SD

# Submittal Description Item Submitted

Paragraph

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 70 00 06 Test Reports Pre-Construction Testing Record 1.3.11 G

2 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G

3 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

4 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G

5 00 71 00 07 Certificates Safety Meetings 1.3

6 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

7 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G

8 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.1

9 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.10 G Provide only one. Reference specification for additional information

10 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction

11 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4

12 00 72 00 - Attch 2 01 Preconstruction Submittals Documentation of Training/ Experience C.2 C.13

13 00 72 00 - Attch 2 01 Preconstruction Submittals Employee Physicals C.2 C.13

14 00 72 00 - Attch 2 01 Preconstruction Submittals Regulatory Agency Notification C.3

15 00 72 00 - Attch 2 01 Preconstruction Submittals Security Documentation C.4

16 00 72 00 - Attch 2 01 Preconstruction Submittals Communications C.5

17 00 72 00 - Attch 2 01 Preconstruction Submittals Step-by-Step Abatement Procedures C.6 G

18 00 72 00 - Attch 2 01 Preconstruction Submittals Glovebag Procedures C.7 G

19 00 72 00 - Attch 2 01 Preconstruction Submittals Negative Pressure Enclosure Construction Procedures C.8 G

20 00 72 00 - Attch 2 01 Preconstruction Submittals Respirator Protection Program C.9

21 00 72 00 - Attch 2 01 Preconstruction Submittals Encapsulation Procedures C.11 G

22 00 72 00 - Attch 2 01 Preconstruction Submittals Landfill Qualifications C.14

23 00 72 00 - Attch 2 01 Preconstruction Submittals Work Schedule C.16

24 00 72 00 - Attch 2 01 Preconstruction Submittals Emergency Plans and Fire Prevention Plans C.17 G

25 00 72 00 - Attch 2 01 Preconstruction Submittals Written Hazardous Communication Program C.18

26 00 72 00 - Attch 2 01 Preconstruction Submittals Rental Equipment C.19

27 00 72 00 - Attch 2 07 Cerificates Manufacturer’s Certifications C.10

28 00 72 00 - Attch 2 07 Cerificates Laboratory and Monitoring Qualifications/Certifications C.12

29 00 72 00 - Attch 2 07 Cerificates Asbestos Waste Transporter Certification of Insurance C.13

30 00 72 00 - Attch 2 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets C.15

31 00 72 00 - Attch 2 11 Closeout Submittals Waste Disposal Receipt M.1(1) G

32 00 72 00 - Attch 2 11 Closeout Submittals Air Sampling Results M.1(2) G

33 00 72 00 - Attch 3 01 Preconstruction Submittals Documentation of Training/ Experience C.1

34 00 72 00 - Attch 3 01 Preconstruction Submittals Employee Physicals C.2

35 00 72 00 - Attch 3 01 Preconstruction Submittals Security Documentation C.3

36 00 72 00 - Attch 3 01 Preconstruction Submittals Step-by-Step Abatement Procedures Plan C.4 G

37 00 72 00 - Attch 3 01 Preconstruction Submittals Full Containment Construction Procedures/Drawings C.5 G

38 00 72 00 - Attch 3 01 Preconstruction Submittals Respirator Protection Program C.6

TITLE: WWYK210380

SUBMITTAL REGISTER

JOB NAME: REPLACE DUCTWORK AT POST P39 AND POST P37 TO T37, B3001

LOCATION: Tinker Air Force Base

CONTRACT NO: TBD

CONTRACTOR: TBD

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

Submittal Register_v3_03/07/22

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Trans mittal #

Specification Section

SD

# Submittal Description Item Submitted

Paragraph

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

39 00 72 00 - Attch 3 01 Preconstruction Submittals Work Schedule C.11 G

40 00 72 00 - Attch 3 03 Product Data Materials List C.10

41 00 72 00 - Attch 3 07 Cerificates Manufacturer’s Certifications C.7

42 00 72 00 - Attch 3 07 Cerificates Laboratory and Monitoring Qualifications C.8

43 00 72 00 - Attch 3 11 Closeout Submittals Waste Disposal Receipt M.1.1 G

44 00 72 00 - Attch 3 11 Closeout Submittals Air Sampling Results M.1.2 G

45 00 72 00 - Attch 3 11 Closeout Submittals Verification of Decontamination of Rental Equipment M.1.3

46 00 72 00 - Attch 3a 01 Preconstruction Submittals Removal Procedures B.1 G

47 00 72 00 - Attch 3a 03 Product Data List of Material B.2

48 00 72 00 - Attch 3a 08 Manufacturer's Instructions Material Data Sheets B.3

49 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

50 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

51 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.

52 01 32 16.00 20 01 Preconstruction Submittals Baseline Design Schedule 1.2 G Provide within 10 days of NTP.

53 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO

54 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report

55 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G

56 01 33 16.00 10 01 Preconstruction Submittals Preconstruction Conference 1.5.2.3

57 01 33 16.00 10 01 Preconstruction Submittals DCM Procedures 3.5.1 G

58 01 33 16.00 10 11 Closeout Submittals DD Form 1354 3.8.5 A

59 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G

60 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report

61 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

62 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

63 01 78 00 03 Product Data Warranty Letter 1.7.1

64 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and

(2) hard copies

65 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and

(1) hard copy

66 SOW Product Data Metal Duct 3.2.3 G

67 SOW Product Data Flexible Duct Connector 3.2.4 G

68 SOW Product Data Duct Sealants 3.2.5 G

69 SOW Product Data Balance Dampers 3.2.6 G

70 SOW Product Data Access Doors 3.2.7 G

71 SOW Product Data Smoke Detectors 3.2.8 G

72 SOW Product Data Wrap Insulation 3.2.9 G

73 SOW Product Data Air Devices 3.2.10 G

74 SOW Reports Duct air leakage Test (DALT) 3.2.12 G

75 SOW Reports Test and Balance 3.2.13 G 76 SOW Certificates Verification of Compliant Installation 3.5 G 77 SOW Certificates Request for Government Final Test 3.5 G 78 SOW Certificates Controlled Area Training 1.3.7 G 79 SOW Closeout Submittals Visitor's badge Return Receipt 1.3.8 G

Submittal Register_General Requ

File details come from the government source that posted it. Updated .