This document is a Task Group Instruction (TGI) for replacing deck covering on the USS Higgins (DDG-76), specifically in the Type I Airlock (04-164-2-L) compartment. The work involves removing 16 square feet of existing chemical-resistant flooring and installing a new chemical-resistant flooring system with MIL-PRF-32584, Type IV specifications, in Navy blue color with white flake. The project requires replacing 18 square feet of deck plating, including vertical structural surfaces.
The contract work is scheduled from 25 August 2025 to 15 October 2025, with the Navy's Ship Repair Facility - Japan Regional Maintenance Center (SRF-JRMC) providing supporting services including crane rigging, utility services, and safety/quality assurance inspections. The task instruction notes a potential asbestos hazard and specifies that primer must conform to MIL-PRF-23236, Type V, VI, or VII. The job is part of a larger maintenance package for the USS HIGGINS at a government facility in Japan, with the solicitation targeted at authorized contractors capable of operating in Japan.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6264925RA062.pdf | ||
| N6264925RA062-0001.pdf | ||
| TGI_38KB264503A01_c0v0.pdf | ||
| TGI_38KB263401A01_c0v0.pdf | ||
| TGI_38KB264509A01_c0v0.pdf | ||
| TGI_38KB264508A01_c0v0.pdf | ||
| Att IV GFP_GFM listings.xlsx | XLSX spreadsheet | |
| Att III Request for Information Form.pdf | ||
| TGI_38KB264502A01_c0v0.pdf | ||
| TGI_38KB264506A01_c0v0.pdf | ||
| Att II Price Proposal Form N6264925RA062.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
28-APR-2025 0925
20.14.15.2.9020 (September 2024) ICN: 38KB264507 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 04-164-2-L DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-76 USS HIGGINS KB2 64511
CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 04-164-2-L
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
NN010944
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NANBA, RYOUSUKE 231A 3152436141 28-MAR-2025
APPROVED BY: CODE: PHONE: DATE:
NAKAMURA, YUUJI 231A 3152436041 28-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
NN01-0944
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE 04-164-2-L 04 U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
645A1107
1 SCOPE/PURPOSE:
1.1 Title: Deck Covering in 04-164-2-L; replace
1.2 Location of Work:
1.2.1 Type I Airlock (04-164-2-L)
1.3 Identification:
1.3.1 Quantity (16 SF), Chemical-Resistant Floorings System [Existing]
1.3.2 Quantity (16 SF), Chemical-Resistant Floorings System
Specification: MIL-PRF-32584, Type IV Color: 706 Navy blue color coat with white flake
1.3.3 Quantity (18 SF), Deck Plating, including vertical structural surface up to height of One inch from complete chemical-
TGI Short Form
28-APR-2025 0925
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KB264507 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 04-164-2-L DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-76 USS HIGGINS KB2 64511
CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 04-164-2-L
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
resistant floorings system level
Remarks: The area excepts where insulation is installed.
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard
1.6 Contractor work start date: 25/AUG/2025
1.7 Contractor work completion date: 15/OCT/2025
2 PROCEDURE:
2.1 Accomplish the requirements of 009-26 of Ref. No. One, including Attachment C, for removal of each existing equipment listed in 1.3.1 and installation of each new equipment listed in 1.3.2.
2.1.1 Accomplish the requirements of 009-32 of Ref. No. One, including Table 3, Line(s) 6, Column(s) A, B, and D, for each area listed in 1.3.3. Primer must conform to MIL-PRF-23236, Type V, VI, or VII.
2.2 Notes:
2.2.1 Planner: Code 231A R. Nanba, 243-6141
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN NN01-0944 is related to this TGI.
2.3 Government Furnished Material (GFM): None.
2.4 SRF-JRMC will provide the following service work: (TGI No. 38KB264507S02)
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) symbol(s).
28-APR-2025 0925
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KB264507 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 04-164-2-L DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-76 USS HIGGINS KB2 64511
CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 04-164-2-L
FOUO Pg 3 of 3
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38KB264507 KEY OP: A01
File details come from the government source that posted it. Updated .