TGI_3819P26202_A01_c0v0.pdf
PDF 116 KB Posted
- Solicitation number
- N6264925RA024
About this file
This document is a Task Group Instruction (TGI) for flushing the Main Engine Lube Oil System on the USS Blue Ridge (LCC-19), scheduled for contractor work from June 14, 2027 to August 28, 2027. The instruction specifies a Level II cleaning requirement for the Main Reduction Gear (MRG) Lube Oil system, with detailed procedures for cleaning, flushing, and refilling the system with new lubricating oil (MIL-PRF-17331 Symbol 2190 TEP).
The TGI requires the project team to obtain permission from the Ship's Force Engineering Officer and establish physical security controls. SRF-JRMC (Ship Repair Facility Japan Regional Maintenance Center) will provide supporting services including crane and rigging, utility services (electrical, low pressure air, water, and steam), safety inspections, gas-free inspections, and quality assurance inspections. The work is part of a broader maintenance package for the USS Blue Ridge at Commander, Fleet Activities Yokosuka Naval Base in Japan.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
30-AUG-2024 1600
20.14.15.0.8998 (August 2024) ICN: 3819P26202 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MRG LUBE OIL SYSTEM AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - FLUSH MAIN ENGINE LUBE OIL SYSTEM, 8-86-0-E
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
EM01L249
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
IIKURA, TOSHIAKI 232 3152432374 22-AUG-2024
APPROVED BY: CODE: PHONE: DATE:
OZAWA, AKIHITO 232 3152432493 24-AUG-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM01-L249
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
KANKE, KOUHEI
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
262A1102
1. SCOPE/PURPOSE:
1.1 Title: Main Engine Lube Oil System Flushing; accomplish
1.2 Location of Work:
1.2.1 Engine Room (8-86-0-E)
1.3 Identification:
1.3.1 Quantity (One AY), Main Engine Lubricating Oil System
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Physical Security Watch Required by Ship’s Force: Project Team must notify and obtain Ship’s Force Engineering Officer
TGI Short Form
30-AUG-2024 1600
20.14.15.0.8998 (August 2024) (Continued) ICN: 3819P26202 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MRG LUBE OIL SYSTEM AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - FLUSH MAIN ENGINE LUBE OIL SYSTEM, 8-86-0-E
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
permission to perform Main Reduction Gear (MRG) Lube Oil (LO) system work. Ship’s Force must also setup minimum physical security controls in accordance with NSTM S9086-HK-STM-010/241-4.2.3.
1.6 Contractor work start date: 6/14/2027
1.7 Contractor work completion date: 8/28/2027
2. PROCEDURE:
2.1 Accomplish the requirements of 009-107 of Ref. No. One for cleaning and flushing of each system listed in 1.3.1, using Ref.
No. 3 and Ref. No. 4 for guidance.
2.1.1 Accomplish the requirements of 009-57 of Ref. No. One.
2.1.2 Accomplish the requirements of 009-09 of Ref. No. One.
2.1.3 Ensure General Cleaning must be Level II.
2.1.4 Fill the sump with new system oil.
2.1.4.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing the date and quantity of new oil needed to the SUPERVISOR at least 10 days prior to the required date.
2.2 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.3 Notes:
2.3.1 Planner: Code 232 T. Iikura, 243-2374
2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.3.3 Opening, initial cleaning, and closing of lube oil sump tank (8-94-0-F) will be covered by TGI No. 3819P12334A01 (KTR
TGI).
2.3.4 JCN EM01-L249 is related to this TGI.
2.5 Government Furnished Material (GFM):
2.5.1 SRF-JRMC will provide lubricating oil MIL-PRF-17331 Symbol 2190 TEP of required quantity to fill main lube oil sump upon receipt of Condition Report.
2.6 SRF-JRMC will provide the following service work: (TGI No. 3819P26202S02)
2.6.1 [C740] Crane and crane rigging services.
2.6.2 [X99E] Utility service, electrical.
2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
30-AUG-2024 1600
20.14.15.0.8998 (August 2024) (Continued) ICN: 3819P26202 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MRG LUBE OIL SYSTEM AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - FLUSH MAIN ENGINE LUBE OIL SYSTEM, 8-86-0-E
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.6.6 [C133] QA inspection for (G) Symbol(s).
30-AUG-2024 1600
20.14.15.0.8998 (August 2024) (Continued) ICN: 3819P26202 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MRG LUBE OIL SYSTEM AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: *F/O - FLUSH MAIN ENGINE LUBE OIL SYSTEM, 8-86-0-E
FOUO Pg 4 of 4
OTHER SPECIAL REQUIREMENTS:
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 TM S9086-H7-STM-
010/CH-262
Lubricating Oils, Greases, Specialty Lubricants, and Lubrication Systems
12 N
4 DWG 211-2492126 LO Service Piping - DIAG D Y ALL
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 PFTR: HRs, WELD: HRs, IMCH: HRs, OMCH: HRs, SMTL: HRs, RGRs: HRs, QA: HRs
22/KE PC N
2.2 PNTR: HRs, QA: HRs 22/KE PC N
Flushing Work CFM for gaskets, fasteners, covering material, filter material, jumper piping, blank flanges, cleaning agent, oil analysis and misc.
22/MQ CS N
Process Funding Document. 10/CT OM N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P26202 KEY OP: A01