This is a Scope of Work document for the State of Alabama regarding tennis court resurfacing and cabana installation at the Orange Beach Tennis Center. The project encompasses resurfacing eight tennis courts and installing four cabanas. The tennis court resurfacing involves comprehensive surface preparation including pressure washing at 3500 psi minimum, crack filling and repair using American Patch Binder and the FaultLine Crack Repair System, leveling of low areas to within 1/8 inch tolerance, and application of three coats of Acrytech Acrylic materials (base coat, color concentrate, and finish coat) followed by white pickleball court line painting conforming to American Sports Builders Association specifications. The four cabanas feature black powder-coated steel frames with 3-inch by 3-inch posts spaced 80 feet apart to accommodate existing holes in the court floor, double-sided benches with backrests, and 8-foot canopy lengths installed via direct burial method.
Bidder qualifications include a mandatory minimum of ten years' experience in court construction and resurfacing, with demonstration of at least fifteen major court projects completed within the past five years, including multiple-court resurfacing projects. Bidders must be approved members and Certified Tennis Court Builders of the American Sports Builders Association and approved applicators for both the Acrytech Surface System and FaultLine Crack Repair System. The contractor shall guarantee all labor, materials, and workmanship for one year from final billing, excluding new cracks, and is responsible for obtaining all required Alabama state licenses and general contractor designations. The contractor must verify existing post hole measurements and coordinate site preparation, material delivery in sealed and properly labeled containers, and final site cleanup.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A-Tennis Court Resurfacing:
1. Resurfacing eight tennis courts located at the Orange Beach Tennis Center, as specified below:
a) Thoroughly clean and pressure wash the courts utilizing a pressure washer with at least 3500 psi. Areas of algae, dirt, sand, delaminating surface material, etc. should be removed.
b) All cracks should be filled American Patch Binder (as shown in Item 4) (Grinding or buffing may be necessary to level some the cracks).
c) Install the FaultLine Crack Repair System over the existing cracks to manufacturers specifications.
d) All low areas must be leveled to within 1/8" with American Patch Binder. Mix 100 lbs. silica sand with 2 gallons of Portland Cement and add Binder until desired consistency is achieved.
e) Over the Asphaltic Surface Course, apply one (1) coat of Acrytech Acrylic Resurfacer in accordance with the manufacturer's directions at a rate of not less than .04 - .06 gallons per square yard (32 - 48 gallons for 800 square yards). Dilution rate will not exceed 1part water, 2 parts concentrate.
f) The second coat should be Acrytech Color Concentrate in accordance with the manufacturer's directions at a rate of not less than .03 - .06 gallons per square yard (24 - 48 gallons for 800 square yards). Dilution for this texture coat shall be 2 parts concentrate, 1 part water, and one part sand.
g) The final Finish Coat of Acrytech shall be applied as directed by the manufacturer at a rate of not less than .03 - .06 gallons per square yard (24 - 48 gallons for 800 square yards).
Dilution for this texture coat shall be 2 parts concentrate, 1 part water, and one part sand.
h) White lines conforming to the American Sports Builders Association specifications for pickleball playing lines shall be laid out and Acrytech Textured Line Paint (100% acrylic latex) applied by brush or roller using masking tape or templates.
2. General:
Materials specified for the Color System shall be delivered F.O.B. to the site in sealed, painted containers, properly labeled with Manufacturer’s labels, and stenciled with the proper batch code number. Products packaged or labeled in any other manner will not be accepted. Mixing with clean fresh water shall only be done at the job site. Spreading rates are based upon material prior to mixing with water as directed.
Upon completion, the Contractor shall remove all containers, surplus, materials and debris, and leave the site in a clean and orderly condition acceptable to the Owner.
3. Guarantee:
The Contractor shall guarantee labor, materials, and workmanship (except for the return of any or new cracks) for a period of one (1) year from the date of the final billing. Anytime during this time period, the Contractor shall make necessary repairs to the surface without cost to the Customer.
4. Bidder Qualifications:
Bidder must have ten (10) years minimum experience in court construction and resurfacing.
Upon request, Bidder must present a minimum of fifteen (15) major court projects completed during the past five (5) years, as well as, a list including resurfacing projects with multiple courts.
Bidder must be an approved member and Certified Tennis Court Builder of the American Sports Builders Association
Bidder must be an approved applicator for Acrytech Surface System and the FaultLine Crack Repair System.
Contractor is responsible for obtaining and maintaining all required licenses and professional designations necessary to perform the work, and for ensuring full compliance with all applicable laws and regulations of the State of Alabama and the Alabama Licensing Board for General Contractors.
B-Cabana Specifications:
1. Four (4) Cabanas
2. Canopy Color: Black
3. Canopy Length: 8 feet
4. Bench should be double-sided with a backrest
5. The posts must be 80'' apart to use the existing holes in court floor
1. It is the responsibility of the contractor to verify these measurements to ensure a correct fit in existing holes
6. Installation will be direct burial
7. Black powder-coated frame of heavy gauge steel (3'' x 3'' posts)