Technical Specifications for 26PW01 - SE Stephens Paving and Curb Ramp Improvements - Phase 1
This technical specifications document outlines requirements for the City of Portland, Oregon's paving and curb ramp improvement project on SE Stephens Avenue. The project encompasses pavement rehabilitation, curb ramp construction to meet Americans with Disabilities Act (ADA) standards, and associated site work. The specifications detail materials, construction methods, and quality standards for asphalt paving, portland cement concrete curbs and ramps, drainage systems, and traffic control measures. Key specifications include requirements for asphalt mix design, compaction standards, concrete strength ratings, proper slope and drainage installation, and ADA-compliant curb ramp dimensions and surfaces. The work must comply with Portland's Standard Specifications for Construction, current City of Portland standards, and applicable state and federal regulations. The project area includes specific street segments with defined limits of work, and contractors must coordinate with existing utility locations and minimize disruption to adjacent properties and traffic.
The specifications establish performance standards and inspection requirements throughout the construction process, including material testing, compaction verification, and quality assurance checkpoints. Contractors must provide detailed submittals for materials, equipment, and construction methodologies prior to work commencement. The document specifies warranty periods for completed work, typically 12 months for workmanship defects, and establishes remedies for non-compliance including removal and replacement of substandard materials or work. Traffic control during construction must maintain public safety and access, with specific signage, lane closure, and detour requirements outlined. All work must be completed in compliance with environmental regulations, erosion control requirements, and noise/dust mitigation measures to protect surrounding neighborhoods.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Plans_Vol 2.pdf | ||
| 26PW01 - Bid Opening Results.pdf | ||
| Plans_Vol 1.pdf | ||
| Front Ends.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026 SE Stephens Street Pavement and Curb Ramp Improvements – Phase 1 Project No. 26PW01
TECHNICAL PROVISIONS
WORK TO BE DONE
The Work to be done under this Contract consists of the following on the 26PW01 2026 SE Stephens Street Pavement and Curb Ramp Improvements – Phase 1 project.
1. Furnish, install, and remove temporary traffic control devices and temporary erosion control measures.
2. Construct sidewalk and curb ramps.
3. Construct storm drain improvements.
4. Replace asphalt concrete pavement adjacent to ramps.
5. Grind and inlay asphalt concrete pavement.
6. Install permanent striping.
7. Construct Rectangular Rapid Flashing Beacon (RRFB).
8. Perform additional and incidental Work as called for by the Specifications and Plans.
APPLICABLE SPECIFICATIONS
The Specifications that are applicable to the Work on this Project are the 2024 edition of the "Oregon Standard Specifications for Construction".
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
CLASS OF PROJECT
This is a City of Roseburg Project.
SECTION 00110 - ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND
DEFINITIONS
Comply with the City of Roseburg “General Conditions” and Section 00110 of the Standard Specifications, modified as follows:
00110.05(e) Reference to Websites - Add the following bullet list to the end of this subsection:
• American Traffic Safety Services Association (ATSSA) www.atssa.com
• BidExpress www.bidx.com
• ODOT Construction Section www.oregon.gov/odot/construction/pages/index.aspx
• ODOT Construction Section - Qualified Products List (QPL) www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx
• ODOT Electronic Bidding Information Distribution System (eBids) (Also referred to as ODOT eBids website) ecm.odot.state.or.us/cf/EBIDS/
• ODOT Estimating www.oregon.gov/ODOT/Business/Pages/Steel.aspx
• Oregon Legislative Counsel www.oregonlegislature.gov/lc
• ODOT Procurement Office - Conflict of Interest Guidelines and Disclosure Forms www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx
• ODOT Procurement Office - Construction Contracts Unit Notice of Intent www.oregon.gov/ODOT/Business/Procurement/Pages/NOI.aspx
• ODOT Procurement Office - Construction Contracts Unit prequalification forms www.oregon.gov/odot/business/procurement/pages/bid_award.aspx
• Oregon Secretary of State: State Archives sos.oregon.gov/archives/Pages/default.aspx
• ODOT Traffic Control Plans Unit www.oregon.gov/ODOT/Engineering/Pages/Work-Zone.aspx
• ODOT Traffic Standards www.oregon.gov/ODOT/Engineering/Pages/Signals.aspx
SECTION 00120 - BIDDING REQUIREMENTS AND PROCEDURES
Replace Section 00120 of the Standard Specifications except for the Section number and title, with the following:
Comply with the City of Roseburg “General Conditions” located within this booklet and supplemented and/or modified as follows:
The plans, which are applicable to the work to be performed under the contract, bear title and date as follows:
Project # 26PW01
Examination of Work Site and Bidding Documents – Before submitting a bid, bidders shall carefully examine the site of the proposed work, the bid booklet, plans, and specifications.
Submission of a bid will be considered proof that the bidder has examined the site and bidding documents and understands the conditions to be encountered in performing the work and all requirements of the contract.
The City or its employees or agents will not be responsible for loss or unanticipated costs suffered by the bidder because the bidder failed to become fully informed about all conditions of the work. Any explanation or interpretation of plans and specifications needed by the bidder shall be requested in writing and directed to the following:
• Technical Information pertaining to work on this project:
Rawley Voorhies, P.E., Century West Engineering 5500 Meadows Road, Suite 250 Lake Oswego, OR 97035
(503) 740-8444 rvoorhies@centurywest.com
• All other requests:
City of Roseburg City Recorder 900 SE Douglas Roseburg, OR 97470
(541) 492-6866 anytes@cityofroseburg.org
The request shall be made in sufficient time for the reply to reach the bidders before submission of the bidder’s bid. No requests will be answered that are submitted less than 10 days prior to the bid submission deadline. Refer to “Information to Bidders”. Oral explanations or interpretations given before receiving bids for a project will not be binding. To be binding, interpretation of the plans and specifications by the City must be made by written addendum or written clarification furnished to all plan holders.
Changes to Plans, Specifications, or Quantities before Opening of Bids – The City reserves the right to issue addenda making changes or corrections to the plans, specifications, or quantities. Only holders of bidding documents obtained from the ORPIN will be notified of these changes or corrections by email, sent to the bidder’s email address as it appears on the plan holder’s list files.
The City will not be responsible for failure of bidders to receive addenda sent as described in the preceding paragraph. Bids will be rejected if opened and found not to be based on changes or corrections sent before bids were opened.
Disqualification of Bidders – Any of the following reasons may be sufficient to disqualify a bidder and cause its proposal(s) to be rejected:
• More than one proposal for the same work from an individual, partnership, corporation, or joint venture under the same or different name
• Evidence of collusion among bidders. Participants in collusion will be found not responsible and may be subject to criminal prosecution.
• The reasons cited in ORS 279.037
A bidder will be disqualified if the bidder has:
• Not been prequalified as required by the Information for Bidders, Section 9
• Been declared ineligible by the commissioner of the Bureau of Labor and Industries under ORS 279.361.
• Not registered with the Oregon Construction Contractors Board or been licensed by
State Landscape Contractors Board before submitting a bid (ORS 279.025(2)(k) and (671.530). The bidder’s registration number and expiration date shall be shown in the proposal form, if requested. Failure to furnish the registration number, if requested, will render the bid non-responsive and subject to rejection. (Not required on Federal- Aid projects.)
SECTION 00130 - AWARD AND EXECUTION OF CONTRACT
Replace Section 00130 of the Standard Specifications except for the Section number and
Comply with the City of Roseburg “General Conditions”.
SECTION 00140 - SCOPE OF WORK
Comply with the City of Roseburg “General Conditions” and Section 00140 of the Standard Specifications.
SECTION 00150 - CONTROL OF WORK
Comply with the City of Roseburg “General Conditions” and Section 00150 of the Standard Specifications modified as follows:
00150.10(a) Order of Precedence - Replace this subsection, except for the subsection number and title, with the following:
The Engineer will resolve any discrepancies between these documents in the following order of precedence:
• Contract Change Orders;
• Special Provisions;
• Stamped Agency-prepared drawings specifically applicable to the Project and bearing the Project title;
• Reviewed and accepted, stamped Working Drawings;
• Supplemental Agency-prepared line, grade and cross section data applicable to the project;
• Standard Drawings;
• Approved unstamped Working Drawings;
• City of Roseburg “General Conditions”;
• Standard Specifications; and
• All other Contract Documents not listed above.
Notes on a drawing shall take precedence over drawing details.
Dimensions shown on the drawings, or that can be computed, shall take precedence over scaled dimensions.
00150.15(b) Agency Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Engineer will perform the Agency responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.5 (see Section 00305).
00150.15(c) Contractor Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Contractor shall perform the Contractor responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305).
The Contractor shall perform slope staking including intersections and set stakes defining limits for clearing which approximate right-of-way and easements.
00150.30 Delivery of Notices - Add the following to the end of this subsection:
For purposes of this subsection, the time zone is Pacific Standard Time (PST) to determine time of receipt of notices and other documents. For purposes of this subsection, non-business days are Saturdays, Sundays and legal holidays as defined by ORS 187.010 and 187.020.
Following Notice to Proceed, all notices and other documents submitted to the Contractor by the Engineer, or to the Engineer by the Contractor, electronically under 00170.08:
• If recorded in Doc Express® as received before 5:00 p.m. PST on a business day, it shall be considered as received on the business day on which it was actually received in Doc Express®.
• If recorded in Doc Express® as received on a non-business day, or after 5:00 p.m. PST on a business day, it shall be considered as received at 8:00 a.m. PST on the next business day.
Claims must be submitted on paper documents according to Section 00199.
Add the following subsection:
00150.50(f) Utility Information – The following organizations have been contacted and been provided with the following schedules for relocation of facilities:
Lumen – Utility poles noted for relocation at corner reconstructions along NW Garden Valley Boulevard, as identified on the plans, shall be relocated prior to the start of construction.
The Contractor shall contact those Utilities having buried facilities and request that they locate and mark them for their protection prior to construction.
Utility Contact Person's Name and Phone Number Pacific Power (power provider) Marty Warner (541) 679-3602 Lumen Jordan Kienlen (541) 639-8358 Avista Utilities (natural gas provider) Ryan Peace (541) 671-8729 Roseburg Public Works Department (water) Dan Forrest (541) 643-1396 Roseburg Public Works Department (storm sewer) Jim Johnson (541) 492-6896 ODOT Electrical Crew (J-boxes, push buttons, radar detection coordination)
Brian Henry (541) 957-3669
ODOT Traffic Signals (timing, loops, etc.) Aaron Brooks (541) 957-3500 Roseburg Urban Sanitary Association (sanitary) Ryon Kershner (541) 430-4256
00150.60(d) Access and Work Zone – Construction equipment access shall be limited to existing public right-of-way and the access locations shown on the construction plans.
SECTION 00160 - SOURCE OF MATERIALS
Comply with the City of Roseburg “General Conditions” and Section 00160 of the Standard
SECTION 00165 - QUALITY OF MATERIALS
Comply with the City of Roseburg “General Conditions” and Section 00165 of the Standard
00165.03 Testing by Agency – Replace this subsection except for the subsection number and title, with the following:
No testing will be performed by the City. All testing shall be the responsibility of the Contractor.
00165.04 Cost of Testing – Replace this subsection except for the subsection number and title, with the following:
All testing required to be performed by the Contractor will be considered incidental and will be at the Contractor’s expense.
SECTION 00170 - LEGAL RELATIONS AND RESPONSIBILITIES
Comply with the City of Roseburg “General Conditions” and Section 00170 of the Standard
00170.60 – Safety, Health, and Sanitation Provisions - Add the following paragraph to the end of this subsection:
The Contractor shall provide and maintain proper portable sanitary facilities for their employees and their subcontractors’ employees during day and night shifts that will comply with the regulations of the local and State departments of health and as directed by the Engineer.
SECTION 00180 - PROSECUTION AND PROGRESS
Comply with the City of Roseburg “General Conditions” and Section 00180 of the Standard
00180.40(c) Specific Limitations - Limitations of operations specified in these Special Provisions include, but are not limited to, the following:
Limitations Subsection
Cooperation with Utilities .......................................... 00150.50 Closed Lanes .................................................. 00220.40(e)(1) Special Events ............................................ 00220.40(e)(2)(b) Maintenance Under Traffic ....................................... 00620.43 Opening Sections to Traffic ....................................... 00220.70
The Contractor shall be aware of and subject to schedule limitations in the Standard Specifications that are not listed in this subsection.
00180.41 Project Work Schedules - After the paragraph that begins "One of the following Type…" add the following paragraph:
In addition to the "look ahead" Project Work schedule, a Type A schedule as detailed in the Standard Specifications is required on this Contract.
00180.50(c) Beginning of Contract Time - Replace this subsection except for the subsection number and title, with the following:
When the Contract Time is stated in Calendar Days, a counting of Contract Calendar Days will begin on the day “Notice to Proceed” is issued by the City.
00180.85 Failure to Complete on Time; Liquidated Damages - Replace this subsection, except for the subsection number and title, with the following:
(a) Time is of the Essence - Time is of the essence in the Contractor's performance of the Contract. It is essential and in the public interest that the Contractor prosecute the Work vigorously to Contract completion and within Contract Time or adjusted Contract Time.
The Agency does not waive any rights under the Contract by permitting the Contractor to continue to perform the Contract, or any part of it, after the Contract Time or adjusted Contract Time has expired.
(b) Liquidated Damages - Delays in the Contractor's performance of the Work will cause the Agency to sustain damages; increase risk to, inconvenience, and interfere with the traveling public and commerce; and increase costs to taxpayers. Because the Agency finds it is unduly burdensome and difficult to demonstrate the exact dollar value of such damages, the Contractor agrees to pay to the Agency, not as a penalty but as liquidated damages, the amount(s) determined as specified below for each Calendar Day the Work remains incomplete after the expiration of the Contract Time or adjusted Contract Time applicable to that Work. The liquidated damages shall constitute payment in full only of damages incurred by the Agency due to the Contractor's failure to complete the Work on time.
Payment by the Contractor of liquidated damages does not release the Contractor from its obligation to fully and timely perform the Contract according to its terms. Nor does acceptance of liquidated damages by the Agency constitute a waiver of the Agency's right to collect any additional damages it may sustain by reason of the Contractor's failure to fully perform the Contract according to its terms.
If the Contract is terminated according to 00180.90(a), and if the Work has not been completed by other means on or before the expiration of Contract Time or adjusted Contract Time, liquidated damages will be assessed against the Contractor for the duration of time reasonably required to complete the Work.
Liquidated damages will be assessed per Paragraph 11 of the Bid Form.
SECTION 00190 - MEASUREMENT OF PAY QUANTITIES
Comply with the City of Roseburg “General Conditions” and Section 00190 of the Standard
SECTION 00195 - PAYMENT
Comply with the City of Roseburg “General Conditions” and Section 00195 of the Standard
00195.12(d) Steel Materials Pay Item Selection - Add the following paragraph to the end of this subsection:
No Pay Items under this Contract qualify for the steel escalation/de-escalation program for this Project.
SECTION 00196 - PAYMENT FOR EXTRA WORK
Comply with the City of Roseburg “General Conditions” and Section 00196 of the Standard
SECTION 00197 - PAYMENT FOR FORCE ACCOUNT WORK
Comply with the City of Roseburg “General Conditions” and Section 00197 of the Standard
SECTION 00199 - DISAGREEMENTS, PROTESTS, AND CLAIMS
Replace Section 00199 of the Standard Specifications except for the Section number and
Comply with the City of Roseburg “General Conditions”.
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.02(a) General Requirements - Replace the bullet that begins, "Do not stop or hold vehicles..." with the following bullet:
• Maintain at least one lane of traffic in each direction of travel at all times. Do not stop or hold traffic in any one direction for more than 5 minutes. Do not block driveways, intersections, or approaches. Provide reasonable access to driveways, intersections and approaches at no additional cost to the Agency.
Add the following bullets to the end of the bullet list:
• Provide minimum 72 hours notice to affected property owner prior to closure or blocking of driveways.
• Maintain and coordinate access to all affected properties. Allow unrestricted vehicle and pedestrian access to all properties outside the allowable working hours.
• When an abrupt edge is created by excavation, protect traffic using the “EXCAVATION ABRUPT EDGE DETAIL” and the “TYPICAL ABRUPT EDGE SIGNING DETAIL” configurations shown on Standard Drawings TM800.
• Do not allow vertical differences in pavement height, created by paving or removal, to exceed 2 inches. Pavements not meeting this requirement shall either be closed to traffic or provide tapered asphalt pavement wedges across all pavement joints exposed to traffic according to 00620.40(d)
• Signs, including ‘Open For Business’ placards, required shall be furnished by the Contractor and included in Bid Item 3 Temporary Protection and Direction of Traffic.
Signs shall be approximately 24” wide by 36” high. Contractor shall accommodate signage at the start and endpoints of pedestrian routes adjacent to work zones and account for signage in TPAR.
00220.02(b) Temporary Pedestrian Accessible Route (TPAR) Plan - Add the following bullets to the end of the bullet list:
• For any single curb ramp/intersection corner, the TPAR shall not be in place for any longer than 7 Calendar Days, unless otherwise indicated on the plans. All curb ramp work must be completed before the TPAR is removed.
• The Agency will allow more than one corner of an intersection to be constructed concurrently if the Contractor submits, and the City approves, a TPAR that shows adequate pedestrian accessibility through the work zone.
00220.03(b) Road Closures – In addition to the requirements of 0220.03(b), if public streets are to be closed for any duration, obtain the required permits from the City’s Public Works Department and comply with all requirements including any notification requirements for the affected residences and required public notifications. Generally, provide a 72-hour initial public notification published in the local paper, broadcast on at least one local radio station, and as a public service announcement on the local television station. Maintain access for residences and school employees.
00220.03(b) Closures - Add the following bullet to the end of the bullet list:
• Obtain a City of Roseburg Permit for all street closures prior to closing the street. Obtain permit at least 7 days in advance of actual closures.
00220.03 Work Zone Notifications - Add the following bullet to the end of the sub-section:
(c) Permitting and Public Notification - Obtain a City of Roseburg Street Closure Permit for all lane, shoulder or sidewalk closures prior to closing. Obtain permit at least 7 days in advance of actual closure.
• The City will provide general notification through the news media of the scope of the project. However, the Contractor shall provide a minimum of seven days’ notice to each property owner who is affected by the temporary interruption of their access, one-way restrictions, detours, temporary road closures, restricted parking, etc. It shall be the Contractor’s responsibility to provide written and verbal notice to each property owner, resident, or business manager whose access is restricted or limited.
• It shall be the Contractor’s responsibility to contact all emergency responding facilities such as, but not limited to, City police, City fire department and ambulance services before any one way or detour routes are established.
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
SE Stephens Street Curb Ramp Construction Work (and associated improvements):
Travel lanes shall be a minimum of 14’ wide when providing a single lane, or 11’ wide when providing two lanes, unless otherwise noted.
No more than 4 parking stalls per block shall be closed at any given time.
Unless otherwise indicated in the plans or approved in writing by the Engineer, maintain two-lane traffic during all daily work hour times. One Traffic Lane may be closed when allowed, shown, or directed only at ramp bulb-out locations and during the following periods of time except as indicated in 00220.40(e-2). Maintain minimum one-lane, one-way traffic at all times.
• Daily, Monday through Friday between 6:00 a.m. and 3:00 p.m.
Unless otherwise indicated in the plans or approved in writing by the Engineer, maintain two-lane, two-way traffic on adjoining side streets and business access approaches during all daily work hour times. One-lane, two-way traffic on adjoining public side streets and business access approaches shall be allowed during nightly work hours, if approved by the City.
Contractor to provide necessary flaggers, flagger station lighting, etc. at all times that 2-lane, 2-way traffic is not provided on two-way streets.
Only one corner of an intersection shall be closed for construction at a time, unless the Contractor submits, and the City approves, a TPAR that shows adequate pedestrian accessibility through the work zone. Any TPAR on private property is the sole responsibility of the contractor and requires the contractor to obtain approval from the property owner in advance of placing the TPAR.
If no active construction will occur within the work zone adjacent to a lane closure within the upcoming 24-hour period, the lane closure must be removed.
SE Stephens Street Grind/Inlay Paving and Markers/Markings:
No work shall occur during daytime hours.
Travel lanes shall be a minimum of 14’ wide when providing a single lane, or 11’ wide when providing two lanes, unless otherwise noted.
A minimum of one-lane, one-way traffic shall be maintained during the following times, unless approved in writing by the City:
• Nightly, Sunday through Friday between 7:00 PM and 6:00 am.
Maintain a minimum of one-lane, two-way traffic on adjoining business access approaches at all times, unless otherwise indicated in the plans or approved in writing by the property owner. Any access closures and/or traffic detours on private property are the sole responsibility of the contractor and require the contractor to obtain approval from the property owner in writing.
Maintain a minimum of one-lane, two-way traffic on adjoining public side street approaches at all times, unless otherwise indicated in the plans or approved in writing by the Engineer.
00220.40(e)(2)b. Special Events – Add the following to the end of this subsection:
The following special events will occur during this Project:
Graffiti Weekend – July 8th – 11th, 2026 Douglas County Fair – August 5th – 8th, 2026
SECTION 00221 – COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
Comply with Section 00221 of the Standard Specifications modified as follows:
00221.01(b) Definitions – Add the following to the end of the subsection:
Temporary Walk – Temporary Surfacing for a sidewalk or Multi-Use Path designated to be used by pedestrians, bicyclists, or other non-motorized users.
00221.06 Traffic Control Plan – Replace the section in its entirety with the following:
The Contractor shall be responsible for developing all TCP’s for the project. Submit the TCP’s for approval a minimum of 10 Calendar Days before construction begins. The Contractor shall provide Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD, and the following:
A TPAR plan that includes:
o Details and features used to provide pedestrian accessibility.
o Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.
o Temporary alternate facilities or detour routes for pedestrian traffic.
Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.
Proposed order and duration of the TCM.
A detailed temporary striping plan.
If modifications are made to the TCP, submit Working Drawings, according to 00221.06(b), at least 14 calendar days before beginning construction activities that required the TCP changes.
00221.90(a) Pay Quantities – replace this subsection, except for the subsection number and title, with the following:
The accepted quantities of work zone TCM and TCD will be paid for according to 00222.90, 00223.90, 00224.90, 00225.90, 00226.90, 00227.90, and 00228.90. Items not specifically listed in the Schedule of Values shall be considered incidental to the Temporary Protection and Direction of Traffic item.
00221.90(b) Temporary Protection and Direction of Traffic - Add the following bullets to the end of this section:
• Removing permanent pavement striping.
• Furnishing, installing, maintaining, moving, and removing temporary pavement striping or removable tape.
• Furnishing, installing, maintaining, moving, and removing temporary pavement markers.
• Furnishing, placing, replacing, maintaining, moving and removing temporary plastic drums.
• Furnishing, placing, replacing, maintaining, moving and removing temporary sign supports.
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
Comply with Section 00222 of the Standard Specifications modified as follows:
00222.40(a)(2) Regulatory Speed Zone Signs - Delete the words "State Traffic" from the first paragraph.
00222.40(e) Temporary Signs - Add the following to the end of the bullet list:
• Install an 18 by 24-inch "NO PARKING" (R8-3a) sign in every block where on-street parking is prohibited, facing incoming traffic.
• When construction requires bicycles to use the Traffic Lanes, install a "Bicycle ON ROADWAY" (CW11-1) symbol sign in advance of, and on 1/2 mile spacing through the affected area. Keep the signs in place until completion of the Shoulder or bikeway final surface.
00222.45(b) Portable Changeable Message Signs - Add the following to the end of the bullet list:
• PCMS shall be in place 7 calendar days in advance of construction (both directions) and remain in place throughout the duration of construction activities.
• PCMS shall be placed at Highway 99 in advance of construction (northbound) and remain in place when construction signage is installed on Stephens Street
SECTION 00223 – WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
Comply with Section 00223 of the Standard Specifications modified as follows:
00223.90 Payment – Replace this subsection, except for the subsection number and title, with the following:
No separate or additional payment will be made for work zone traffic control labor, equipment and/or vehicles, unless listed in the Schedule of Values. Items not specifically listed in the Schedule of Values shall be considered incidental to the Temporary Protection and Direction of Traffic item.
SECTION 00224 – TEMPORARY TRAFFIC CHANNELIZING DEVICES
Comply with Section 00224 of the Standard Specifications modified as follows:
00224.10 Tubular Markers - Add the following paragraph to the end of this subsection:
Blue plastic tubular markers shall be reflectorized with at least two blue, flexible reflective bands at least 3 inches wide, securely attached no more than 2 inches from the top with no more than 6 inches but not less than 1 inch between the bands.
SECTION 00225 – TEMPORARY PAVEMENT MARKING
Comply with Section 00225 of the Standard Specifications modified as follows:
00225.83(b) Temporary Tape - Replace this subsection, except for the subsection number and title, with the following:
No separate measurement will be made for removable, non-removable, and non-reflective tape.
00225.90 Payment - Replace this section with the following:
No separate or additional payment will be made for temporary pavement markings.
SECTION 00280 - EROSION AND SEDIMENT CONTROL
Comply with Section 00280 of the Standard Specifications modified as follows:
00280.00 Scope - Add the following:
The ESCP has not been developed as a part of the plan set. Prepare and submit an ESCP to be approved by the Engineer and Agency prior to beginning Work. Engineer may require additional erosion and sediment control measures at no additional cost to the Agency in order to approve submitted methods of operations and scheduling.
00280.06 Erosion and Sediment Control Manager - Delete this subsection.
00280.62 Inspection and Monitoring - Replace this subsection, except for the subsection number and title, with the following:
Inspect the Project Site and all ESC devices for potential erosion or sediment movement on a weekly basis and when 1/2 inch or more of rainfall occurs within a 24-hour period, including weekends and holidays.
If a significant noncompliance or serious water quality issue occurs that could endanger health or the environment, verbally report it to the Engineer with 24 hours.
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications.
SECTION 00305 - CONSTRUCTION SURVEY WORK
Comply with Section 00305 of the Standard Specifications.
SECTION 00310 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Comply with Section 00310 of the Standard Specifications modified as follows:
00310.45 Removal of Existing Surfaces
Remove sidewalk and surfacings as shown on the Plans. Sidewalk and surfacings to be removed shall be cut in neat, straight lines with vertical edges along the limits of removal.
The cut lines for removal of asphaltic or cement concrete pavement shall be reviewed and approved by the Engineer in the field before cutting. Demolish and remove concrete curbs, islands and other surfacings as directed by the Engineer or as shown. Make a vertical saw cut between any existing curb that is to remain and portion that is to be removed. Remove roadway pavement in the street adjacent to curbs and islands as shown on the Plan or as directed by the Engineer. Remove existing aggregate underneath concrete and/or pavements to be removed, and existing concrete underneath asphalt pavements to be removed, to allow for new concrete pavement, base aggregate and roadway pavement to be constructed as indicated in the Plans.
00310.92 Separate Item Basis - Add the following:
When the Contract Schedule of Items does not indicate payment for Work on a separate item basis, no separate or additional payment will be made. Payment will be included in payment made according to 00310.90 or 00310.91, as applicable.
The paragraph that begins with the words “Item (d) includes…” is replaced with the following:
Item (d) includes all work associated with surfacing removal including but not limited to saw cutting, removal of existing asphalt, curbs, islands, sidewalks and other surfacings to the limits and grades shown on the plans. No separate or additional payment will be made for the removal of other features or earthwork inside the removal of surfacings limits as this work is considered incidental.
SECTION 00320 - CLEARING AND GRUBBING
Comply with Section 00320 of the Standard Specifications.
SECTION 00330 – EARTHWORK
Comply with Section 00330 of the Standard Specifications modified as follows:
00330.03 Basis of Performance - Add the following paragraph to the end of this subsection:
Perform all earthwork under this Section on the excavation basis.
00330.42(c)(3) Embankment Slope Protection - Add the following paragraph:
Construct the outer 6 inches of embankments with suitable Materials to establish slope stabilization through permanent seeding. If suitable material is not available, provide suitable materials from a Contractor-provided source which conforms to the requirements of 00330.11 or 00330.13 and provides favorable conditions for germination of seed and growth of grass.
00330.45 Filling of Holes - Replace the last two sentences of this subsection with the following:
No separate or additional payment will be made for this Work.
00330.80 Measurement - Replace this subsection, except for the subsection number and
No measurement of quantities will be made for Work performed under this Section.
SECTION 00331 - SUBGRADE STABILIZATION
Comply with Section 00331 of the Standard Specifications.
SECTION 00340 - WATERING
Comply with Section 00340 of the Standard Specifications.
SECTION 00440 - COMMERCIAL GRADE CONCRETE
Comply with Section 00440 of the Standard Specifications modified as follows:
00440.02 Abbreviations and Definitions:
ASTV – Actual Strength Test Value – See 02001.02 for definition.
00440.12 Properties of Commercial Grade Concrete - Replace the bullet that begins "Compressive strength…" with the following bullet:
• Compressive Strength - ASTV minimum of 4,000 psi at 28 days for driveways, 5,000 psi at 7 days for manhole frame adjustments, and minimum 3,300 psi at 28 days for all other commercial grade concrete.
00440.14(d) Hardened CGC - Add the following to the end of this subsection:
The ASTV at 28 Days is the average compressive strength of the three cylinders tested.
Discard all specimens that show definite evidence, other than low strength, of improper sampling, molding, handling, curing, or testing. The average strength of the remaining cylinders shall then be considered the test result.
SECTION 00405 – TRENCH EXCAVATION, BEDDING, AND BACKFILL
Comply with Section 00405 of the Standard Specifications modified as follows:
00405.12 Bedding – Delete the second and fourth items from the bulleted list.
00405.42 Rock Excavation – Replace the second paragraph with the following:
The use of explosives shall not be allowed.
00405.46(a) General – Add the following to the end of the paragraph beginning with “Thoroughly tamp and compact …”:
Contractor may elect to use non-vibratory compaction methods to achieve the required density. Indirect damage resulting from vibratory compaction equipment to adjacent structures shall be the responsibility of the Contractor.
00405.46(e) Temporary Trench Plating - Add the following:
Temporary trench plating may not be used for more than a maximum of 48 hours at any one location. Any period exceeding 48 hours will require the backfilling of the trench with aggregate and capping with temporary ACP.
00405.48(c) Pavement, Curb, and Sidewalk – Replace the first two paragraphs with the following:
Use saws to cut Portland cement concrete pavement, curbs, and sidewalks, regardless of thickness. The trench shall be cut as shown on the Contract Drawings and be parallel to the pipe centerline. Slurry waste generated from saw cutting shall be removed by vacuum immediately following the completion of the saw cutting.
00405.80 Measurement – Replace the first paragraph with the following:
No measurement of quantities will be made for work performed under this Section.
00405.90 Payment - Replace this subsection with the following:
No separate or additional payment will be made for trench excavation, bedding, and backfill.
SECTION 00415 – VIDEO PIPE INSPECTION
Comply with Section 00415 of the Standard Specifications modified as follows:
00415.90 Payment - Replace this subsection with the following:
No separate or additional payment will be made for video pipe inspection.
SECTION 00445 – SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE
Comply with Section 00445 of the Standard Specifications modified as follows:
00445.02 – Contractor’s Options– Delete this subsection.
00445.80(a) Pipes– Modify this subsection as follows:
The quantities of pipe of the various kinds, types, and sizes, will be measured on the length basis, and will be determined by the length of installation as follows:
Length – The length will be measured, with no deduction of Structures or fittings, along the pipe flow line from center to center of manholes, inlets, or special sections; or the ends of pipe or end sections, whichever is appliable.
00445.91 Payment – Modify this subsection beginning with Item (a) includes as follows:
Item (a) includes all pipe sizes and depths. Item (a) includes all fittings, and couplings.
00445.91 Payment – Supplement this subsection with the following:
No separate or additional payment will be made for:
Exploratory excavations Saw cutting Temporary trench resurfacing Trench protection Pipe bedding Dewatering Bypass of sewer or storm Connections to existing and proposed storm sewer pipes from new structures Potholing of existing utilities potentially in conflict in order to determine grade of storm sewer laterals backfill Tee, wye, or coupling fittings Video pipe inspection Pipe runs less than 5 feet in length
00445.91 Payment – Delete the sentence “Video pipe inspection will be paid for according to 00415.90.”
SECTION 00470 – MANHOLES, CATCH BASINS, AND INLETS
Comply with Section 00470 of the Standard Specifications, modified as follows:
00470.10 Materials – Add the following to the end of the section:
Sizes of existing pipes are to be verified by the contractor prior to ordering materials.
00470.18 Catch Basin and Curb Inlet Water Quality Filter Insert – Furnish new water quality filter inserts for all newly constructed catch basins and curb inlets. Water quality inserts shall provide filtration through a filter screen or filter liner, and hydrocarbon capture shall be effected using a non-leaching absorbent material contained in a pouch or similar removable restraint. Hydrocarbon absorbent shall not be placed at an exposed location at the entry to the filter that would allow blinding by debris and sediment without provision for self-cleaning in operation. The filter shall conform to the dimensions of the inlet in which it is applied, allow removal and replacement of all internal components, and allow complete inspection and cleaning in the field.
The filter support frame shall be constructed of type 304 stainless steel. Filter screen, when used in place of filter liner, shall be type 304 or 316 stainless steel, with an apparent opening size of not less than 4 U.S. mesh. Filter liner, when used in place of filter screen, shall be woven polypropylene geotextile fabric liner with an apparent opening size (AOS) of not less than 40 U.S. mesh as determined by ASTM D 4751. Filter liner shall include a support basket of polypropylene geogrid with stainless steel cable reinforcement. Filter frame shall be rated at a minimum 25-year service life. All other materials, with the exception of the hydrocarbon absorbent, shall have a rated service life in excess of 2 years. All hardware and anchors shall be 304 stainless steel. Resin anchor systems shall be used for mounting hardware.
00470.40 (b) Pipe Connections – Add the following to the end of the section:
Inverts for existing pipes are to be verified by the contractor and field fit as required.
00470.90 Payment – Modify this subsection as follows:
Add the following paragraph after the pay item list:
Item (d) shall include furnishing and installing one (1) water quality filter insert per inlet.
Add the following:
Item (c), (d), and (k) includes all pipe stub connections to the new structure.
Add the following bulleted list as the end of the section:
Saw cutting Temporary trench restoration Trench protection Potholing
SECTION 00490 – WORK ON EXISTING SEWERS AND STRUCTURES
Comply with Section 00490 of the Standard Specifications modified as follows.
00490.90 Payment – Add the following pay item:
Pay Item Unit of Measurement
(j) Reconstructing Meter Boxes……….. …………………................. EA
Item (j) includes removing and disposing of the existing water meter box, furnishing a new water meter box, meter box lid, and adjusting the new meter box to grade. All water meter boxes shall be DFW Meter Box meeting City standards.
SECTION 00620 – COLD PLANE PAVEMENT REMOVAL
Comply with Section 00620 of the Standard Specifications modified as follows:
00620.80 Measurement – Add the following to the end of this section:
Areas marked in the field by the Engineer as requiring additional spot grinding prior to mainline overlay paving or additional grinding after the initial cold planning operations for mainline inlay paving will be measured under the bid item for “Cold Plane Pavement Removal, 0” - 1” Deep”.
00620.90 Payment – Replace this subsection, except for the subsection number and title, with the following:
Pay Item Unit of Measurement
(j) Cold Plane Pavement Removal, ____ Deep……………...……….SY
(k) Cold Plane Pavement Removal, 0 – 1 Inch Deep.…………………….SY
In item (a), the depth will be inserted in the blank.
Payment will be payment in full for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.
No separate or additional payment will be made for temporary wedges constructed, maintained, and removed under 00620.40(d), or for replacement of cutting teeth.
SECTION 00641 - AGGREGATE SUBBASE, BASE, AND SHOULDERS
Comply with Section 00641 of the Standard Specifications modified as follows:
00641.10(a) Base and Shoulder Aggregate - Replace the first paragraph with the following:
Aggregate for bases and Shoulders shall be sized as specified. Base aggregate shall be dense-graded 3/4" - 0 for sidewalk, curb ramp, and curb construction. Use clean, hard, durable aggregates, reasonably well-graded from maximum size to dust.
Existing aggregate exposed during the removal of existing asphalt shall be left in place, regraded, recompacted and used as a base for new asphalt concrete pavement (ACP).
Import 3/4" – 0 aggregate shall be utilized for fine grading as needed if Engineer determines that existing aggregate has insufficient gradation, fines, etc.
00641.16(d) Existing Aggregate Base to Remain – Existing aggregate to remain as a base for ACP will be accepted based on the Engineer’s visual inspection.
Add the following subsection:
00641.44(c) Existing Aggregate Base Course to Remain – Shape and compact existing aggregate in accordance with subsection 00641.44(a).
00641.80 Volume Basis - Replace this subsection, except for the subsection number and title, with the following:
Except for approved Subgrade stabilization, backfill below elevations shown, and ordered changes, field measurement of the quantity will not be performed.
00641.90 Payment - Replace this subsection, except for the subsection number and title, No separate or additional payment will be made for base and/or shoulder Aggregates.
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
Comply with Section 00730 of the Standard Specifications modified as follows:
00730.90 Payment - Replace this subsection, except for the subsection number and title, No separate or additional payment will be made for Emulsified Asphalt tack coat.
SECTION 00744 - ASPHALT CONCRETE PAVEMENT
Comply with Section 00744 of the Standard Specifications modified as follows:
00744.00 Scope – Replace this subsection with the following:
This work consists of constructing asphalt concrete pavement (ACP) to the lines, grades, thicknesses, and cross sections shown or established.
Where shown, work shall include furnishing all materials, equipment, labor, and incidentals for mixing aramid fiber into ACP, when aramid fiber is required as a mixture ingredient. The fiber reinforced ACP will be subject to all requirements for ACP in this Section.
00744.02 Definitions – Insert the following in alphabetical order:
Reinforcing Fibers – An asphalt concrete additive consisting of aramid fibers blended at time of mixing.
00744.05 Reinforcement Fiber Blend - Provide a reinforcing fiber blend of Virgin Polyolefins and Virgin Aramids conforming to the minimum requirements below. Design JMF without the reinforcing fibers. Do not alter the final mix design for the addition of fiber at the asphalt plant.
Certified reinforcing fiber test data for the fibers to be used on the project shall be submitted at the time of the JMF submittal.
Property Measure Standard Material Aramid ASTM D276 Form Monofilament fibers Manufacturer Certification Length 0.75 inches (+/- 10%) Manufacturer Certification Specific Gravity 1.44 ASTM D276 Minimum Tensile Strength 400,000 psi ASTM D3379 Maximum Tensile Elongation 1.8 % ASTM D3379 Degradation Temperature 800 degrees F ASTM D276 Acid and Alkali Resistance Inert Manufacturer Certification
Submit the following:
Identify the mixing plant.
Provide a fiber product data sheet and certification from the manufacturer that the fiber product supplied meets the requirements of this specification.
Manufacturer’s instructions and general recommendations.
Provide the following from product supplier at least three weeks prior to ACP production.
o The supplier’s specified mix rate for the aramid product.
o Evidence showing how many times, if any, the supplier’s fiber product has been successfully produced at the asphalt plant to be used for the project.
o Process for introducing the fiber product to the mix.
00744.11(a) Asphalt Cement - Add the following to the end of this subsection:
Provide PG 70-22ER or PG 64-22 grade asphalt cement for this Project as indicated in the plans.
00744.18 Fiber Storage, Mixing and Mix Production - Store, mix and produce the fiber reinforced ACP mixture in accordance with the following requirements:
1. Deliver fiber-reinforcement in sealed, undamaged containers with labels intact and legible, indicating material name and lot number.
2. Deliver fiber-reinforcement to location where it will be added to each batch or loaded into the mixer.
3. Store materials covered and off the ground. Keep sand and dust out of boxes and do not allow boxes to become wet.
4. Add aramid and polyolefin reinforcing fiber blends at a dosage rate of one (1) pound fiber per one (1) ton of asphalt. Non-aramid fiber blends, aramid fiber blends with dosages less than 1 pound per ton, or fiber ton equivalents will not be accepted.
5. Have a fiber manufacturer’s representative on site during mixing and production.
6. Batch Plant - When a batch plant is used, add fiber to the aggregate in the weigh hopper and increase both dry and wet mixing times. Ensure that the fiber is uniformly distributed before the injection of asphalt cement into the mixture.
7. Drum Plant:
a. Inject fibers through the RAP collar manually or by feeding them with a metered air blown system to promote rapid and complete fiber dispersion. Rate the feeding of fibers with the rate the plant is producing asphalt mix. If there is any evidence of fiber bundles at the discharge chute, increase the mixing time and/or temperature or change the angle of the fiber feeder line to increase dry mixing time.
b. Add fibers continuously and in a steady uniform manner. Provide automated proportioning devices and control delivery within ±10% of the mass of the fibers required. Perform an equipment calibration to the satisfaction of the fiber manufacturer’s representative to show that the fiber is being accurately metered and uniformly distributed into the mix.
Include the following with the air blown system:
Low level indicators No-flow indicators A printout of feed rate status in pounds/minute A section of transparent pipe in the fiber supply line for observing consistency of flow or feed.
Manufacturer’s representative’s approval of fiber addition system
00744.19 Reinforcement Fiber Quality Control - Provide reinforcement fiber quality control according to the following:
1. Collect a 10kg sample of mix from the discharge chute during first 50 tons of production. Visually assess the state of aramid fibers and rate the sample as “Pass” or “Fail”.
i. “Pass” = All fibers exist in an Individual State and no Undistributed Clips or Agitated Bundles of fiber are detected.
ii. “Fail” = One or more Undistributed Clips or Agitated Bundles are detected.
2. If a sample is rated as “Fail”, adjust mixing operations to improve fiber dispersion and repeat Step 1 above.
3. If Visual Test results in three consecutive “Fail” ratings, stop production until a plan for corrective action is approved by the Engineer.
4. In addition to Visual Test, use a shovel to inspect the fiber reinforced mix in the back of first three trucks and every tenth truck thereafter to confirm adequate blending of the fiber.
5. Remove any observed fiber bundles from placed mixture and adjust operations per the manufacturer’s recommendation to eliminate future fiber bundle development, and repeat Steps 1 through 3 above to confirm adequate aramid fiber dispersion.
Insert the following new section:
00744.46 Asphalt Side Street Connections – Pave all side street connections prior to paving the mainline.
Insert the following new section:
00744.50 Joints - Sand seal all joints following the final lift. Width of joint seal coat shall be no less than four inches and no more than six inches.
Add the following subsection:
00744.51 Opening Sections to Traffic - Schedule work so that, during the same shift, the surfaces being paved are paved full width and length through the wearing Course before opening to traffic.
00744.70 Pavement Smoothness – At the end of the first paragraph, insert the following sentence:
These tolerances shall apply to water valve boxes, manhole lids and other utility appurtenances that can be adjusted as part of the paving operations.
00744.90 Payment – In the first group of bulleted items, replace the third bullet with the following:
The words "in Leveling", "in Temporary", "in Leveling and Temporary", or “with Fibers” will be inserted in the third blank when applicable.
In the second group of bulleted items, insert the following…
This is the start of the file's text. The full file is on GovTribe.