This is a Technical Factors evaluation document for a Request for Quote (RFQ) solicitation (W50S6T26QA036) issued by the 144 Fighter Wing, Department of the Army National Guard, for repair and replacement work on an aircraft arresting system.

The solicitation seeks contractors to remove and replace a foundation concrete slab and eight anchor bolts for a Barrier Arresting Kit (BAK-12) Aircraft Arresting System located at Fresno, California. This is a Women-Owned Small Business (WOSB) set-aside with NAICS code 237310 and will be awarded as a Firm Fixed Price (FFP) contract without negotiations. To be considered for award, contractors must submit: (1) a written work procedure addressing Statement of Work requirements, limited to three pages; (2) identification of any subcontractors at time of quote submission, including primary and alternative options with business names and cities; and (3) proof of qualifications, specifically a current California B or C-8 contractor's license held by the prime or subcontractor with license number provided, or equivalent credential/certificate. All prospective quoters must possess a CAGE code and be registered with SAM.gov. Quotes are due by a specified deadline and must be submitted electronically to jarrod.sanchez@us.af.mil and justin.scales.1@us.af.mil. A site visit is available August 27, 2026 at 9:00 AM at the West gate near 5323 E McKinley Ave, Fresno, CA 93727. Submitted offers are valid through September 30, 2026.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Factors Project: Repair Concrete Foundation and Replace BAK-12 Anchor Bolts To be considered for award a contractor must have a fully developed plan to execute contract performance and satisfy the statement of work (SOW). The following concerns must be addressed to be considered for award.

1. Procedure. Provide a brief written work procedure to satisfy the SOW requirements of section 3.0. (Response limited to three pages).

2. Acknowledgment of subcontractors. If a subcontractor is utilized, they must be selected at the time of quote submission. A primary and alternative may be referenced. Provide the business name and city of the selected subcontractor(s).

3. Qualifications. The SOW requires qualifications to prove competence in the area of work. A current CA B or C-8 license by the prime or the sub-contractor will satisfy this requirement. If a CA B or C-8 is held provide the license number. In lieu of a license an equivalent credential/certificate may suffice and must be provided to evaluate competency.