TECHNICAL EXHIBIT Z
CHAPTER 2
FACILITY SYSTEMS
2-1 RELIABILITY CENTERED MAINTENANCE (RCM) METHODOLOGY. The objective of ITM for fixed fire protection systems is to assure that the systems will function on demand. RCM analysis identifies any defects responsible for system malfunction and how they can be detected and corrected before a fire. A byproduct of RCM analysis is a list of ITM tasks and how often they must be accomplished (frequencies) to achieve a desired reliability (0.99 for this UFC; reference paragraph 1.6). The methodology used to develop the ITM tasks in this UFC is summarized in AFCESA Technical Report, “Risk Based Reliability Centered Maintenance of DoD Fire Protection Systems," January 1999. The model used in the report assumed a system demand of one event in fifty (1/50) years and a task effectiveness (ITM done right) of 99 percent. This RCM analysis emphasized task effectiveness (is it the right thing to do and is it done right?) and timeliness (is it done before a demand?). The resulting list of tasks and frequencies, therefore, considered frequency and probabilities of demands and failures.
2-2 ITM TASK DESCRIPTIONS AND FREQUENCIES
Note: Military Family Housing Systems are addressed in Chapter 3.
2-2.1 Task Descriptions. The ITM tasks in Tables 2-1 through 2-19 and 3-1 through 3-2 were selected to assure the fire protection would function upon demand.
2-2.1.1. Supervised Components. Supervision of components increases the likelihood that conditions or faults will be detected without an inspection activity. In these cases, the ITM task is to respond to the alarm and to test the supervisor device (e.g., valve tamper switch) periodically. Accordingly, the tables reflect the improved fault or condition detection by specifying less frequent inspections. Different frequencies are recommended for monitored and for unmonitored fire alarm control equipment. A monitored system is a system which transmits trouble alarms to a supervisory station.
2-2.1.2. Event-Driven Tests. Some tests should be event-driven. For example, a main drain test is intended to verify the open condition of a control valve to a sprinkler or water spray system, and needs to be done only when the control valve has been operated for maintenance or testing. The frequency indicated in the tables is after valve operation.
2-2.1.3. Excluded National Fire Code Tasks. Some of the tasks the National Fire Codes recommend are not included in the tables. These are tasks which do not improve the operability of the systems because: (1) the faults they detect are not significant; (2) the faults are detected by other tasks or means; or (3) the faults will be self-evident (fix it when it breaks) and do no significantly impair the system.
2-2.1.4. Non-ITM Activities. Inspection activities listed at the end of each ITM table are not part of the ITM program, but part of building overall inspection, and are listed for information only. They were not included in the model used to develop the 99 percent reliability requirements; however, they should be incorporated into each DoD component activity's fire prevention, safety, facility condition, and related inspection/evaluation program.
2-2.2 Fire Detection and Alarm Systems. The type and frequency of ITM tasks for fire detection and alarm systems depend on whether the system is monitored or not. Guidance on the tasks in Table 2-1 is contained in the Inspection, Testing, and Maintenance section of National Fire Protection Association Standard 72 (NFPA 72). Residential smoke detectors are addressed in Chapter 3.
Table 2-1. Fire Detection and Alarm System ITM Tasks
Frequency Component Tasks Annual
1. Control Panel and Annunciator Equipment (monitored)
1. Test to verify proper receipt of alarm supervisory and trouble signals (inputs) and operation of notification appliances and auxiliary functions (outputs). 2. Verify all lamps and LEDs are illuminated. 3. Load test backup batteries (when provided).
2. Initiating Devices: a. Fire Alarm Boxes
1. Verify box is accessible (visual).
b. Radiant Energy Detectors
1. Test to verify alarm initiation and receipt. 2. Verify no facility change which affects performance.
c. Gas Detectors
1. Test to verify alarm initiation and receipt. 2. Verify no facility change which affects performance.
UFC 3-600-02 1 January 2001 Table 2-1. Fire Detection and Alarm System ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
3. Notification Appliances and Voice Communication (telephone, speakers, horns, and strobe lights)
1. Test to verify operability.
4. Digital Alarm Transmitters and Receivers
1. Test to verify operability.
5. Initiating Devices:
a. Fire Alarm Boxes
1. Operate to verify alarm receipt.
b. Heat Detectors
1. Test with heat source to verify
(restorable) alarm initiating and receipt.
2. Verify no facility change which affects performance.
c. Smoke Detectors
1. Test with smoke or aerosol to verify smoke entry and alarm initiation and receipt. 2. Verify no facility change which affects performance.
d. Supervisory Devices (low air, temperature, water level)
1. Test to verify initiation and receipt of supervisory alarm.
5 Years
1. Smoke Detectors
1. Test detector sensitivity to ensure the detector has remained within its listed and marked sensitivity range (or 4 percent obscuration light gray smoke, if not marked).
As Part of Entire System
1. Visually check:
Building
a. Detectors unblocked/uncovered.
Inspection
b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed. 2. Exercise evacuation notification appliances for audibility, clarity, and visibility.
2-2.3 Wet Pipe Automatic Sprinkler Systems. Technical guidance on the tasks in Table 2-2 is contained in NFPA 25. Residential sprinklers are addressed in Chapter 3.
Table 2-2. Wet Pipe Sprinkler Systems ITM Tasks
Frequency Component Tasks Annual
1. Control Valves (locked or supervised)
1. Verify valve position.
2. Waterflow Alarm Devices
1. Operate to verify initiation and receipt of alarm. 2. Verify alarm test valve alignment and tamper switch (if supervised).
3. Alarm Valve and Trim
1. Visually check exterior of valves, gauges, trim alignment. 2. Verify valve pressure and legibility of hydraulic nameplate.
4. Main Drain
1. Conduct main drain test to verify supply (valve position)
5. Fire Department Connection
1. Verify accessibility and condition. 2. If caps removed or missing, check for obstructions.
6. Control Valves
1. Operate valve through entire travel to verify function. 2. Lubricate valves and stems to ensure operability.
2 Years
1. Alarm Valve
1. Clean and inspect internally to verify condition.
2. Strainers, Check Valves
1. Internal inspection and cleaning to verify condition.
5 Years
1. Gauges
1. Replace gauges.
20 Years
1. Fast Response Sprinklers and Extra High Temperature Heads
1. Test sample heads to verify response characteristics.
50 Years
1. Standard Sprinkler Heads
1. Replace or test sample heads to verify response characteristics.
As Part of Building Inspection Entire System Visually check: 1. Pipe hangers. 2. Heads for obstruction. 3. Piping for leaks. 4. Riser condition. 5. Sprinkler spares. 6. Area susceptible to freezing.
2-2.4 Dry Pipe Automatic Sprinkler Systems. Technical guidance for these tasks is contained in NFPA 25.
Table 2-3. Dry Pipe Automatic Sprinkler Systems ITM Tasks
Frequency Component Tasks Annual
1. Control Valves (locked or supervised)
1. Verify valve position.
2. Waterflow Alarm Devices
1. Operate to verify initiation and receipt of alarm. 2. Verify alarm test valve alignment and tamper switch (if supervised).
3. Dry Pipe Alarm Valve and Trim
1. Visually inspect exterior of valves, gauges, trim alignment. 2. Verify valve pressure and legibility of hydraulic nameplate.
4. Main Drain
1. Conduct main drain test to verify supply (valve position).
5. Fire Department Connection
1. Verify accessibility and condition. 2. If caps removed or missing, check for obstructions.
6. Dry Pipe Alarm Valve Enclosure Heating
1. Verify operability at beginning of heating season (for constant cold areas annually).
7. Low Temperature Alarm
1. Verify initiation and receipt of alarm at beginning of heating season.
8. Low Point Drains
1. Drain all low points to remove condensation prior to cold season.
9. Control Valves
1. Operate valve through entire travel to verify function. 2. Lubricate valve stem.
10. Dry Pipe Alarm Valves
1. Trip valve to verify operability. 2. Inspect internal condition before resetting and clean valve seat. 3. Check priming water level (before and after trip test).
Table 2-3. Dry Pipe Automatic Sprinkler Systems ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
11. Quick Opening Devices
1. Test to verify operability.
12. Low Air Pressure Alarm
1. Test to verify initiation and receipt of supervisory alarm.
13. Automatic Air Pressure Maintenance Devices
1. Inspect to verify proper operation.
5 Years
1. Strainers, Check Valves
1. Internal inspection and cleaning to verify condition.
2. Gauges
1. Replace gauges.
20 Years
1. Fast Response Sprinklers and Extra High Temperature Heads
1. Test sample heads to verify response characteristics.
50 Years
1. Standard Sprinkler Heads
1. Replace or test sample heads to verify response characteristics.
As Part of Building Inspection Entire System Visually check: 1. Pipe hangers. 2. Heads for obstruction. 3. All piping for leaks. 4. Riser condition. 5. Sprinkler spares.
2-2.5 Deluge Sprinkler Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 25.
Table 2-4. Deluge Sprinkler Systems ITM Tasks
Frequency Component Tasks Annual
1. Control Valves (locked or supervised)
1. Verify valve position.
2. Waterflow Alarm Devices
1. Operate to verify initiation and receipt of alarm. 2. Verify alarm test valve alignment and tamper switch (if supervised).
Table 2-4. Deluge Sprinkler Systems ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
3. Deluge Alarm Valve and Trim
1. Inspect exterior of valves, gauges, trim alignment. 2. Verify pressure and legibility of hydraulic nameplate.
4. Main Drain
1. Conduct main drain test to verify supply (valve position).
5. Fire Department Connection
1. Verify accessibility and condition. 2. If caps removed or missing, check for obstructions.
6. Valve and Riser Heated Enclosure (if provided)
1. Verify operability at beginning of heating season.
7. Low Temperature Alarm
1. Verify initiation and receipt of alarm at beginning of heating season.
8. Control Valves
1. Operate valve to verify operability. 2. Lubricate valve stem.
9. Deluge Valve
1. Trip to verify operability. 2. Verify manual actuators are operable. 3. Inspect internal condition and clean valve seat before resetting.
10. Low Point Drains
1. Drain all low points after deluge valve test and before cold weather.
5 Years
1. Strainers, Check Valves
1. Inspect internally and clean to verify condition.
2. Gauges
1. Replace.
3. Deluge Valve
1. Conduct full flow test. Flow will be observed for no less than one minute.
As Part of Building Inspection
1. Visually check: a. Pipe hangers. b. Heads for obstruction. c. All piping for leaks. d. Riser condition. e. Sprinkler spares. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed.
2-2.6. Pre-Action Automatic Sprinkler Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 25.
Table 2-5. Pre-Action Automatic Sprinkler Systems ITM Tasks
Frequency Component Tasks Annual
1. Control Valves (locked or supervised)
1. Verify valve position.
2. Waterflow Alarm Devices
1. Operate to verify initiation and receipt of alarm. 2. Verify alarm test valve alignment and tamper switch (if supervised).
3. Pre-Action Valve and Trim
1. Inspect exterior of valves, gauges, trim alignment. 2. Verify valve pressure and legibility of hydraulic nameplate.
4. Main Drain
1. Conduct main drain test to verify supply (valve position).
5. Fire Department Connection
1. Verify accessibility and condition. 2. If caps removed or missing, check for obstructions.
6. Valve and Riser Heated Enclosure (if provided)
1. Verify operability at beginning of heating season.
7. Low Temperature Alarm
1. Verify initiation and receipt of alarm at beginning of heating season.
8. Control Valves
1. Operate valve through entire travel to verify function. 2. Lubricate valve stem.
9. Pre-Action Valve
1. Trip to verify proper operation. 2. Verify manual actuators (if provided). 3. Inspect internal condition and clean valve seat before resetting.
Table 2-5. Pre-Action Automatic Sprinkler Systems ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
10. Low Point Drains
1. Drain all low points after pre-action valve trip test and before cold weather (if unheated area).
11. Air supply (if present)
1. Test automatic air pressure maintenance device. 2. Test Hi/Low air supply alarm.
5 Years
1. Strainers, Check Valves
1. Clean and inspect interior to verify condition.
2. Gauges
1. Replace gauges.
20 Years
1. Fast Response Sprinklers and Extra High Temperature Heads
1. Test sample heads to verify response characteristics.
50 Years
1. Closed Head Nozzles
1. Replace or test sample closed head nozzles to verify response characteristics.
As Part of Building Inspection
1. Visually Inspect System: a. Pipe hangers. b. Heads for obstruction. c. All piping for leaks. d. Riser condition. 2. Ensure: a. Manual stations in-place and unobstructed. b. Check sprinkler spares. c. Detectors unblocked/uncovered. d. Panels secured and indicator lamps functional. e. Notification appliances in place. f. Manual stations in place and unobstructed.
2-2.7 Water Spray Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on these tasks is contained in NFPA 25.
Table 2-6. Water Spray Systems ITM Tasks
Frequency Component Tasks Annual
1. Control Valves (locked or supervised)
1. Verify valve position.
2. Waterflow Alarm Devices
1. Operate to verify initiation and receipt of alarm. 2. Verify alarm test valve alignment and tamper switch (if supervised).
3. Pre-Action Valve and Trim
1. Inspect exterior of valves, gauges, trim alignment. 2. Verify valve pressure and legibility of hydraulic nameplate.
4. Main Drain
1. Conduct main drain test to verify supply (valve position).
5. Fire Department Connection
1. Verify accessibility and condition. 2. If caps removed or missing, check for obstructions.
6. Valve and Riser Enclosure Heater
1. Verify operability at beginning of heating season.
7. Low Temperature Alarm
1. Verify initiation and receipt of alarm at beginning of heating season.
8. Control Valves
1. Operate valve to verify operability. 2. Lubricate valve stem.
9. Water Spray Valve
1. Trip to verify operability. 2. Verify manual actuators (if provided). 3. Verify spray pattern (if experience shows nozzles are not moved, this can be extended to 10 years or after modifications). 4. Inspect interior of valve and clean valve seat before resetting.
Table 2-6. Water Spray Systems ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
10. Low Point Drains
1. Drain all low points after pre-action valve trip test and before cold weather.
5 Years
1. Strainers, Check Valves
1. Clean and inspect interior to verify condition.
2. Gauges
1. Replace.
20 Years
1. Fast Response Sprinklers and Extra High Temperature Heads
1. Test sample heads to verify response characteristics.
50 Years
1. Standard Sprinkler Heads
1. Replace or test sample heads to verify response characteristics.
As Part of Building Inspection
1. Visually check: a. Pipe hangers. b. Heads for obstruction. c. All piping for leaks. d. Riser condition. e. Sprinkler spares 2. Ensure: a Manual stations in-place and unobstructed. b. Detectors unblocked/uncovered. c. Panels secured and indicator lamps functional. d. Notification appliances in place. e. Manual stations in place and unobstructed.
UFC 3-600-02 1 January 2001 2-2.8 Water Mist Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 750.
Table 2-7. Water Mist Systems ITM Tasks
Frequency Component Task
Semi-Annual
1. Pumps
1. Churn test to ensure operability.
2. Air Compressors
1. Start to ensure operability.
3. System Operating Components
1. Inspect to verify valve alignment and valve is free of damage.
Annual
1. Water Tanks (supervised and monitored)
1. Check water level and supervisory switch.
2. Air Compressors/ Receivers/Cylinders (supervised and monitored)
1. Check air pressure and supervisory pressure switch.
3. Water Flow Alarm
1. Operate to verify initiation and receipt of alarm.
4. Pumps
1. Conduct full flow functional test.
5. Pressure Relief Devices
1. Manually operate to ensure operability.
6. Manual Actuators
1. Verify operability.
7. Control Valve (sectional water supply valve)
1. Verify operability and position.
5 Years
1. Pressure cylinders (normally at atmospheric pressure)
1. Pressurize to verify operability.
2. System
1. Conduct flow test.
3. Water
1. Verify water quality when refilling.
4. Water Tanks
1. Inspect tanks for structural integrity prior to refilling.
5. Nozzle Sampling
1. Test sample heads to verify response characteristics.
Table 2-7. Water Mist Systems ITM Tasks (Continued)
Frequency Component Task 5 Years
1. Storage Vessels
1. Conduct hydrostatic test for pressure cylinders in accordance with US Occupational Safety and Health Administration (OSHA) and US Department of Transportations (DOT) standards.
As Part of Entire System
1. Visually check:
Building
a. Check pipe hangers.
b. Check heads for obstruction. c. Check all piping for leaks. d. Check riser condition. e. Check nozzle spares. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed.
2-2.9 Foam and Foam-Water Systems. Table 2-8 addresses low expansion foam systems for flammable liquid tanks as covered in NFPA 11. Table 2-9 addresses low expansion foam spray and sprinkler systems including aqueous film forming foam (AFFF), as covered in NFPA 16, 16A, and 25. Table 2-10 addresses high expansion foams as covered in NFPA 11A.
Table 2-8. Low Expansion Foam Systems for Flammable Liquid Tanks ITM Tasks
Frequency Component Tasks Annual
1. Foam Concentrate
1. Inspect for quality and evidence of sludge or deterioration.
2. Foam Pumps/Proportioners
1. Test to verify operability and proper proportioning. 2. Flush pumps after operation.
3. System Actuators
1. Verify all manual and automatic actuation functions.
4. Foam Concentrate Strainers
1. Inspect and clean if necessary.
5. Distribution/Discharge
1. Ensure discharge devices are free of damage. 2. Inspect pipe and hanger to verify support and pitch.
Table 2-8. Low Expansion Foam Systems for Flammable Liquid Tanks ITM
2-13 UFC 3-600-02 1 January 2001 Tasks (Continued)
Frequency Component Tasks 3 Years
1. Distribution Piping (including underground)
1. Spot-check piping interior for evidence of deterioration.
2. Strainers, Check Valves
1. Inspect and clean if necessary.
Table 2-9. Foam Spray and Sprinkler Systems ITM Tasks
Frequency Component Tasks
Annual
1. Foam Concentrate
1. Verify adequate supply and foam quality.
2. Foam Proportioning System
1. Test pump to ensure operability. 2. Inspect proportioning system for proper valve alignment and system condition.
3. Control Valves (supervised and monitored)
1. Verify valve in proper position.
4. Foam Concentrate Strainers
1. Inspect exterior to ensure blow down valve is closed.
2 Years
1. Control Valve
1. Operate valve through entire travel to verify function. 2. Lubricate stem.
2. Foam Proportioning System
1. Conduct full flow test to ensure proper system function. Flow will be observed for no less than one minute. 2. Verify proper concentration. 3. Refill with approved foam concentrate after testing is complete.
3. Actuators
1. Verify operability of manual and automatic actuators.
4. Distribution System
1. Verify nozzle (head) coverage during flow test. 2. Inspect piping hangers, heads, and nozzles for condition and location.
5. Foam Concentrate Strainers
1. Inspect and clean after flow test.
Table 2-9. Foam Spray and Sprinkler Systems ITM Tasks (Continued)
Frequency Component Tasks 2 Years (continued)
6. Balancing Valve
1. Flush to prevent concentrate buildup on diaphragm.
7. Strainers, Check Valves
1. Inspect and clean internally.
5 Years
1. Foam Concentrate Tank
1. Drain, flush and perform internal inspection for corrosion. If pressure vessel, perform hydrostatic test. Refill with approved foam concentrate.
As Part of Building Inspection Entire System
1. Visually check: a. Pipe hangers. b. Heads for obstruction. c. All piping for leaks. d. Riser condition. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed. 3. Check sprinkler spares.
Table 2-10. High Expansion Foam Systems ITM Tasks
Frequency Component Tasks Annual
1. Foam Concentrate
1. Inspect to verify adequate supply.
2. Foam Generator
1. Inspect to verify condition and proper valve alignment.
2 Years
1. Foam Generator
1. Conduct discharge test to verify operability. Flow will be observed for no less than one minute.
2. Actuators
1. Verify all manual and automatic actuators function.
After Activation
1. Strainers, Check Valves
1. Inspect and clean after system actuation. 2. Refill with approved foam concentrate.
Table 2-10. High Expansion Foam Systems ITM Tasks (Continued)
Frequency Component Tasks As Part of Building Inspection
1. Visually Check: a. Pipe hangers. b. Heads for obstruction. c. All piping for leaks. d. Riser condition. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed.
2-2.10 Standpipe Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 14 and 25.
Table 2-11. Standpipe Systems ITM Tasks
Frequency Component Tasks Annual
1. Hose Connection and Pressure Reducing Valves
1. Inspect for damage, leaking, missing caps, and obstruction.
2. Piping
1. Inspect for damage and pipe supports.
2 Years
1. Standpipe
1. Conduct flow test to verify flow capacity at farthest point of system. 2. Hydrostatic test to ensure integrity, 200 psi for minimum of 2 hours.
As Part of Building Inspection
1. Visually check: a. Pipe hangers. b. Connections for obstruction. c. All piping for leaks. d. Riser condition.
2-2.11 Hydrants and Monitors. Technical guidance on the tasks in Table 2-12 is contained in NFPA 25.
Table 2-12. Hydrants and Monitors ITM Tasks
Frequency Component Task 2 Years
1. Hydrants
1. Inspect for accessibility, leaks, and worn threads. 2. Operate to ensure proper functioning. 3. Verify drainage of barrel (after all operations and before cold weather). 4. Lubricate hydrant to ensure ease of operation.
2. Yard Monitor Nozzles
1. Inspect for condition. 2. Conduct flow test to verify proper function and range of motion. 3. Lubricate to ensure proper operating conditions.
3. Hose Houses
1. Inspect for accessibility and physical condition. 2. Verify inventory and its condition.
3 Years
1. Underground and Exposed Piping.
1. Conduct flow tests.
After Flow
1. Strainers
1. Inspect and clean after each flow.
2-2.12 Fire Pumps. Technical guidance on these tasks is contained in NFPA 20 and NFPA 25.
Table 2-13. Fire Pumps ITM Tasks
Frequency Component Tasks Annual
1. Pump House
1. Inspect for proper condition, ventilation and heating.
2. Control Valve and Isolation Valve
1. Verify proper valve position.
3. Pressure Gauges
1. Check reading and verify gauge operability.
Table 2-13. Fire Pumps ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
4. Controllers
1. Inspect electric connections. 2. Operate manual and automatic stations.
5. Batteries
1. Verify proper charge.
6. Pumps
1. Start and churn to verify operability. (Where equipment permits, allow water to flow back to the source.) 2. Verify operation of relief valves. 3. Verify full level (for engine-driven pumps). 4. Inspect exhaust system for leaks (for engine-driven pumps). 5. For engine driven pumps, start again using second battery set and churn to verify operability. (Where equipment permits, allow water to flow back to the source.)
7. Control Valve
1. Operate and lubricate valves to ensure operability.
8. Controllers
1. Calibrate pressure switches. 2. Exercise circuit breakers and switches to verify operability. 3. Inspect fuses.
9. Pumps
1. Check coupling alignment to ensure shaft aligned. 2. Check pump shaft end play. 3. Lubricate bearings. 4. Lubricate couplings. 5. Lubricate right-angle drives.
10. Fuel (Engine-Driven Pumps)
1. Sample fuel to verify quality.
11. Relief Valves
1. Calibrate valves.
12. Emergency Power Supply
1. Test to verify availability and capacity for pump motor.
2 Years
1. Pump
1. Conduct flow test to verify pump output.
2-2.13 Water Supply Tanks. Technical guidance on these tasks is contained in NFPA 25.
Table 2-14. Water Supply Tanks ITM Tasks
Frequency Component Tasks Annual
1. Control Valves
1. Verify proper valve position.
2. Water Level
1. Verify proper water level in tank.
3. Tank Heating System
1. Verify operability of tank heater (prior to cold weather). 2. Test temperature alarms to verify proper operation (maintain thermometer in accordance with manufacturer’s recommendations).
4. Tank
1. Inspect exterior for condition, damage, corrosion, and accessibility. 2. Verify air pressure (for pressure tanks).
5. Cathodic Protection
1. Inspect to ensure proper operation.
6. Control Valves (including drain valves)
1. Operate valve through entire travel to verify function. 2. Lubricate valves to ensure operability.
7. Water Level Alarms and Level Indicators
1. Test water level alarms to verify operability and set points.
3. Tank Vent
1. Inspect and clean tank vents.
5 Years
1. Tank (without cathodic protection)
1. Conduct internal tank inspection to determine condition and amount of corrosion.
Table 2-14. Water Supply Tanks ITM Tasks (Continued)
Frequency Component Tasks 5 Years
1. Tanks (with cathodic protection)
1. Conduct internal tank inspection to determine condition and amount of corrosion.
2. Pressure Gauges
1. Replace gauges.
3. Check Valves
1. Inspect interior of valves.
4. Level Indicator Test
1. Calibrate level indicator.
2-2.14 Dry Chemical Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on these tasks is contained in NFPA 17.
Table 2-15. Dry Chemical Systems ITM Tasks
Frequency Component Tasks Semi-Annual
1. Piping
1. Inspect piping for obstructions and proper support.
2. flow inert gas through piping to check for obstructions.
2. Storage Vessels
1. Inspect agent container for condition. 2. Verify storage pressure of propellant.
3. Agent
1. Verify quantity and quality of agent.
4. Actuators
1. Inspect manual actuators for accessibility. 2. Inspect detection devices (fusible links or heat detectors) for contamination, and clean. 3. Test actuation system without agent release. 4. Verify interfaces (gas shutoff, power shutoff) operate properly.
5. Actuators
1. Replace detection devices (fusible links or heat detectors) 5 Years
1. Storage Vessels
1. Conduct hydrostatic test for pressure cylinders in accordance with OSHA and DOT standards.
Table 2-15. Dry Chemical Systems ITM Tasks (Continued)
Frequency Component Tasks As Part of Building Inspection
1. Visually check: a. Pipe hangers. b. Heads for obstruction. c. Riser condition. 2. Ensure: a. Detectors unblocked/ uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed. e. Nozzle covers in place.
2-2.15 Wet Chemical Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 17A.
Table 2-16. Wet Chemical Systems ITM Tasks
Frequency Component Tasks Semi-Annual
1. Piping
1. Inspect piping for obstructions and proper support.
2. flow inert gas through piping to check for obstructions.
2. Storage Vessels
1. Inspect agent container for condition. 2. Verify storage pressure of propellant.
3. Agent
1. Verify quantity and quality of agent.
4. Actuators
1. Inspect manual actuators for accessibility. 2. Inspect detection devices (fusible links or heat detectors) for contamination, and clean or replace as necessary. 3. Test actuation system without agent release. 4. Verify interfaces (gas shutoff, power shutoff) operate properly.
Table 2-16. Wet Chemical Systems ITM Tasks (Continued)
Frequency Component Tasks Semi-Annual (continued)
5. Actuators
1. Replace detection devices (fusible links or heat detectors) 5 Years
1. Storage Vessels
1. Conduct hydrostatic test for pressure cylinders in accordance with OSHA and DOT standards.
As Part of Entire System
1. Visually Check:
Building
a. Pipe hangers.
Inspection
b. Heads for obstruction. c. Riser condition. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed. e. Nozzles' covers in place.
2-2.16 Halon Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 12A.
Table 2-17. Halon Systems ITM Tasks
Frequency Component Tasks Annual
1. Piping
1. Inspect piping and nozzles for condition and orientation.
2. Flow inert gas through piping to check for obstructions.
2. Flexible Hoses
1. Inspect for damage.
3. Storage Vessels
1. Inspect storage containers’ exterior (tanks, spheres, cylinders).
4. Agent and Propellant
1. Verify quantity of agent is sufficient. 2. Verify pressure of agent/ propellant is sufficient.
5. Actuators
1. Inspect manual actuators for accessibility. 2. Test actuation without agent release.
Table 2-17. Halon Systems ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
6. Auxiliary Equipment
1. Test to verify interfaces (equipment shutdown, dampers, and door closures) operate properly and are activated by the system actuation.
7. Valves
1. Verify valves in proper alignment.
5 Years
1. Cylinders
1. Complete external inspection of non-discharged cylinders to ensure suitability for use.
2. Flexible Hoses
1. Pressure test hoses to ensure suitability for use.
2 Years (and after modifications to compartment)
1. Protected Enclosure (Room)
1. Inspect the enclosure to verify integrity and ability to maintain agent concentration.
As Part of Building Inspection
1. Visually Check: a. Pipe hangers. b. Heads for obstruction. c. Piping for leaks. d. Riser condition. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed. e. Nozzles' covers in place.
2-2.17 Clean Agent Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 2001.
Table 2-18. Clean Agent Systems ITM Tasks
Frequency Component Tasks Annual
1. Piping
1. Inspect piping and nozzles for condition and orientation.
2. Flow inert gas through piping to check for obstructions.
2. Flexible Hoses
1. Inspect for damage.
3. Storage Vessels
1. Inspect storage containers’ exterior (tanks, spheres, cylinders).
4. Agent and Propellant
1. Verify adequate quantity of agent. 2. Verify adequate pressure of agent/propellant.
5. Actuators
1. Inspect manual actuators for accessibility. 2. Test actuation without agent release.
6. Auxiliary Equipment
1. Test to verify interfaces (equipment shutdown, dampers, and door closures) operate properly and are activated by the system actuation.
7. Valves
1. Verify valves in proper alignment.
8. Protected Enclosure (Room)
1. Inspect the enclosure to verify integrity and ability to maintain agent concentration.
3 Years
1. Cylinders
1. Perform complete external inspection of non-discharged cylinders to ensure suitability for use.
2. Flexible Hoses
1. Pressure-test hoses to ensure suitability for use.
Table 2-18. Clean Agent Systems ITM Tasks (Continued)
Frequency Component Tasks As Part of Entire System
1. Visually Check:
Building
a. Pipe hangers.
b. Heads for obstruction. c. Piping for leaks. d. Riser condition. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. C. Notification appliances in place. d. Manual stations in place and unobstructed. e. Nozzles' covers in place.
2-2.18 Carbon Dioxide Systems. Detection devices for actuation are addressed in paragraph 2-2.2. Technical guidance on the tasks is contained in NFPA 12.
Table 2-19. Carbon Dioxide Systems ITM Tasks
Frequency Component Tasks Semi-Annual
1. Liquid Level (low pressure CO2)
1. Verify adequate liquid level with tank level gauge.
Annual
1. Piping and Nozzles
1. Inspect piping for condition and proper support. 2. Check nozzles for obstruction and alignment.
2. Flexible Hoses
1. Inspect for damage.
3. Low Pressure Tanks
1. Check level and pressure gauges. 2. Verify valve alignment.
4. High Pressure Cylinders
1. Inspect for condition and securing.
5. Actuation System
1. Exercise control panel function including zone valve operation. 2. Inspect manual actuators for accessibility. 3. Check times and time delay (pre-discharge).
Table 2-19. Carbon Dioxide Systems ITM Tasks (Continued)
Frequency Component Tasks Annual (Continued)
6. Auxiliary Equipment
1. Test to verify interfaces (shutdown, door closers, and dampers) operate properly and are activated by the control panel.
2 Years
1. High Pressure Cylinders
1. Verify CO2 quantity by weighing cylinders.
As Part of Entire System
1. Visually Check:
Building
a. Check pipe hangers.
b. Check heads for obstruction. c. Check piping for leaks. d. Check riser condition. 2. Ensure: a. Detectors unblocked/uncovered. b. Panels secured and indicator lamps functional. c. Notification appliances in place. d. Manual stations in place and unobstructed. e. Nozzles' covers in place.
CHAPTER 3
MILITARY FAMILY HOUSING SYSTEMS
3-1 SCOPE. The maintenance concepts for military family housing (MFH) fire protection systems are based on the management and controls unique to the MFH program. In the civilian sector, an owner/tenant makes a personal choice to occupy a dwelling unit and is responsible for their maintenance/repair and any associated fire protection devices. In MFH, occupants are assigned housing units and the housing management activity is responsible for the maintenance/repair of units and associated fire protection devices. Each MFH occupant is required to attend a briefing on their responsibilities as a MFH occupant prior to occupying a new MFH dwelling. These briefings include the occupant's responsibilities for conducting tests and cleaning installed fire protection features. On average, MFH maintenance teams conduct “change of occupancy” maintenance every one to two years; therefore, scheduled maintenance performed by the housing management activity is centered on this change of occupancy.
3-1.1 Residential Smoke Detectors. MFH units are required to have hard-wired smoke detectors. Each installation develops programs to train occupants in the testing and maintenance actions for the smoke detector installed. Actions required as part of change of occupant maintenance by the housing management activity are listed in Table 3 1.
3-1.2 Residential Sprinkler Systems. Some MFH units are also provided sprinkler systems.
3-1.2.1 Residential sprinkler systems in multi-family buildings up to 4 stories are normally constructed in accordance with NFPA 13R, Sprinkler Systems, Residential Occupancies Up To and Including 4 Stories. These systems are maintained in accordance with the tables in Chapter 2 of this UFC. Building occupants are not expected to conduct system tests or maintenance actions.
3-1.2.2 Residential sprinkler systems in multi-family buildings over 4 stories are normally constructed in accordance with NFPA 13, Sprinkler Systems. These systems are maintained in accordance with the tables in Chapter 2 of this UFC. Building occupants are not expected to conduct system tests or maintenance actions.
3-1.2.3 Residential sprinkler systems in one- and two-family dwellings and townhouse-style units are normally constructed in accordance with NFPA 13D, Sprinkler Systems, Dwellings. Installations develop their own programs to train occupants in the testing and maintenance actions required. Actions required as part of change of occupant maintenance by the housing management activity are listed in Table 3-2.
3-2 ITM TASK DESCRIPTIONS. The ITM tasks in Tables 3-1 and 3-2 should be part of the housing maintenance conducted between occupancies.
UFC 3-600-02 1 January 2001 Table 3-1. MFH Residential Smoke Detectors ITM Tasks
Frequency Component Tasks Change of Occupancy
1. Smoke Detector
1. Activate each detector with an approved smoke simulant. 2. Remove cover and inspect for grease build-up; replace and relocate detector with evidence of grease build-up in the detector. 3. Vacuum the detector and replace the cover. 4. Activate each detector with the installed test button. 5. Replace any detector failing to activate on either the smoke simulant or the test button.
2. Backup Battery (if present)
1. Replace battery (if present).
10 Years
1. Smoke Detectors
1. Replace detectors with supplemental/backup batteries or test detector sensitivity to ensure the detector has remained within its listed and marked sensitivity range (or 4 percent obscuration light gray smoke, if not marked).
25 Years
1. Smoke Detectors (hardwired without battery backup)
1. Replace detectors.
Table 3-2. MFH Residential Sprinkler Systems ITM Tasks
Frequency Component Tasks Change of Occupancy
1. Sprinkler Heads
1. Inspect all heads. 2. Clean or replace heads (as necessary). 3. Inspect ceilings/wall at head for signs of leakage or water stains.
2. Valves
1. Inspect all valves to ensure they are open and sealed.
3. Waterflow and Alarm Devices
1. Test to verify operability.
20 Years
1. Fast Response Sprinkler Heads
1. Test a sample of heads or replace.
APPENDIX A REFERENCES
Government Publications Department of Defense Military Handbook 1008 Fire Protection Engineering for Facilities, Engineering, Design, and Construction HQ AFCESA Technical Report (available at http://www.afcesa.af.mil) Risk Based Reliability Centered Maintenance of DoD Fire Protection Systems, January 1999
Non-Government Publications National Fire Protection Association 1 Batterymarch Park P.O. Box 9101 Quincy, MA 02269-9101
1. NFPA 11 Standard for Low-Expansion Foam, 1998 Edition
2. NFPA 11A Standard for Medium- and High-Expansion Foam Systems
3. NFPA 12 Standard on Carbon Dioxide Extinguishing Systems
4. NFPA 12A Standard on Halon 1301 Fire Extinguishing Systems
5. NFPA 13 Standard for the Installation of Sprinkler Systems
6. NFPA 13 D Standard for the Installation of Sprinkler Systems in One and Two Family Dwellings
7. NFPA 13 R Standard for the Installation of Sprinkler Systems in Residential Occupancies up to 4 Stories
8. NFPA 14 Standard for the Installation of Standpipe and Hose Systems
9. NFPA 15 Standard for Water Spray Fixed Systems for Fire Protection
10. NFPA 16 Standard for the Installation of Deluge Foam-Water Sprinkler and Foam-Water Spray Systems
| 11. | NFPA 16A Standard for the Installation of Closed-Head Foam-Water Sprinkler Systems |
| 12. NFPA 17 | Standard for Dry Chemical Extinguishing Systems |
13. NFPA 17A Standard for Wet Chemical Extinguishing Systems
14. NFPA 20 Standard for the Installation of Centrifugal Fire Pumps
15. NFPA 22 Standard for Water Tanks for Private Fire Protection
16. NFPA 25 Standard for the Inspection, Testing and Maintenance of Water Based Fire Protection Systems
17. NFPA 72 National Fire Alarm Code
18. NFPA 750 Standard on Water Mist Fire Protection Systems
19. NFPA 2001 Standard on Clean Agent Fire Extinguishing Systems