Headquarters III Corps, Fort Hood Directorate of Public Works (DPW)
Technical Exhibit “A”
IDIQ Fencing Contract
Contract No.W91151‐23‐D‐XXXX
Specifications
Directorate of Public Works Engineering
Division US Army, III Corps 4612 Engineer Dr.
Fort Hood, TX 76544
22 August 2022
SPECIFICATIONS TABLE OF CONTENTS
DIVISION SECTION TITLE
A
GENERAL REQUIREMENTS
Scope of Work Summary of Work
B Project Schedule C Submittal Procedures D Special Project Procedures for Fort Hood E Owner Safety Requirements F Safety and Occupational Health Requirements G Quality Control (QC) H Environmental Protection I Closeout Procedures J Utilities K Excavation and Utility Clearance Coordination
Detailed Specifications for Select Line Items
LINE ITEM TITLE
0 Bond 1 Record Drawings 2 Grading 3 Clearing & Grubbing - Light <6" diameter 4 Clearing & Grubbing - Medium >6" diameter 5 Removal of Fencing - Chain Link Posts & Fabric 6 Removal of Fencing - Chain Link Fabric and Fabric
Accessories
7 Removal of Fencing - Individual Posts Set in Concrete 8 Removal of Fencing - Chain Link Bracing 9 Removal of Fencing - Chain Link Barbed Wire 10 Removal of Fencing - Stainless Steel 18” Helical Razor Wire 11 Removal of Fencing - Individual Barbed Wire Extension Arm 12 Removal of Fencing - Chain Link Tension Wire 13 Removal of Fencing - Chain Link Fence Rail 14 Removal of Fencing - Chain Link Gates - Swing 15 Removal of Fencing - Chain Link Gates - Sliding & Cantilever 16 Removal of Fencing - Privacy Slats 17 Removal of Fencing - Barbed Wire Fence 18 Removal of Fencing - Wooden Fence Sections 19 Removal of Fencing - Wooden Fence Posts Set in Concrete 20 Install Post - 2 3/8" Diameter Line Post 21 Install Post - 2 3/8" Diameter Line Post Per Ft Over 8' 22 Install Post - 2 7/8" Diameter Terminal Post 23 Install Post - 2 7/8" Diameter Terminal Post Per Ft Over 8' 24 Install Post - 4" Diameter Gate Post 25 Install Post - 6 5/8" Diameter Gate Post 26 Install Post - 8 5/8" Diameter Gate Post 27 Install Post - 6' T-posts 28 Install Post - Single 'H' w/ Braces 29 Install Post - Double 'H' w/ Braces 30 Install Post - Single 2 3/8' Line Post w/ Braces 31 Install Post - Setting Post Through Asphalt or Concrete 32 Install Fence Material - Chain Link Fabric Up To 6' 33 Install Fence Material - Chain Link Fabric 7'
Install Fence Material - Chain Link Fabric 8' Install Fence Material - Chain Link Bracing Assembly Install Fence Material - Galvanized Brackets Install Fence Material - Truss Rod Assembly Install Fence Material - Tension Bars Install Fence Material - Drop Rod Assembly Install Fence Material - Standard Hinge Install Fence Material - Offset Hinge Install Fence Material - Galvanized Gate Keeper Install Fence Material - Tension Wire Install Fence Material - Top Rail or Bottom Install Fence Material - Barbed Wire for Chain Link Install Fence Material - Single Barbed Wire Support Arm Install Fence Material - Stainless Steel 18 " Helical Razor Wire Install Fence Material - Double "V" Barbed Wire Support Arm Install Fence Material - Barbed Wire for 5 Strand Barbed Wire Fence Install Fence Material - Up To 8' High Wooden Privacy Fence Install Fence Material - Wood Fence Sections Up To 8' Install Post Caps - (Post < 3 inch) Install Post Caps - (Post > 3 inch) Gates - Install Up to 8' High Chain Link Swing Gate Gates - Install Up To 8' High Chain Link Sliding Gate Gates - Install Cable Barrier Gates – Install Concrete Dead Man Anchor Gates - Replacement of Gate Accessories Gates - Install 4' High Pipe Gate for Barbed Wire Fence Gates - Install Barbed Wire Water Gap Gates - Install Chain Link Water Gap Retention and Retie - Chain Link Fabric and Tension Wire Retention and Retie - Barbed Retention and Retie - Straighten / Align post Miscellaneous - Miscellaneous Concrete 3000 psi Miscellaneous - Electrical Ground Rods Miscellaneous - Waterproof - Seal Wooden Fencing Miscellaneous - Geo-textile Material Miscellaneous - Install Bermuda Sod Miscellaneous - Scour Stop Miscellaneous - Flexterra FGM Miscellaneous - Install Fence Stays for Barbed Wire Fence Miscellaneous – Install Winged PVC Privacy Slats up to 8’ Miscellaneous – Install WindScreen Miscellaneous – Herbicide Install Fence Assembly - 7' Chain Link Fence, 2 7/8" Terminal Posts, 2 3/8" Line Posts, Tension Wire Top and Bottom, 3 Strands of Barbed Wire on Top Unpriced Unit Items Schedule of Drawings Bond (2.5% of Total)
-- END --
SECTION 001
RECORD DRAWINGS
1.1 SUMMARY
This Section covers the following line items:
Line Item: 001 Record Drawings
Description - This item shall govern for the preparation and submittal of record drawings.
The unit of measure for recording drawings shall be for “EACH SET OF RECORD DRAWINGS”. Drawings are to include surveyed information with elevations, angles, and distances. Surveying calculations should be stamped by a registered surveyor.
Payment shall be at the contract unit price per each for record drawings.
1.2 RECORD DRAWINGS
Record drawings shall be a record of the construction as installed and completed by the Contractor. They include all the information reflected on the delivery order scope of work and a record of all deviations, modifications, or changes from the scopes of work, however minor, which were incorporated in the work; all additional work not reflected in the scope of work; and all changes which are made after final inspection of the delivery order work. The location and size of all uncharted existing utilities encountered shall be included. Microstation files shall conform to the Microstation requirements of Fort Hood and shall be demonstrated to work on the designated Government computer systems. Microstation files shall be error and virus free.
1.2.1 Submittals of Preliminary Record Drawings
For each delivery order, the Contractor shall, within 30 days after the final acceptance inspection, produce from the working drawings two sets of blue line or black line prints to show all requirements of the scope of work, all changes from the scope of work which are made in the work or additional information which might be uncovered in the course of construction, including uncharted utilities, shall be accurately and neatly recorded as they occur by means of details and notes. All changes and/or required additions to the preliminary record drawings shall be clearly identified in a color contrasting to the blue or black line drawings and which is compatible with reproduction of the preliminary record drawing.
Blue or black line prints shall be full size, 22" by 34" image on 24" by 36" sheets. Drawings shall be produced at a scale acceptable to the Contracting Officer. All blue or black line prints shall exhibit good readable print with clear, sharp, dark lines, and shall not be smeared, faded, double imaged, or have torn or ragged edges. The blue or black line drawings will be jointly inspected for accuracy and completeness by the assigned representative of the Contractor's Quality Control Organization and the Contracting Officer's representative (COR) prior to submission. If upon review, the drawings are found to contain errors and/or omissions, they will be returned to the Contractor for corrections. Failure of the Contractor to make timely delivery of the preliminary record drawings on any or all items of work will be cause for the Government to delay substantial completion and to assess liquidated damages in accordance with the terms and conditions of the contract. The record drawings shall show the following information, but not be limited thereto:
1.2.1.1 The location and description of any utility lines or
other installation of any kind or description known to or found to exist within the construction area. The location of exterior utilities includes actual measured horizontal distances from utilities to permanent facilities/ features. These measurements shall be shown at sufficient points to permit easy location of utilities for future maintenance purposes. Measurements shall be shown for all change of direction points and all surface or underground components such as valves, manholes, drop inlets, cleanouts, meter, etc. The general depth range of each underground utility line shall be indicated. The description of exterior utilities includes the actual quantity, size, and material of utility lines.
1.2.1.2 Correct grade or alignment of roads, structures or
utilities if any changes were made from delivery order working drawings.
1.2.1.3 Correct elevations if changes were made in site grading.
1.2.1.4 Changes in details of design or additional information obtained from working drawings prepared by the Contractor including but not limited to fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.
1.2.1.5 The topography and grades of all drainage installed or affected as a part of the project construction.
1.2.2 Final Record Drawings
Upon approval of the preliminary record drawings, the contractor will modify the original drawings as may be necessary to correctly show all the features of the project as it was constructed by bringing the contract set into agreement with the preliminary record drawings, including adding additional drawings as may be necessary. The original drawings are part of the permanent records of this project and the Contractor shall be responsible for the protection and safety thereof until returned to the Contracting Officer.
1.2.2.1 Verifying the Accuracy of Measurement and Location of Site Location in reference to the Fort Hood Data Base
The accuracy of the final record drawing shall be verifiable.
There are two types of project site locations that are distinguished by their proximity to permanent facilities. One type of a project site location is in a location that is in eye contact with existing permanent facilities. The other type of project site location is in a remote area without eye contact with existing permanent facilities. The following procedures shall be engaged such that accuracy of work and verification of site locations are verifiable.
1.2.2.1.1 Project Site Locations near Existing Permanent
Facilities
Place a #3 bar, 6-inches in length, painted orange, flush with the ground at the perimeter of the work zone in a location that will not be disturbed. Employing an Electronic Distance Meter, reference this point by angel and distance to three building corners that are more than 90 degrees apart. Also, reference from the same reference point a minimum of ten distinct construction elements by distinctive points. A few examples are: north-east corner of headwall, back of curb, start of radius of curb return, center of cleanout, center of manhole, etc.
1.2.2.1.2 Project Site Locations in Remote Area not in
eye contact with Existing Permanent Facilities
In this situation start at the nearest hard surfaced road that is identifiable on the Fort Hood Data Base. Place two #3 bar, 6-inches in length, painted orange flush with the ground, 100 feet apart at a location that will not be disturbed. At each of these points place cross-ties to aide with relocating the points. Employing a Electronic Distance Meter create a coordinate route to the project site location. At each turn in the coordinate route place a #3 bar painted orange flush with the ground at a location that will not be disturbed. Upon reaching the site location record the angle and distance to a minimum of ten distinct construction elements.
1.2.2.2 Drafting
All additions and corrections to the contract drawings shall be neat, clean, and legible and shall match the adjacent existing line work and/or lettering being annotated in type, density, size, and style.
All drawings, modifications and new drawings shall conform to applicable requirements of the Southwestern Division Architectural and Engineering Instruction Manual available from the DPW-Master Planning Office. The Contracting Officer will review all record drawings for accuracy and conformance to the above specified drafting and standards.
The Contractor will make all corrections, changes, additions, and deletions required to meet these standards.
1.2.2.3 Title Blocks and Border Sheets
The title block and border sheet format to be used for any record drawings shall be as provided by the Government.
1.2.3 Final Revisions
1.2.3.1 Title Block Additions
When final revisions have been completed, place the words "REVISED AS- BUILT DRAWING," in letters at least 3/16 inch high, and the date of completion in the revision block above the latest existing revision notation on each drawing Microstation file. The contractor shall procure from the Government the applicable Drawing Management Index (DMI) numbers and place these numbers in the appropriate block of the title block. Also, drawings shall use the DMI# as the file name.
1.1.3.2 Copies of the Final Record Drawings
Blue line or black line prints shall be full size sheet; 22" by 34" image on 24" by 36" sheet. All blue or black line prints shall exhibit good readable print with clear, sharp, dark lines, and shall not be smeared, faded, double imaged, or have torn or ragged edges.
1.2.4 Electronic Drawing Files
1.2.4.1 Standards
The Contractor shall incorporate all information from the final record drawings into .dgn and .pdf files that conform to the Microstation requirements of the Fort Hood System and shall be demonstrated to work on the designated Government computer systems. Microstation and PDF files shall be error and virus free. Microstation and PDF files shall be provided on compact disks (CD).
1.2.4.2 Drafting Qualifications
Only personnel proficient in the preparation of engineering drawings and Microstation shall be employed to prepare contract drawings, additional new drawings, and the Microstation and PDF files. Furnish for approval the qualifications and experience of the personnel, and types of equipment and software, to be used for this work.
Modification of Microstation files will not proceed until the resulting Microstation files have been acceptably demonstrated to work on Fort Hood DPW Microstation systems. Microstation files shall conform to the Fort Worth District Microstation Operating Procedures Manual available from the DPW-P&P Office. The Contracting Officer will review all Microstation files for accuracy and conformance to the above specified drafting and standards.
1.3 Measurement.
This item will be measured by the individual set of sheets and electronic copies in the proper format required for the final approved record drawings.
1.4 Payment.
The work performed and materials furnished in accordance with this item and measured as provided under “Measurement” will be paid for at the unit price bid for “Record Drawings”. This price shall be full compensation for all work necessary in the preparation of final record drawings to include all necessary survey and data gathering, drafting, file preparation, and submission of Microstation and PDF files.
--END OF SECTION--
SECTION 002
CLEARING & GRUBBING - GRADING
2.1 SUMMARY
Line Item: 002 Grading
2.2 DEFINITIONS
None
2.3 MEASUREMENT AND PAYMENT
Line Item: 002 - CLEARING / GRUBBING - Grading
2.3.1 The unit of measure for Grading shall be the Square Yard.
2.3.2 Payment shall be at the contract unit price per square yard.
2.4 DELIVERY, STORAGE, AND HANDLING
Perform in a manner to prevent contamination or segregation of materials.
2.5 REQUIREMENTS FOR OFF SITE SOIL
Soils brought in from offsite shall not contain any chemicals of concern.
2.6 SOIL MATERIALS
All materials shall be obtained from sources outside of Fort Hood unless otherwise specified.
2.6.1 Backfill and Fill Material
ASTM D 2487, classification GW, GP, GM, GC, SW, SP, SM, SC with a maximum ASTM D 4318 liquid limit of 35, maximum ASTM D 4318 plasticity index of 5, and a maximum of 25 percent by weight passing ASTM D 1140, No. 200 sieve.
2.6.2 Topsoil
Natural, organic non expansive soil free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. When unsuitable materials are present at the construction site the contractor shall import suitable materials from off site.
2.7 PROTECTION OF SOILS AND DEWATERING
2.7.1 Protection of Soils
So that construction operations progress successfully, completely drain construction site during periods of construction to keep soil materials sufficiently dry in accordance with Section H (Environmental Protection) "SOIL SURFACE EROSION CONTROL". Provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils, prevent erosion and undermining of foundations.
When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified.
2.7.2 Dewatering
Within 24 hours of the completion of a rain event, all open excavations shall be dewatered. All dewatering discharge shall be indirect flow, no less than 50 feet from any storm water collection point. If it is closer than 50’, contractor shall follow Section H part 3.1.
2.8 FINISH OPERATIONS
2.8.1 General
Clear fence line of trees, brush, and other obstacles at a distance of 10' on either side of the fence line, unless otherwise specified, to install fencing. Establish a fine graded, compacted fence line prior to fencing installation.
2.8.2 Grading
Finish grades shall be within one-tenth of one foot. Grade all areas to drain water away from Fence line at a 6’(H) to 1’(V) slope min.
Maintain areas free of trash and debris. For existing grades that will remain but which were disturbed by Contractor's operations, grade as directed.
2.8.3 Topsoil
Provide 4 inches of suitable topsoil to all cut sections to meet indicated finish grade. Correct irregularities in finish surfaces to eliminate depressions. Protect finished topsoil areas from damage by vehicular or pedestrian traffic.
2.8.4 Protection of Surfaces
Protect newly backfilled, graded, and top soiled areas from traffic, erosion, and settlements that may occur. Repair or reestablish damaged grades, elevations, or slopes.
2.9 DISPOSITION OF SURPLUS MATERIAL
Remove from Government property surplus, excavated foreign obstructions or other soil material not required or suitable for filling or backfilling, and brush, refuse, stumps, roots, and timber.
Refer to Section H for specifications.
SECTION 003
CLEARING & GRUBBING - LIGHT <6" DIAMETER
3.1 SUMMARY
Line Item: 003 CLEARING & GRUBBING - Light <6" diameter
3.2 DEFINITIONS
3.3 MEASUREMENT AND PAYMENT
Clearing shall be specified in each individual task order by square yard when needed.
Line Item: 003 - Clearing & Grubbing Light <6" diameter
3.3.1 The unit of measure for Clearing & Grubbing Light <6" diameter shall be the Square Yard.
3.3.2 Payment shall be at the contract unit price per square yard.
3.4 SUBMITTALS
3.5 EXECTUTION
3.5.1 General
Clear fence line of trees, brush, and other obstacles at a distance of 10' on either side of the fence line, unless otherwise specified, to install fencing.
3.5.2 Clearing and Grubbing
Unless indicated otherwise, remove trees, stumps, logs, shrubs, brush and vegetation and other items that would interfere with construction operations within the clearing limits. Remove stumps entirely. Grub out matted roots and roots over 2 inches in diameter to at least 18 inches below existing surface. Remove all foreign materials and obstructions that will interfere with excavation and compaction operations. Backfill excavated hole following the guidance stated in Section 002 under SOIL MATERIALS.
3.5.3 Disposal of Materials
Trees and stumps shall be brought to the Fort Hood Compost Center as an alternative to hauling off post or as otherwise directed as by the Contracting Officer. Tree roots shall be free of dirt. Please see Section H (Environmental Protection) for further details. Clearing debris (LCD) can be taken to the Fort Hood Compost Center for disposition as an alternative to hauling off post for the contractor. Tree trunks and limbs shall not exceed 4 feet in length. Root balls shall be free of dirt.
SECTION 004
CLEARING & GRUBBING - MEDIUM > 6" DIAMETER
4.1 SUMMARY
Line Item: 004 CLEARING & GRUBBING - Medium > 6" diameter
4.2 REFERENCES
4.3 MEASUREMENT AND PAYMENT
Clearing shall be specified in each individual task order by square yard when needed.
Line Item: 004 - Clearing & Grubbing Medium > 6" diameter
4.3.1 The unit of measure for Clearing & Grubbing Medium > 6" diameter shall be the Square Yard of area work is performed.
4.3.2 Payment shall be at the contract unit price per square yard for area work is performed.
4.4 SUBMITTALS
4.5 General
Clear fence line of trees, brush, and other obstacles at a distance of 10' on either side of the fence line, unless otherwise specified, to install fencing.
4.6 Clearing and Grubbing
Unless indicated otherwise, remove trees, stumps, logs, shrubs, brush and vegetation and other items that would interfere with construction operations within the clearing limits. Remove stumps entirely. Grub out matted roots and roots over 2 inches in diameter to at least 18 inches below existing surface. Remove all foreign materials and obstructions that will interfere with excavation and compaction operations. Backfill excavated hole following the guidance stated in Section 002 under SOIL MATERIALS.
4.7 Disposal of Materials
Trees and stumps shall be brought to the Fort Hood Compost Center as an alternative to hauling off post or as otherwise directed as by the Contracting Officer. Tree roots shall be free of dirt. Please see Section H (Environmental Protection) for further details. Clearing debris (LCD) can be taken to the Fort Hood Compost Center for disposition as an alternative to hauling off post for the contractor. Tree trunks and limbs shall not exceed 4 feet in length. Root balls shall be free of dirt.
5.1 SUMMARY
SECTION 005
REMOVAL OF FENCING – CHAIN LINK FABRIC & POSTS
Line Item: 005 REMOVAL OF FENCING – Chain Link Fabric & Posts
5.2 DEFINITIONS
Chain Link Fabric & Posts: Includes all post, fabric, concrete, bracing, and any accessories attached to the fence being removed.
This line item includes all labor, materials, and equipment for the complete removal of fence post, fabric, all concrete attached to the post, tension wire, barbed wire, barbed wire support arms, all bracing, and any accessories that are attached to the fence being removed, i.e. brace bands, tension bands, grounding rods or wire ties. All are to be removed and disposed of at the contractor’s expense. All holes are to be backfilled and compacted when a new fence is not being erected in the location of the demolished fence.
5.3 MEASUREMENT AND PAYMENT
Line Item: 005 - Removal of Fencing – Chain Link Fabric & Posts
5.3.1 The unit of measure for Removal of Fencing – Chain Link Fabric & Posts shall be by the linear foot.
5.3.2 Payment shall be at the contract unit price by the linear foot.
5.4 DISPOSAL OF REMOVED FENCING MATERIAL
All ferrous metal fencing material from demolition shall be offered to Fort Hood Recycle center and they will have first right and refusal of said material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or similar surface to allow for collection by the Recycle center. (254-535-8566)
-- END OF SECTION --
SECTION 006
REMOVAL OF FENCING – CHAIN LINK FABRIC AND ALL FABRIC ACCESSORIES
6.1 SUMMARY
Line Item: 006 REMOVAL OF FENCING – Chain Link Fabric and All Fabric
Accessories
6.2 DEFINITIONS
Chain Link Fabric and All Fabric Accessories: Includes all Fabric and
Accessories in the designated length of fence to be removed.
This line item includes all labor, materials, and equipment for the removal, in designated lengths, of fencing fabric with all accessories, to include tension bars, tension bands, and brace bands. All are to be removed and disposed of at the contractor’s expense.
6.3 MEASUREMENT AND PAYMENT
Line Item: 006 – REMOVAL OF FENCING – Fabric and All Fabric Accessories
6.3.1 The unit of measure for REMOVAL OF FENCING – Chain Link Fabric and All
Fabric Accessories shall be the linear foot.
6.3.2 Payment shall be at the contract unit price per linear foot.
6.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or similar surface to allow for collection by the Recycle center. (254-535- 8566).
SECTION 007
REMOVAL OF FENCING – INDIVIDUAL POSTS SET IN CONCRETE
7.1 SUMMARY
Line Item: 007 REMOVAL OF FENCING – Individual Posts Set in Concrete
7.2 DEFINITIONS
Individual Posts Set in Concrete: Includes Post, Concrete, and any accessories attached to the post being removed.
removal of the fence post, all concrete attached to the post, and any accessories that are attached to the post being removed, i.e. brace bands, tension bands, or wire ties. All are to be removed and disposed of at the contractor’s expense.
7.3 MEASUREMENT AND PAYMENT
Line Item: 007 - REMOVAL OF FENCING – Individual Posts Set in Concrete
7.3.1 The unit of measure for REMOVAL OF FENCING – Individual Posts Set in Concrete shall be by each post removed.
7.3.2 Payment shall be at the contract unit price by each post removed.
7.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 008
8.1 SUMMARY
REMOVAL OF FENCING – CHAIN LINK BRACING
Line Item: 008 REMOVAL OF FENCING – Chain Link Bracing
8.2 DEFINITIONS
Chain Link Bracing: Includes all pipe bracing, truss rods, and any accessories that are an integral piece of the bracing being removed.
removal of pipe bracing, rail end cups, brace bands, and truss rods and holder that are attached to the bracing being removed within two posts, as at a pull post or corner post. All are to be removed and disposed of at the contractor’s expense.
8.3 MEASUREMENT AND PAYMENT
Line Item: 008 - REMOVAL OF FENCING – Chain Link Bracing
8.3.1 The unit of measure for REMOVAL OF FENCING – Chain Link Bracing shall be by the single set of bracing materials removed inside two posts.
8.3.2 Payment shall be at the contract unit price by the single set of bracing materials removed inside two posts.
8.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 009
9.1 SUMMARY
REMOVAL OF FENCING – CHAIN LINK BARBED WIRE
Line Item: 09 REMOVAL OF FENCING – Chain Link Barbed Wire
9.2 DEFINITIONS
Barbed Wire: Single strand of barbed wire.
removal of a single strand of barbed wire. All are to be removed and disposed of at the contractor’s expense.
9.3 MEASUREMENT AND PAYMENT
Line Item: 09 - REMOVAL OF FENCING – Chain Link Barbed Wire
9.3.1 The unit of measure for REMOVAL OF FENCING – Barbed Wire shall be by the linear foot of a single strand of barbed wire.
9.3.2 Payment shall be at the contract unit price by the linear foot of a single strand of barbed wire.
9.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 010
10.1 SUMMARY
REMOVAL OF FENCING – HELICAL RAZOR WIRE
Line Item: 010 REMOVAL OF FENCING – Helical Razor Wire
10.2 DEFINITIONS
Helical Razor Wire: Coiled razor wire placed on top of a high security fence.
This line item includes all labor, materials, and equipment to complete remove helical razor wire for a high security chain link fence.
10.3 MEASUREMENT AND PAYMENT
Line Item: 010 - REMOVAL OF FENCING – Stainless Steel 18" Helical Razor
Wire
10.3.1 The unit of measure for Stainless Steel 18" Helical Razor Wire shall be by the linear foot of the fence line.
10.3.2 Payment shall be at the contract unit price by the linear foot of the fence line.
10.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 011
REMOVAL OF FENCING – INDIVIDUAL BARBED WIRE EXTENSION ARM
11.1 SUMMARY
Line Item: 011 REMOVAL OF FENCING – Individual Barbed Wire Extension Arm
11.2 DEFINITIONS
Individual Barbed Wire Extension Arm: Single barbed wire extension arm removal of, single or double, barbed wire extension arms of any size that sit on top of any chain link fence. All forms of attachment to a post are covered in this line item. All specified are to be removed and disposed of at the contractor’s expense.
11.3 MEASUREMENT AND PAYMENT
Line Item: 011 - REMOVAL OF FENCING – Individual Barbed Wire
Extension Arm
11.3.1 The unit of measure for REMOVAL OF FENCING – Individual Barbed Wire Extension Arm shall be by each single or double extension arm that is removed.
11.3.2 Payment shall be at the contract unit price by each single or double extension arm that is removed.
11.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 012
12.1 SUMMARY
REMOVAL OF FENCING – CHAIN LINK TENSION WIRE
Line Item: 012 REMOVAL OF FENCING – Chain Link Tension Wire
12.2 DEFINITIONS
Chain Link Tension Wire: Any single strand, slick wire that is used at either the top or bottom of the fence to hold tension on the fabric between the posts.
removal of tension wire of any size and whatever holds it to the fabric. All are to be removed and disposed of at the contractor’s expense.
12.3 MEASUREMENT AND PAYMENT
Line Item: 012 - REMOVAL OF FENCING – Chain Link Tension Wire
12.3.1 The unit of measure for REMOVAL OF FENCING – Chain Link Tension
Wire shall be by the linear foot.
12.3.2 Payment shall be at the contract unit price by the linear foot.
12.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 013
13.1 SUMMARY
REMOVAL OF FENCING – CHAIN LINK FENCE RAIL
Line Item: 013 REMOVAL OF FENCING – Chain Link Fence Rail
13.2 DEFINITIONS
Chain Link Fence Rail: Any tubing that is used at either the top, middle, or bottom of the fence to hold tension on the fabric between the posts and for structural integrity of the fence itself.
removal of fence rail tubing of any size and accessories which hold it to the fence. All are to be removed and disposed of at the contractor’s expense.
13.3 MEASUREMENT AND PAYMENT
Line Item: 013 - REMOVAL OF FENCING – Chain Link Fence Rail
13.3.1 The unit of measure for REMOVAL OF FENCING – Chain Link Fence
Rail shall be by the linear foot.
13.3.2 Payment shall be at the contract unit price by the linear foot.
13.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 014
14.1 SUMMARY
REMOVAL OF FENCING – CHAIN LINK GATES - SWING
Line Item: 014 REMOVAL OF FENCING – Chain Link Gates - Swing
14.2 DEFINITIONS
Chain Link Gates - Swing: Any chain link swinging gate and all accessories.
removal of chain link swinging gates of any size and accessories, i.e.
hinges, latches, barbed wire, tie wire, gate keeper, drop rod assembly, etc.
All are to be removed and disposed of at the contractor’s expense. All holes are to be backfilled and compacted when a new fence is not being erected in the location of the demolished fence.
14.3 MEASUREMENT AND PAYMENT
Line Item: 014 - REMOVAL OF FENCING – Chain Link Gates - Swing
14.3.1 The unit of measure for REMOVAL OF FENCING – Chain Link Gates - Swing shall be by the linear foot of the entire gate section removed.
14.3.2 Payment shall be at the contract unit price by the linear foot.
14.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 015
REMOVAL OF FENCING – CHAIN LINK GATES - SLIDING & CANTILEVER
15.1 SUMMARY
Line Item: 015 REMOVAL OF FENCING – Chain Link Gates - Sliding
& Cantilever
15.2 DEFINITIONS
Chain Link Gates - Sliding & Cantilever: Any chain link sliding or cantilever gate and all accessories.
removal of chain link sliding or cantilever gates of any size and its accessories, i.e. hinges, wheels, rollers, mounting hardware, latches, barbed wire, and tie wire. All are to be removed and disposed of at the contractor’s expense. All holes are to be backfilled and compacted when a new fence is not being erected in the location of the demolished fence.
15.3 MEASUREMENT AND PAYMENT
Line Item: 015 - REMOVAL OF FENCING – Chain Link Gates - Sliding & Cantilever
15.3.1 The unit of measure for REMOVAL OF FENCING – Chain Link Gates –
Sliding & Cantilever shall be by the linear foot of the entire gate section removed.
15.3.2 Payment shall be at the contract unit price by the linear foot.
15.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 016
16.1 SUMMARY
REMOVAL OF FENCING – PRIVACY SLATS
Line Item: 016 REMOVAL OF FENCING – Privacy Slats
16.2 DEFINITIONS
Privacy Slats: Vinyl slats that run either vertically or diagonally weaved between the chain link fabric to partially block the view from outside a designated area of fence.
removal of vinyl privacy slats from a designated length of chain link fencing. All are to be removed and disposed of at the contractor’s expense.
16.3 MEASUREMENT AND PAYMENT
Line Item: 016 - REMOVAL OF FENCING – Privacy Slats
16.3.1 The unit of measure for REMOVAL OF FENCING – Privacy Slats shall be by the linear foot.
16.3.2 Payment shall be at the contract unit price by the linear foot.
16.4 DISPOSAL OF REMOVED PRIVACY SLATS
Refer to Section H (Environmental Protection)
SECTION 017
17.1 SUMMARY
REMOVAL OF FENCING – BARBED WIRE FENCE
Line Item: 017 REMOVAL OF FENCING – Barbed Wire Fence
17.2 DEFINITIONS
Barbed Wire Fence: 3 to 5 barbed wire strands and stays.
removal of all strands of barbed wire, fence stays (metal or wooden), all line posts, and all accessories, i.e. tie wire or braces. All are to be removed and disposed of at the contractor’s expense. All holes are to be backfilled and compacted when a new fence is not being erected in the location of the demolished fence.
17.3 MEASUREMENT AND PAYMENT
Line Item: 017 - REMOVAL OF FENCING – Barbed Wire Fence
17.3.1 The unit of measure for REMOVAL OF FENCING – Barbed Wire Fence shall be by the linear foot.
17.3.2 Payment shall be at the contract unit price by the linear foot.
17.4 DISPOSAL OF REMOVED FENCING MATERIAL
material. Recycle Center will provide containers for material to be deposited in. Concrete attached to fence posts shall be removed before depositing in to container. Container must be placed on a hard stand or
SECTION 018
18.1 SUMMARY
REMOVAL OF FENCING – WOODEN FENCE SECTIONS
Line Item: 018 - REMOVAL OF FENCING – Wooden Fence Sections
18.2 DEFINITIONS
Wooden Fence Sections: Sections of wooden privacy fencing attached to posts set in concrete.
removal of wooden privacy fencing. This includes the wooden fencing slats, railing they are attached to, all bracing, and all accessories, i.e. gate hinges or metal brackets that hold wooden fencing to a metal post. All are to be removed and disposed of at the contractor’s expense. The contractor can take wood material to the Fort Hood Compost Center as an alternative to hauling off post. Lengths shall not exceed 4’.
This line item does not include the removal of line posts set in concrete.
18.3 MEASUREMENT AND PAYMENT
Line Item: 018 - REMOVAL OF FENCING – Wooden Fence Sections
18.3.1 The unit of measure for REMOVAL OF FENCING – Wooden Fence
Sections shall be by the linear foot.
18.3.2 Payment shall be at the contract unit price by the linear foot.
18.4 DISPOSAL OF REMOVED FENCING MATERIAL
Refer to Section H (Environmental Protection)
SECTION 019
REMOVAL OF FENCING – WOODEN FENCE POSTS SET IN CONCRETE
19.1 SUMMARY
Line Item: 019 REMOVAL OF FENCING – Wooden Fence Posts Set in Concrete
19.2 DEFINITIONS
Wooden Fence Posts Set in Concrete: Includes Post, Concrete, and any accessories attached to the post being removed.
removal of the wooden fence post, all concrete attached to the post, and any accessories that are attached to the post being removed, i.e. brackets, nails, or screws. All are to be removed and disposed of at the contractor’s expense. The contractor can take wood material to the Fort Hood Compost Center as an alternative to hauling off post. Lengths shall not exceed 4’.
Concrete shall be removed from the posts before depositing at the compost center. All holes are to be backfilled and compacted when a new fence is not being erected in the location of the demolished fence.
19.3 MEASUREMENT AND PAYMENT
Line Item: 019 - REMOVAL OF FENCING – Wooden Fence Posts Set in Concrete
19.3.1 The unit of measure for REMOVAL OF FENCING – Wooden Fence Posts
Set in Concrete shall be by each post removed.
19.3.2 Payment shall be at the contract unit price by each post removed.
SECTION 020
20.1 SUMMARY
INSTALL POST – 2 3/8" DIAMETER LINE POST
Line Item: 020 INSTALL POST – 2 3/8" Diameter Line Post
20.2 DEFINITIONS
2 3/8" Diameter Line Post: Individual 2 3/8” Line posts set in concrete (Galvanized).
This line item includes all labor, materials, and equipment to install 2 3/8” line posts set in concrete in lengths up to 8’ above grade. All lengths over 8’ above grade shall be covered in line item 21.
20.3 MEASUREMENT AND PAYMENT
Line Item: 020 - INSTALL POST – 2 3/8" Diameter Line Post
20.3.1 The unit of measure for INSTALL POST – 2 3/8" Diameter
Line Post shall be by each post installed up to 8’ above grade, in length.
20.3.2 Payment shall be at the contract unit price by each post installed up to 8’ above grade, in length.
20.4 DELIVERY, STORAGE, AND HANDLING
Deliver materials to site in an undamaged condition. Store materials off the ground to provide protection against oxidation caused by ground contact.
20.5 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A 702(2089; R 2006) Standard Specification for Steel Fence Posts and Assemblies, Hot Wrought
ASTM C 94/C 94M (2009a) Standard Specification for Ready-Mixed Concrete
ASTM F 567(2007) Standard Practice for Installation of Chain Link Fence
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS RR-F-191/3(Rev D) Fencing, Wire and Post, Metal (Chain- Link Fence Posts, Top Rails and Braces)
20.6 SUBMITTALS
Government approval is required for all submittals submit the following in accordance with Section C (SUBMITTAL PROCEDURES):
SD-03 Product Data
Submit Manufacturer's catalog data for the following items:
Posts
Concrete Tickets
SD-07 Certificates
Submit Certificates of compliance in accordance with the applicable reference standards and descriptions of this section for the following items:
Zinc Coating
20.7 PRODUCTS
ASTM A 702, FS RR-F-201/3
20.7.1 ZINC COATING
Ferrous-metal components and accessories, except as otherwise specified, must be hot-dip galvanized after fabrication.
20.7.2 Chain Link Fencing
All terminal posts shall be class 1 galvanized steel pipe. End, Corner, pull, and personnel gate posts: 2.375" OD, minimum wall thickness 0.145".
20.7.3 5 Strand barbed Wire Fence
All line posts shall be constructed from class 1 galvanized steel pipe, 2.375" schedule 80, with all brace joints welded, in place, completely around the joint.
20.7.4 Concrete
Provide concrete conforming to ASTM C 94/C 94M. Concrete mix must obtain a minimum 28-day compressive strength of 3,000 psi
20.8 EXECUTION
Completed installation must conform to ASTM F 567.
20.8.1 Excavation
Excavations for post footings must be augured holes in virgin or compacted soil, of minimum sizes as follows:
2.375" posts: 12" diameter, 36" post, 6” deeper for cone = 42” deep.
Soil from excavations must be spread uniformly adjacent to the fence line or on areas of Government property, as directed. Rock over 1” in diameter shall be removed from the hole.
When solid rock is encountered near the surface, the Contractor must drill into the rock at least 18" for end, pull, corner, and gate posts. Drill holes at least 1 inch greater in diameter than the largest dimension of the placed post.
If solid rock is below the soil overburden, Contractor must drill to the full depth required except that penetration into rock need not exceed the minimum depths specified above.
20.8.2 Setting Posts
Concrete used in the setting of posts must conform to ASTM C 94/C 94M.
obtain a minimum 28-day compressive strength of 3,000 psi.
Remove loose and foreign materials from holes and the soil moistened prior to placing concrete.
Provide tops of footings that are trowel finished and sloped or domed at least 1” above finished grade to shed water away from posts. Set hold-open devices, sleeves, and other accessories in concrete.
Posts set in concrete construction must be set plumb and in line, with tops aligned and held in position for 72 hours before any other work is done on the posts.
SECTION 021
INSTALL POST – 2 3/8" DIAMETER LINE POST PER FT OVER 8' ABOVE GRADE
21.1 SUMMARY
Line Item: 020 INSTALL POST – 2 3/8" Diameter Line Post per Ft Over 8' Above Grade
21.2 DEFINITIONS
2 3/8" Diameter Line Post Per Ft Over 8' Above Grade: Individual 2 3/8” line posts set in concrete (Galvanized)
This line item is for the installation of 2 3/8” line posts set in concrete, for lengths over 8’ above grade. This line item is intended to be used in conjunction with line item 020.
All specifications for this line item will be referenced in the specifications for line item 020.
21.3 MEASUREMENT AND PAYMENT
Line Item: 021 - INSTALL POST - 2 3/8" Diameter Line Post per ft Over
10'
21.3.1 The unit of measure for INSTALL POST – 2 3/8" Diameter Line Post per ft Over 8' above grade shall be by the linear foot of the post over 8’ above grade in length.
21.3.2 Payment shall be at the contract unit price by the linear foot of the post over 8’ above grade in length.
SECTION 022
22.1 SUMMARY
INSTALL POST – 2 7/8" DIAMETER TERMINAL POST
Line Item: 022 INSTALL POST – 2 7/8" Diameter Terminal Post
22.2 DEFINITIONS
2 7/8" Diameter Terminal Post: Individual 2 7/8” terminal concrete (Galvanized). Examples of a terminal post are an Pull, or Gate post.
posts set in End, Corner, This line item includes the installation of 2 7/8” terminal posts set in concrete in lengths up to 8’ above grade. All lengths over 8’ above grade shall be covered in line item 23. All Diameters over 2 7/8” shall be covered in Line items 0024 – 4”, 0025 - 6 5/8”, and 0026 – 8 5/8”. The concrete and excavation required to set the post are included in this line item.
22.3 MEASUREMENT AND PAYMENT
Line Item: 022 - INSTALL POST – 2 7/8" Diameter Terminal Post
22.3.1 The unit of measure for INSTALL POST – 2 7/8" Diameter
Terminal Post shall be by each post installed up to 8’ above grade in length.
22.3.2 Payment shall be at the contract unit price by each post installed up to 8’ above grade in length.
22.4 DELIVERY, STORAGE, AND HANDLING
22.5 REFERENCES
ASTM A 702(1989; R 2006) Standard Specification for Steel Fence
22.6 SUBMITTALS
in accordance with Section C SUBMITTAL PROCEDURES:
Concrete Tickets
SD-07 Certificates
Submit Certificates of compliance in accordance with the
22.7 PRODUCTS
ASTM A 702, FS RR-F-191/3
22.7.1 ZINC COATING
22.7.2 Chain Link Fencing
All terminal posts shall be class 1 galvanized steel pipe. End, Corner, pull, and personnel gate posts: 2.875" OD, minimum wall thickness 0.203".
22.7.3 5 Strand barbed Wire Fence
All terminal posts shall be constructed from class 1 galvanized steel pipe, 2.875" schedule 80, with all brace joints welded, in place, completely around the joint. After welding, each weld shall be cleaned thoroughly and a galvanizing paint shall be used to cover each weld and any area around the weld where damage has occurred to the galvanizing material.
22.7.4 Concrete
22.8 EXECUTION
22.8.1 Excavation
2.875" posts: 18" diameter, 36" post, 6” deeper for cone = 42” must drill into the rock at least 18" for end, pull, corner, and gate posts. Drill holes at least 1 inch greater in diameter than the largest dimension of the placed post.
22.8.1.1 Chain Link Fencing
Terminal (corner and pull) posts shall be set at changes in vertical and horizontal alignment of 15 degrees or more. Provide fabric continuous between terminal posts; however, runs between terminal posts shall not exceed 500' which shall be the maximum distance between braced posts.
Each gate post shall be extended sufficiently above the top of the fabric height to attach the three strands of barbed wire on the top of the fence with brace bands. A post cap shall be used at each Gate Post. NO BARBED WIRE SUPPORT ARMS SHALL BE USED ON
GATE POSTS.
22.8.1.1.1 Air Gap for Flood Prone Areas
Place a 6" air gap up the fence line from the flood prone area as indicated. There shall be a end post and proper bracing on each end of the existing fence where air gap is to be placed so that fence can be stretched in both directions. The air gap pole footings shall be divided with a piece of .5" engineered wood so that there is no concrete connecting the two separate footings in the ground. This will allow for a clean sever in the event of flooding and the accumulation of trash against the fence to prevent further damage to the rest of the fence line.
22.8.1.2 5 Strand Barbed Wire Fence
Terminal (corner and pull) posts shall be set at changes in vertical and horizontal alignment of 15 degrees or more. Provide fabric continuous between terminal posts; however, runs between terminal posts shall not exceed 1/4 mile. Brace posts shall be set 10' along the fence line on either side of the pull or corner post and on the fence side of end or gate posts.
22.8.2 Setting Posts
posts. Set hold-open devices, sleeves, and other accessories in
Posts set in concrete construction must be set plumb and in line
SECTION 023
INSTALL POST – 2 7/8" DIAMETER TERMINAL POST PER FT OVER 8’ ABOVE
GRADE
23.1 SUMMARY
Line Item: 023 INSTALL POST – 2 7/8" Diameter Terminal Post per Ft Over 8’ Above Grade
23.2 DEFINITIONS
2 7/8" Diameter Terminal Post Per Ft Over 10': Individual 2 7/8” terminal posts set in concrete (Galvanized or Mild Steel)
This line item includes all labor, materials, and equipment to install 2 7/8” terminal posts set in concrete, for lengths over 8’ above grade. This line item is intended to be used in conjunction with line item 022.
All specifications for this line item will be referenced in the specifications for line item 022.
23.3 MEASUREMENT AND PAYMENT
Line Item: 023 - INSTALL POST - 2 7/8" Diameter Terminal Post per ft
Over 8’ above grade
23.3.1 The unit of measure for INSTALL POST – 2 7/8" Diameter Terminal Post per ft Over 8’ above grade shall be by the linear foot of the post over 8’ in length.
23.3.2 Payment shall be at the contract unit price by the linear foot of the post over 8’ above grade in length.
SECTION 024
24.1 SUMMARY
INSTALL POST – 4" DIAMETER GATE POST
Line Item: 024 INSTALL POST – 4" Diameter Gate Post
24.2 DEFINITIONS
4" Diameter Gate Post: Individual 4” galvanized gate posts set in
This line item includes all labor, materials, and equipment to install 4” galvanized gate posts set in concrete, includes post cap and brace bands. The concrete and excavation required to set the post are included in this line item.
24.3 MEASUREMENT AND PAYMENT
Line Item: 024 - INSTALL POST – 4" Diameter Gate Post
24.3.1 The unit of measure for INSTALL POST – 4" Diameter Gate Post shall be by each post installed.
24.3.2 Payment shall be at the contract unit price by each post installed.
24.4 DELIVERY, STORAGE, AND HANDLING
24.5 REFERENCES
24.6 SUBMITTALS
Concrete Tickets
SD-07 Certificates
Submit Certificates of compliance in accordance with the
24.7 PRODUCTS
24.7.1 ZINC COATING
Provide zinc coating of weight not less than 0.90 ounces per square foot.
24.7.2 Chain Link Fencing
All gate posts shall be class 1 galvanized steel pipe. Gate posts: 4" OD, minimum wall thickness 0.226".
24.7.3 Concrete
24.8 EXECUTION
When a 4” gate post is used, the maximum gate leaf length shall not exceed 13’.
Each gate post shall be extended sufficiently above the top of the fabric height to attach the three strands of barbed wire on the top of the fence with brace bands. A post cap shall be used at each Gate Post. NO BARBED
WIRE SUPPORT ARMS SHALL BE USED ON GATE POSTS.
24.8.1 Excavation
4" posts: 18" diameter, 48" post, 6” deeper for cone = 54” must drill into the rock at least 18" for gate posts. Drill holes at least 1 inch greater in diameter than the largest dimension of the placed post.
24.8.2 Setting Posts
posts.
--- END OF SECTION --
SECTION 025
25.1 SUMMARY
INSTALL POST – 6 5/8" DIAMETER GATE POST
Line Item: 025 INSTALL POST – 6 5/8" Diameter Gate Post
25.2 DEFINITIONS
6 5/8" Diameter Gate Post: Individual 6 5/8" galvanized gate posts set in
This line item includes all labor, materials, and equipment to install 6 5/8" galvanized gate posts set in concrete, includes post cap and brace bands. The concrete and excavation required to set the post are included in this line item.
25.3 MEASUREMENT AND PAYMENT
Line Item: 025 - INSTALL POST – 6 5/8" Diameter Gate Post
25.3.1 The unit of measure for INSTALL…
This is the start of the file's text. The full file is on GovTribe.