This is a Scope of Work document for the Tailwater Volunteer Village Campground construction project at Green River Lake in Campbellsville, Kentucky, managed by the U.S. Army Corps of Engineers.
The contractor must furnish all materials, supplies, tools, equipment, transportation, labor, supervision, and quality control to construct a two-site RV campground adjacent to the river corridor. Work includes site excavation, access road installation, and complete installation of water, electrical, and sewage utilities to each campsite. Each campsite is 100 feet long by 20 feet wide with a 25-foot by 25-foot amenity extension for fire rings and picnic tables. Sites require 10-inch excavation depth with road-grade geo-textile fabric, compacted structural stone base, and #9 size stone finish surface. The 175-foot access drive requires 10-inch excavation with geotextile fabric, compacted structural stone base per KYTC specifications, and Dense Graded Aggregate finish surface graded 2 to 4 inches above surrounding soil. The water distribution system uses ¾-inch PEX supply lines buried 30 inches deep with galvanized riser pipes, ball valve controls, and winterization drain lines. The electrical system requires a 320/400 Amp meter base with dual 200 Amp disconnect panels, two 100 Amp breakers in protective conduit, and pedestal-mounted RV receptacles (125V/20A GFCI, 125V/30A, and 125/250V/50A) complying with NEC Articles 550 and 551. The sewage system consists of two 1,000-gallon concrete holding tanks, full RV sewer inlets, PVC cleanouts, and 600 linear feet of lateral drain field lines in compliance with local health and plumbing codes. Work must begin within 10 calendar days of Notice to Proceed and be completed within 120 calendar days. The contractor must have at least five years' experience, attend a mandatory pre-work conference, provide safety plans and certifications, and comply with security requirements including background investigations for all personnel accessing Louisville District facilities. Work hours are Monday through Friday, 7:30 a.m. to 5:00 p.m. EST, with Department of Labor wage rates applicable. Payment is by Electronic Funds Transfer upon completion and acceptance of work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work Tailwater Volunteer Village Campground
U.S. Army Corps of Engineers Green River Lake
544 Lake Road Campbellsville, KY 42718
TP-1.1 GENERAL:
a. Description. The contractor shall furnish all materials, supplies, tools, parts, equipment, transportation, labor, supervision, communication, and quality control to complete the work listed below, at the areas specified at Green River Lake, located in Campbellsville, KY 42718.
b. Work shall be provided in accordance with all Terms, Conditions, General, Specific and
Technical Provision, Exhibits, Attachments, Drawings, etc. contained herein or incorporated by Reference. All distances and measurements given are approximate. Each interested contractor is urged to visit the job site to assess quantities, critical dimensions, and work conditions. All work will be done according to standard industry practices.
Access to the work area is controlled and appointments to look at the site shall be coordinated with the Technical Representative. This includes all mandatory provisions of the Federal Acquisition Regulation (FAR), whether referenced or not, current at time of award.
c. Contractor Responsibility. Contractor’s work and responsibility shall include but are not limited to supply of equipment/materials, all planning, programming, administration, management, supervision, and inspection required to assure all equipment/materials are acquired and work is conducted in accordance with the contract and all applicable laws, regulations, or directives. The Contractor shall ensure all work meets or exceeds specifications. The prime Contractor shall be responsible for ensuring all subcontractors comply with the provisions of this contract.
d. Performance Required. Special consideration of the Contractor is directed to the fact that required accuracy, thoroughness, safety, and progress of this work are essential to the intended purpose. The contractor must be cognizant of the difficulties involved and of the contingencies which may arise, and must make certain that their personnel, equipment, transportation facilities and supply of materials are adequate at all times to ensure complete compliance with all provisions of these specifications. The work shall be done under professional supervision by competent employees. All contract work shall be in accordance with the submitted documents, and any additions, revisions or deletions must be approved by the Contracting Officer or his/her authorized representative.
e. Completion of Work. Completion of work shall include acceptable performance of all aspects of this contract.
f. Conditions.
1. Pre-Work Conference: The contractor will be required to attend a pre-work conference, scheduled at least one week prior to beginning work, where the Contractors plan of work, safety plan, security plan, start-up date, and other items included in this contract will be briefly discussed. The contractor will also be required to supply the necessary proof of liability insurance (copy of insurance forms) at that time. In addition, a copy of the Safety Data Sheet will be given to the government at this time and reviewed to ensure contractor compliance. This area is a secure area, and the contractor will need to supply the government with a list of contractor personnel that will be working on-site.
2. Damages. The contractor shall be responsible for all damages to government or private property during the course of this contract. The contractor shall have appropriate insurance to cover liability and damages.
3. Hours and Days of Work. Work may be conducted between the hours of 7:30 a.m. and
5:00 p.m. EST, Monday through Friday. No work shall be performed on Saturday or Sunday or on federally observed holidays, i.e., Memorial Day, 4th of July and Labor Day unless approved by the Corps Park Manager.
4. Site Visit.
52.236-27 Site Visit (Construction) (Feb 1995) Alternate I (Feb 1995).
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-
Tuesday August 4th at 10:00AM CT
(c) Participants will meet at -
TPOC: John Houk, 270-465-4463 U.S. Army Corps of Engineers Green River Lake
No inquiries will be allowed during the site visit. All inquiries must be submitted via the ProjNet Bidder Inquiry site. A Bidder Key is provided with the solicitation information.
5. Technical Point of Contact (TPOC).
John Houk, 270-465-4463 U.S. Army Corps of Engineers Green River Lake
6. Payment Procedure/Additional Work. At no time should the contractor do additional work without prior authorization of the Contracting Officer, and no work shall be performed that will cause the Contractor to exceed the contract price. Work performed without a binding contract document authorizing such work shall result in the Contractor not being paid for that work performed. During the course of the contract, any additional work determined to be needed may be requested by the Technical Representative to the Contracting Officer for a Contract Modification.
7. Contract Start and Completion Dates. Work under this contract shall begin within 10 calendar days of Notice to Proceed (NTP) being issued and must be completed within 120 calendar days of Notice to Proceed. Additional time may be granted for inclement weather, when coordinated with and approved by the Technical Representative. This includes delay of work that may occur during excessive rainfall or wet periods.
8. Wage Rates: Department of Labor wage rates apply to this work and are included. The contractor is required to provide payroll documents for all work performed under this contract.
9. The Contractor shall, at all times prior to delivery, take care to protect and preserve all materials, supplies, and equipment of every description (including material and property which may be Government owned) and all work performed. All reasonable requests of the Contracting Officer or his/her authorized representative to enclose or specially protect such property shall be complied with. If so, determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government, and the cost thereof may be charged to the Contractor or deducted from any payment due.
10. The Contractor will notify the Technical Representative or his/her authorized representative, upon commencement of work activities, and difficulties, interruption, or suspension of work, and when the required work has been completed. The Contractor shall update the Technical Representative, or their authorized representative, no less than once weekly on status of work being done. Work will commence when the funds are allocated, and work orders have been received from the Contracting Officer or his/her authorized representative.
TP-1.2 CONTRACTOR SUBMITTAL. Unless otherwise specified, the Contractor shall submit the following information to the Technical Representative prior to the pre-work conference for this contract:
a. Safety Plans. The Contractor shall submit, for acceptance by the Technical
Representative, an accident prevention plan and Activity Hazard Analysis (AHA) in accordance with the requirements of the Corps of Engineer’s Safety and Health Requirements Manual, EM385-1-1, hereinafter referred to as the Safety Manual, current at the time of award.
b. Certification of Employees Qualified to Administer First Aid and CPR. The
Contractor shall submit proof the appropriate number of employees, as required in the Safety Manual, are certified to administer First Aid and CPR.
TP-1.3 SAFETY.
a. General Safety. The Contractor shall comply with the safety standards contained in Corps of Engineers Manual, EM 385-1-1, “Safety and Health Requirements Manual”, current at the time of award, as well as all current provisions of the Occupational Safety and Health Act (OSHA).
b. Safety Manual Requirements. The Contractor and employees shall comply with all pertinent sections of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385-1-1, current at the time of award, and any subsequent revisions. This manual will be available on the Internet at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_3 85-1-1.pdf The Contractor’s safety plan must be submitted in writing and can be turned in at the same time as the pre-work conference.
c. Personal Protective Apparel and Equipment. Protective apparel and equipment, as identified in the AHA, shall be provided to eliminate or minimize hazards to personnel.
As a minimum, each employee shall wear a sleeved shirt, long trousers and safety-toe shoes or boots during all contract work. Hard hats, face shields, safety glasses with side-shields, or goggles, and hearing protection shall be worn by employees when required by safety manual. Fire extinguisher(s) and first aid kit(s) meeting the Safety Manual standards shall also be provided and easily accessible to all employees.
d. Contractor Employees Certified in First Aid & CPR. The Contractor shall schedule employees, so the appropriate numbers of certified personnel are on duty to administer First Aid and CPR as required by the Safety Manual. Copies of their certification shall be provided before work begins under this contract.
TP-1.4 ACCIDENT REPORTING. The Contractor shall maintain accurate accident records and report accidents as prescribed by the Technical Representative. Accidents shall be reported within 24 hours of occurrence, and all serious accidents (those resulting in death or injury requiring medical attention or lost time) shall be reported immediately.
TP-1.5 DAMAGE REPORTS. In all instances where Government property, equipment, natural features, landscape, or trees are damaged by contract employees, an immediate notification shall http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf be made to the Technical Representative. A full report of the incident and extent of such damage shall be submitted to the Technical Representative within two working days of occurrence, excluding weekends and holidays.
TP-1.6 CONTRACT EMPLOYEES. All contract employees shall always conduct themselves in a proper and courteous manner. Contract employees shall comply with all provisions of Title 36, Chapter III, Part 327, CFR and obey all posted signs and regulations in the performance of the work under this contract. Being under the influence of or consuming alcoholic beverages or controlled substances by the Contractor or employees while on duty is prohibited.
TP- 2.1 SPECIAL REQUIREMENTS:
a. Security
i. Access and General Protection/Security Policy and Procedures. All contractors and all associated sub-contractor’s employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor should also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
ii. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the Technical Representative, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Representative NLT 5 calendar days after the completion of the training.
iii. Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the Technical Representative no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete Form I-9, Employment Eligibility Verification, with the designated Government http://www.uscis.gov/e-verify representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
b. Payment: Payment will be made by Electronic Funds Transfer (EFT), upon acceptance of the completed work and providing final invoice and labor records.
Invoice(s) shall be mailed to:
US Army Corps of Engineers Green River Lake
c. Qualifications: The contractor shall have at least five (5) years’ experience in the requirements for this Scope of Work.
SUPPLEMENTAL SECURITY REQUIREMENTS
All Contractors and subcontractor employee(s) working on this contract who require access to any Louisville District Lake Projects and Lock and Dam Projects shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The Louisville District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Louisville District Security Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Louisville District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
FOR ALL LOUISVILLE DISTRICT CONTRACTS:
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Louisville District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted access to Louisville District facilities.
The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working, (2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) US Citizens Security Access Form or Pre-Bid/Site Visit Form; each employee working on site must have a background investigation form submitted directly to the Louisville District Security Office.
The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.
Contractors shall have background checks completed for their employees annually in the case of Contracts with an initial period of performance (POP) greater than 1 year and those Contracts with Options or Modifications Which Extend the POP beyond 1 year. For instance, if the employee was cleared in May of 2022, they shall be cleared again in May of 2023. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.
The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Louisville District USACE Security Office for background purposes.
FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)
The documents listed below are required: SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). Fingerprints are captured electronically at the closest Army Recruiting Station to the contractor’s home of record or at the USACE, Louisville District Security Office.
Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
Following submission of paperwork, the Louisville District Security Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Louisville District Security Office will make recommendations to the PCO or their Designated Representative. The Louisville District Security Office cannot give approval due to unfavorable report(s). The Louisville District Security Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all http://www.opm.gov/forms/ foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.
In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Louisville District Security Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Louisville District Security Office by phone, letter, or email at the following numbers/addresses:
CELRL-SC
220 W. Main Street Suite 120B Louisville, KY 40202
Charles R. Tanner, phone (502) 315-6929; email Charles.R.Tanner@usace.army.mil James R. Milner, phone (502) 315-6916; email James.R.Milner@usace.army.mil Jason Almodovar, phone (502) 315-6754; email Jason.Almodovar@usace.army.mil
TP-3.1 GENERAL SPECIFICATIONS:
a. CLIN 0001 (Base): Tailwater Volunteer Village Campground Construction
Please Note: All distances and measurements given are approximate and should be verified by the contractor prior to ordering materials. Each bidding contractor is urged to visit the job site to assess quantities, critical dimensions, and work conditions. All work will be done according to standard industry practices.
Contractor shall furnish all materials, supplies, tools, equipment, transportation, labor and supervision necessary to construct a small, two-site campground adjacent to the river corridor.
Construction includes site excavation, access road installation and the complete installation of water, electrical and sewage utilities to each campsite. All work must adhere to the project maps provided (Exhibit 1) and the technical specifications detailed below. All materials and mailto:Charles.R.Tanner@usace.army.mil mailto:James.R.Milner@usace.army.mil mailto:Jason.Almodovar@usace.army.mil workmanship will be manufactured and accomplished according to industry standards and specifications.
1. The Contractor shall prepare two (2) individual camping sites backing up to the river.
The sites shall be excavated and surfaced according to the following requirements:
Parameter Specification Details Site Dimensions 100 feet (length) x 20 feet (width) Main vehicle/RV parking pad area
Amenity Extension 25 feet x 25 feet Located off the back-right corner of each site (facing the rear/river) to house a fire ring and picnic table.
Excavation Depth 10 inches Contractor must excavate the entire footprint of each campsite pad (including the extension) to a uniform depth of 10 inches. Then apply road grade geo-textile fabric before introducing the foundation stone.
Foundation Base Structural Stone Base Install and compact a proper foundational stone base to support RV axle weights.
Finished Surface #9 Size Stone Top the completed stone base with #9 size stone to finish grade no more than 6 inches or less than 2 inches above the top-soil edge.
2. The Contractor shall construct an access drive. The length will be roughly 175 feet, but construction must follow the exact placement designated on the project map (Exhibit 1).
Parameter Specification Details Excavation Depth 10 inches Excavate the road entrance and designated pathways to a minimum depth of 10 inches. Then apply road grade geo-textile fabric before introducing the foundation stone.
Foundation Base Structural Stone Base Prior to surface application, install and compact a foundational stone base in accordance with KYTC specifications, selecting aggregate based on the subgrade soil type.
Where stable soil conditions are present, Dense Graded Aggregate (DGA) is sufficient; however, if the underlying soil is soft, wet, or clay-heavy, No. 2 or No. 3 stone must be used to establish a stable bridging lift. All base material must be placed and compacted in uniform lifts not exceeding 6 inches in loose depth to ensure maximum density and eliminate subgrade deflection.
Finished Surface Dense Grade Aggregate
(DGA)
The final driving surface must be capped with Dense Graded Aggregate (DGA), graded and compacted to an elevation between 2” and 4” above the surrounding soil grade.
This elevated profile ensures positive cross-slope drainage, allowing stormwater runoff to shed freely off the shoulders, preventing standing water, and deterring localized puddling on the driving lane.
Dimensions 175 Linear feet Total length of the drive is 175’ and the total width of the drive is no less than 20 feet or more than 22’,
3. The Contractor is responsible for installing water, electrical, and sewage systems in strict compliance with the project maps (Exhibit 1). The government will supply the RV pedestal boxes. The Contractor is responsible for mounting and wiring them. All other materials are Contractor-furnished.
Water Distribution System Component Requirement Installation Standards Supply Line ¾ inch PEX Line Minimum burial depth of 30 inches. To be tapped into the existing water supply available on site.
Riser Assembly ¾ inch Galvanized Riser Pipe
Rigidly strapped to a 4x4 pressure treated wood post. Finished with a ¾ inch ball valve spigot head.
Contral Valve Ball Valve Shut-Off Installed inline, positioned below the hose spigot.
Winterization Drain Line
Low-Point Drain and Blow-Out Port
Contractor must install two dedicated drain lines at the lowest points of the water supply system.
These drain lines must feature a brass ball valve inside an accessible, traffic-rated valve box surrounded by drainage gravel. The system must be configured to allow gravity draining and/or the connection of compressed air to completely blow out water from all lines.
Electrical System Component Requirement Installation Standards
Main Service
320/400 Amp Meter Base with dual 200 Amp Main Service Disconnect Panels.
Install a 320/400A continuous-duty meter base feeding two separate 200A main breaker disconnect panels. Panel 1 will be fully commissioned to power the current sites.
Panel 2 will be installed and pre-wired as a spare/future expansion panel. All work must comply with NEC and local utility standards.
Feeder Line Two (2) 100 Amp Breakers feeding wire routed inside protective conduit (Schedule 80 PVC above grade and under roadways / Schedule 40 below grade).
Feeders must be sized in accordance with NEC Article 551 (Recreational Vehicles and RV Parks) and Article 550 (Mobile Homes).
Service Location Built at the exact location designated by the Technical Point of Contact (TPOC).
The contractor must coordinate with the TPOC to mark all underground utility line routes prior to excavation.
Trench Depth 24 inches minimum cover (or 36 inches if subject to heavy vehicle traffic).
Conduit must be buried to meet or exceed NEC Table
300.5 minimum cover requirements.
Pedestal Mounting Government-Furnished RV Pedestals
Securely mount the government-furnished pedestal boxes to 6x6 pressure-treated wood posts rated for ground contact, buried to a minimum depth of 36 inches and tamped.
Pedestal Receptacles 125V/20A GFCI, 125V/30A, and 125/250V/50A Outlets.
Each RV pedestal box must be fully wired and configured to support all three receptacles simultaneously in accordance with NEC Article 551 standards.
Sewage and Waste System Component Requirement Installation Standards Primary Infrastructure Total of Two (2) 1,000-gallon Concrete Holding Tanks
Tanks must be structurally rated, properly bedded, and leveled. One tank per site.
Site Connections Full Sewer Hookup Install a full RV sewer inlet at the right-hand rear of each campsite.
All site drain lines must utilize gravity flow (minimum 1/4" per foot slope) to drain directly into the holding tank.
System Cleanouts PVC Cleanouts on Main Lines
Install accessible surface-grade cleanouts near each RV connection, before entering the tanks, at any pipe bend exceeding 45 degrees, and every 100 feet of linear pipe.
Drain Field 600 Linear Feet of Lateral Lines
Excavate and install 600 linear feet of lateral lines within the designated lateral bed field. The distribution system must be perfectly leveled and backfilled with approved aggregate or chamber systems in strict accordance with local environmental/health department septic codes
Code Compliance Local Health & Plumbing Codes
All plumbing, connections, venting, cleanouts, and tank tie-ins must comply with standard plumbing codes to prevent backflow and trap sewer gases.
Exhibit 1 – Project Map
TP-1.1 GENERAL: