Tailwater Volunteer Village Campground Construction
Solicitation number
W912QR26QA071
Issued by

About this file

This document contains federal contract clauses for a construction solicitation administered by the U.S. Army Corps of Engineers at Green River Lake in Campbellsville, Kentucky.

The solicitation includes an organized site visit scheduled for Tuesday, August 4th, 2026 at 10:00 AM Central Time. Offerors and quoters are urged and expected to inspect the work site prior to submission. Participants must meet at Green River Lake, 544 Lake Road, Campbellsville, KY 42718, with TPOC John Houk available at 270-465-4463. No inquiries are permitted during the site visit; all questions must be submitted through the ProjNet Bidder Inquiry site using the Bidder Key provided with solicitation materials. The contract will include clauses addressing differing site conditions and site investigations affecting the work.

Under the work completion requirements, the contractor must commence work within 10 calendar days of receiving the notice to proceed, prosecute the work diligently, and complete all work ready for use within 120 calendar days of the notice to proceed. This completion timeline includes final cleanup of the premises.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Clauses

52.236-27 Site Visit (Construction) (Feb 1995) Alternate I (Feb 1995).

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-

Tuesday August 4th , 2026 at 10:00AM CT

(c) Participants will meet at -

TPOC: John Houk, 270-465-4463 U.S. Army Corps of Engineers Green River Lake 544 Lake Road Campbellsville, KY 42718

No inquiries will be allowed during the site visit. All inquiries must be submitted via the ProjNet Bidder Inquiry site. A Bidder Key is provided with the solicitation information.

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after the notice to proceed. The time stated for completion shall include final cleanup of the premises.

File details come from the government source that posted it. Updated .