tableofcontents.doc
DOC document 45 KB Posted
- Attached to
- TRACK RESURFACING
- Solicitation number
- RFP NAP 260000001809 1
- Issued by
- Huron County, Michigan
About this file
This is a bid package table of contents for the Napoleon Community Schools Series #2 Bond Project, specifically for the construction of a new auxiliary gym in Michigan. The project is organized as Bid Package #1 with a bidding manual dated April 13, 2026. The primary work category is track resurfacing, with both base bid and alternate scope documentation provided. The bid package includes comprehensive bidding requirements encompassing project documentation, advertisement for bids, instructions to bidders, bid forms with familial disclosure statements and Iran Economic Sanctions Act compliance affidavits, sample subcontract agreement forms, insurance requirements, and general and supplementary conditions. Additional sections address health and safety procedures, project management and coordination, construction progress documentation, security procedures requiring background check authorization, quality and regulatory requirements, payment procedures, and closeout submittals. The specifications are organized across 17 divisions covering procurement and contracting requirements, general requirements, existing conditions, concrete, masonry, metals, wood and composites, thermal and moisture protection, openings, finishes, specialties, furnishings, plumbing, HVAC, electrical, electronic safety and security, earthwork, exterior improvements, and utilities.
The bid package incorporates Wightman Technical Specs for multiple sections including the project title page, seals page, request for interpretation and substitution forms, project summary, substitution procedures, construction progress schedules, security procedures, quality and regulatory requirements, code-required special inspections, product requirements, execution and closeout requirements, field engineering, and construction waste management. Geotechnical investigations are included as part of the work scope. A sports complex topographical survey drawing is provided as supporting documentation. The package establishes a preliminary milestone schedule and alternate schedule options, with detailed procedures outlined for contract modifications, administrative requirements, and demonstration and training upon project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00 11 13 advertisementforbid - Napoelon Use.doc | DOC document | |
| Work Category #1 - Track Resurfacing.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Napoleon Community Schools Series #2 Bond Project
Construction of the New Auxiliary Gym
BID PACKAGE #1
Project Bidding Manual 4/13/2026 Bidding Requirements:
00 01 01
Project Title Page (See Wightman Technical Specs) 00 01 07
Seals Page (See Wightman Technical Specs) 00 01 10
Table of Contents (See Wightman Technical Specs) 00 11 13
Advertisement For Bids 00 21 13
Instructions To Bidders 00 21 13A
Request For Information 00 31 13 PRELIMINARY milestone schedule
00 41 00 Bid Form (Includes Familial Disclosure Statement & Affidavit Of Compliance – Iran Economic Sanctions Act) 00 50 00
Sample Subcontract Agreement Forms 00 60 00 Insurance Requirements and Certificates 00 60 01
CSI – Request For Interpretation Form (See Wightman Technical Specs) 00 60 02
CSI – Substitution Request Form (During Bidding) (See Wightman Technical Specs) 00 60 03
CSI – Substitution Request Form (After Bidding) (See Wightman Technical Specs) 00 70 00
General Conditions 00 80 00
Supplementary Conditions 00 90 00
Health, Safety & Emergency Response Procedures 01 10 00
Summary (See Wightman Technical Specs) 01 23 00
ALTERNATE SCHEDULE
01 25 00
Substitution Procedures (See Wightman Technical Specs) 01 26 00
Contract Modification Procedures 01 29 00
Payment Procedures 01 30 00
Administrative Requirements (See Wightman Technical Specs) 01 31 00
Project Management & Coordination 01 32 00
Construction Progress Documentation 01 32 16
Construction Progress Schedule (See Wightman Technical Specs) 01 35 53
Security Procedures (See Wightman Technical Specs) 01 35 53.01 BACKGROUND check authorization form 01 40 00
Quality Requirements (See Wightman Technical Specs) 01 41 00
Regulatory Requirements (See Wightman Technical Specs) 01 42 16
Definitions (See Wightman Technical Specs) 01 45 33
Code-Required Special Inspections and Controls (See Wightman Technical Specs) 01 50 00
Temporary Controls 01 60 00
Product Requirements (See Wightman Technical Specs) 01 70 00
Execution and Closeout Requirements (See Wightman Technical Specs) 01 71 23
Field Engineering (See Wightman Technical Specs) 01 73 00
Execution Requirements 01 74 19
Construction Waste Management and Disposal (See Wightman Technical Specs) 01 78 00
Closeout Submittals (See Wightman Technical Specs) 01 79 00
Demonstration and Training (See Wightman Technical Specs) 02 32 00 Geotechnical investigations Work Category Descriptions:
WC #1 – Track Resurfacing
· Base Bid Scope Doc
· Alternate Scope Doc Specifications:
division 00 – procurement and contracting requirements
Division 01 – general requirements division 02 – existing conditions division 03 – Concrete
Division 04 – Masonry
Division 05 – Metals
Division 06 – Wood, plastics and composites Division 07 – Thermal and moisture protection
Division 08 – openings Division 09 – finishes
Division 10 – specialties
Division 12 – FURNISHINGS Division 22 – plumbing Division 23 – heating, ventilating, and air conditions (HVAC) Division 26 – electrical
Division 28 – electronic safety and security division 31 – earthwork division 32 – exterior improvements division 33 – utilities Drawings:
SPORTS COMPLEX-TOPO SURVEY
File details come from the government source that posted it. Updated .