This document includes a statement of work and market survey for a brick veneer repair project at the Federal Aviation Administration air traffic control tower in Burlington, Vermont. The scope of work involves removing and replacing damaged brick, mortar, sealant and installing new weep holes. Interested vendors must have the capability to perform masonry, waterproofing and related construction services. Responses to the market survey are due by March 20, 2024 and will be used to determine adequate competition for either an unrestricted procurement or a small business set-aside. The statement of work provides specifications for brick, mortar, sealants and other materials, as well as safety, quality and warranty requirements. The work must be completed within 45 days of award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tab 3c BTV ATCT Brick Repair Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Aviation Administration
Statement of Work
Burlington, Vermont (BTV) Air Traffic Control Tower
Brick Veneer Repair Project
BRICK VENEER REPAIR PROJECT
AIR TRAFFIC CONTROL TOWER BURLINGTON, VT
Table of Contents
Statement of Work Page 3
Appendix A Site Pictures Page 6
Attachments
• Drawings o BTV-ATCT-D-G001 o BTV-ATCT-D-C001 o BTV-ATCT-D-C002
• Site As Builts o NE-D-24781-A04 o NE-D-24781-A09 o NE-D-26220-S03
1. PROJECT: Burlington, VT (BTV) Air Traffic Control Tower (ATCT) Brick Veneer Repair Project
2. ADDRESS: 1200 Airport Drive, Burlington, VT, 05401
3. DESCRIPTION: The BTV ATCT facility was built in 1993 and consists of an 80 foot tall air traffic control tower and a single story, 9300 square foot base building and link. The purpose of the brick veneer repair project is to repair defects in the brick veneer exterior of the base building and link due to suspected water infiltration, saturation and freeze/thaw effects. The defects in the brick veneer include efflorescence build up, spalling, cracking, loose/missing brick, deteriorated mortar joints and inconsistent drainage from weepholes. There are no structural cracks or bows in the wall.
4. GENERAL: The Contractor must provide all material, equipment, supplies, transportation and labor to complete the specific scope of work. All work to be priced out in accordance with David-Bacon Wage rates.
5. SCOPE OF WORK:
1. Remove and dispose of any mortar at the mortar joint at the lintel face of each corbel and install new commercial grade sealant at the joint throughout the base building exterior. Ensure open head weeps are installed within the sealant.
2. Install new open head weep holes at the section of existing sealant that was installed by others.
3. Install new open head weepholes every 2’ at the following locations:
a. Top of the corbel, directly above the top brick and at the bottom of the flashing throughout the entire base building and link.
b. Just below the rowlock course/window sill at the bottom of the flashing.
c. Soldier course at the base building sidewalk.
d. Above the windows directly above the first brick at the bottom of the flashing.
4. Install new open cell weep hole mesh at all new weepholes above the soldier course brick.
5. Install new stainless steel weep hole covers at new weepholes at the soldier course brick above the sidewalk.
6. At the south wall at one window, remove and dispose of entire rowlock course. Sawcut ~3/4” and remove section of brick. Install new brick and mortar to achieve proper slope (20%) to match other sills.
7. Remove and dispose of any loose, cracked, spalled or damaged brick and replace with new.
8. Remove any deteriorated mortar and install new.
9. Remove efflorescence build up by applying efflorescence remover. Wash and brush areas of mildew and dirt on brick veneer.
10. Pressure wash all surfaces of brick veneer to remove any dirt buildup. Limit PSI of pressure wash so as to not damage brick.
11. Install a new 2’ wide by 1.5’ deep trench as shown in sheet C001 and C002. Install new landscape fabric along all surface of new trench and fill trench with ¾” crushed stone.
**NOTE: Appendix A Site Pictures shows large bushes and mulch in front of the base building. These have since been removed and replaced with gravel.
6. PROJECT MATERIAL SPECIFICATIONS:
a. Brick: Nominal 3-inch x 4-inch x 8-inch Brick. Type FBS, ASTM C-216, Grade SW (To
Match existing brick color as close as possible).
b. Mortar: Portland Cement Type 1 and hydrated lime mixed to type N strength (matching color, texture and joint type of existing mortar), conforming to ASTM C-270.
c. Brick Sealant: Penetrating, silane water repellant for both vertical and horizontal surfaces. Low VOC. Conproco Shield MX, or approved equal.
d. Sealant: Dow 790, or approved equal, ultra low modulus, one-part, neutral cure silicone sealant. Color must match mortar. ASTM C920, type S, Grade NS, Class 100/50. UL
263. Compression capability of ~100/-50 percent.
e. Backer rod: If required by sealant manufacturer for gap size. Backer rod must be 25% larger than joint width.
f. Bond breaker Tape: Use bond breaker tape where backer rod cannot be installed per manufacturer instruction. Bond breaker tape must be polypropylene 3M Bond Breaker Tape 8891, or approved equal.
g. Efflorescence Remover: EaCoChem Effortless, or approved equal.
h. Open cell weep plugs
i. Stainless steel weep covers
7. SPECIAL INSTRUCTIONS:
a. Conduct work of brick removal and replacement as in clean a manner as possible. Take care not to damage the existing flashing when removing old mortar.
b. Thoroughly clean the contact surface of set masonry with muriatic acid and lightly wet prior to applying new masonry.
8. MATERIALS:
a. Materials furnished by the contractor for this project must be new, unless specified materials can be re-used. All product to be installed to the manufacturer’s instructions.
b. Hazardous Materials. No materials supplied by the contractor for this project must contain asbestos or lead-based materials. All SDS sheets must be provided prior to construction for all required materials.
9. SITE VISIT: A pre bid site visit will be scheduled where all prospective bidders are allowed to attend. Attendance to the pre bid site visit is strongly recommended. Site conditions could affect Contractor’s performance cost that would be captured through observable site conditions during a pre bid site visit.
10. PERFORMANCE PERIOD: Complete all work within 45 calendar days of Contractor’s Notice to Proceed. Based on facility requirements, night work may be necessary. Contractor must base their bid on day work.
11. MEETINGS: Attend two separate meetings at the facility/virtual (CO/COR discretion) after contract award and prior to start of work. Meetings may be on different days and several days or weeks apart. All meetings are mandatory. Meetings include:
a. Preconstruction:
i. Logistics, schedule, deliveries, mobilization, etc.
AIR TRAFFIC CONTROL TOWER BURLINGTON, VT
ii. Contractor personnel
iii. Submittal approval
b. Operational Risk Management/Mitigation
i. Personnel and facility safety requirements
ii. Coordination and communication for outages
12. SECURITY: The FAA ATCT is a secured site. Site access is restricted. Contractor employees must be escorted by a badged FAA employee at all times. Comply with all facility security requirements and inspections.
13. SUBMITTALS: Materials and Equipment. Contractor must provide the following minimum submittals for FAA review and approval:
a. Project Portfolio
b. Construction schedule
c. Brick
d. Mortar
e. Open cell weep material
f. Stainless steel weep hole covers
g. Sealant
h. Brick sealer
i. Efflorescence remover
j. As requested by FAA
14. PROJECT CONDITIONS:
a. Work hours:
i. Operational Spaces. Accomplish all work during hours between 6:00 AM and 5:00 PM (local time), Monday through Friday on mutually agreeable dates. Hours and dates are subject to change due to FAA operational requirements. Work must not impact operational time of Air Traffic operations.
b. Operational Risk Avoidance
i. General. This facility provides services to assist in the control of aircraft movement, operates 24 hours a day, 365 days a year and is vital to the National Airspace System. The building is densely filled with electric and electronic equipment. All work will be performed with the facility maintaining full operation.
ii. Coordination of Work Affecting Operational Systems or Personnel. Coordinate all work that has any or may have any impact on any operational systems or personnel within the facility through the COR. Cease any work that is adversely impacting the operations of the facility or personnel and immediately report impact to the COR; repair or restore any portion of the operational system that has been damaged or suffered diminished performance as a result of the Contractor’s activities.
iii. Avoid actions deemed detrimental or increasing risk to the facility’s mission, occupants, or equipment.
iv. Avoid activities that create objectionable noise, release detectable odors, or generate smoke. Review locations of any intake vents.
AIR TRAFFIC CONTROL TOWER BURLINGTON, VT
v. Communicate any activities that produce noise that may impact occupants inside the base building to the FAA so precautions can be taken.
vi. Avoid activities that impede traffic flow to maximum extent feasible, which may delay or impede access of personnel to the facility. Coordinate any impacts in advance.
c. Safety
i. Perform all work safely and in accordance with the following requirements.
ii. Comply with FAA Electrical Standards, FAA Safety Standards, National Electrical
Code (NFPA 70), National Fire Code, OSHA, manufacturer’s recommendations, local, state, and federal regulations, other authorities having jurisdiction, and local facility requirements. FAA Standards are available on request.
iii. Workers must use Personal Protective Equipment (PPE) as required by code, regulation, standard, or manufacturer’s recommendation.
iv. Operators of and heavy equipment or machinery must be properly certified.
v. Contractor to secure the working area at all times to protect personnel and their belongings from debris, machinery or any working hazard as they access or leave the facility. The work area must be properly lit when needed and cleaned after construction activities to avoid any damage. The construction site must be maintained in a clean and orderly fashion at all times.
d. Coordination and Approval
i. Coordinate with and obtain approval from the COR for work schedule, hours, and activities on a daily basis. Coordinate high risk tasks with COR prior to work start.
High risk tasks include, but not limited to noise generating activities.
ii. Drawings. Drawings are included for reference only. The work to be accomplished is described in the statement of work. The drawings are intended to provide a general layout of the work and brick detail. The contractor to maintain redline drawings throughout construction to be provided to the COR at project completion.
15. UTILITIES: Water and electricity is available at the facility at the back of the base building.
16. STORAGE: A staging area can be setup for materials and tools. Review location with FAA.
17. TEMPORARY SANITARY FACILITIES: Provide temporary sanitary facilities to be used by workers on site. Facilities must remain on site for the duration of the contract. Final location will be coordinated with the COR and approved by the COR.
18. CLEANUP: Remove all debris, rubbish, scrap, dirt, and protective coverings from the work areas upon completion of the work shift each day. Site conditions throughout construction period will not impact site operations. The affected work areas must be thoroughly cleaned to their original condition at the end of each work shift. Site must be returned to original condition prior to project completion.
19. QUALITY ASSURANCE AND WORKMANSHIP: All work must be accomplished in a neat, workmanlike manner by skilled workmen regularly engaged in their respective trade resulting in an installation that is absolutely satisfactory in both function and appearance as determined by the
COR.
20. WARRANTY:
a. All material, equipment and workmanship provided in the project must be warranted for a period of one (1) year, from date of acceptance by the COR unless noted otherwise elsewhere in contract documents.
21. INSPECTION: Submit a written request for inspection for Substantial Completion, also referred to as the Contractor Acceptance Inspection (CAI). On receipt of request, COR will either schedule the inspection within fourteen (14) days or notify Contractor of unfulfilled requirements. COR will prepare the Certificate of Substantial Completion after the inspection or will notify Contractor of items, either on Contractor's list or additional items identified by COR, that must be completed or corrected before certificate will be issued. COR will also provide a punch list that will form the basis of requirements for Final Completion.
22. PROJECT CLOSEOUT: Contractor should request final inspection prior to contract completion date. Before requesting final inspection for determining date of Final Completion, complete the following:
a. Submit a Final Application for Payment.
b. Submit a certified copy of COR’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by the COR. The certified copy of the list must state that each item has been completed or otherwise resolved for acceptance.
c. Submit specific warranties, final certifications and similar documents.
d. Perform final cleanup.
Appendix A: Site Pictures
| BTV ATCT Brick Repair SOW 100% |
| Appendix A Site Pictures |
| As Builts |
| btv24781a04 |
| btv24781a09 |
| btv26220s03 |