Supplemental_Instructions.pdf
PDF 104 KB Posted
- Attached to
- Bayfront Park Seawall Reconstruction
- Solicitation number
- 26-14JS
- Issued by
- Sarasota County, Siesta Key CDP, Florida
About this file
This Supplemental Instructions document pertains to the City of Sarasota's Bayfront Park Seawall Reconstruction project (ITB #26-14JS), establishing project-specific conditions beyond the city's standard terms and scope of work. The project involves replacement of approximately 1,500 linear feet of bulkhead at Sarasota Bayfront Park, with work including demolition of existing structures, installation of fiber-reinforced polymer piles, reinforced concrete bulkhead cap, living seawall modules, Baywalk sidewalk restoration, potable water and electrical systems upgrades, and landscaping improvements. Responses are due by February 19, 2026, with a critical project completion deadline of June 30, 2026, to meet FDEP grant compliance requirements. Bidders must have examined 100% construction drawings prepared by Cummins Cederberg, Inc. (Marine Structural Works) and Chen Moore and Associates (Civil, Electrical, and Landscape Architecture Works), both dated October 28, 2025, and must visit the project site to understand local conditions affecting cost and performance. All contractors must demonstrate capability to coordinate with Suntex Marinas and the City to maintain ongoing operations of four boat clubs throughout construction while managing material staging and complying with specified construction hour limitations.
Mobilization and demobilization fees are capped at 10 percent of total construction costs. Longshoreman's Insurance is mandatory for this project. Bidders must submit a detailed construction schedule addressing constraints outlined in the separate Construction Scope of Work document and must have thoroughly reviewed all applicable construction drawings, general notes, and project addenda. The project is partially funded through a $3,588,000 FDEP Resilient Florida Grant, supplemented by City match funding of 42.40%, resulting in a total project cost of approximately $6,229,181.73. Federal compliance requirements include Davis-Bacon Act prevailing wage standards and SLFRF compliance provisions, with mandatory obligation by December 31, 2024, and expenditure by December 31, 2026. All contractors must carry Workers' Compensation insurance, Commercial General Liability insurance with minimum one million dollar combined single limit per occurrence, and Automobile Liability insurance with comparable limits. Performance and payment bonds equal to 100 percent of the total contract amount are required, along with bid bonds for projects exceeding $200,000. Local preference does not apply due to grant funding requirements.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Supplemental Instructions:
These are conditions that are in relation to this bid only and have not been included in the CITY’s standard Terms and Conditions or the Scope of Work.
1. Longshoreman’s Insurance is required for this project.
2. The following notes are related to Bid Form, which is imbedded into the solicitation software.
a. Mobilization/Demobilization fees shall not be greater than 10% of construction cost.
b. Bid quantities and Scope of Work based on 100% Construction Drawings for Marine
Structural Works prepared by Cummins Cederberg, Inc. dated October 28, 2025 and 100% Construction Drawings for Civil, Electrical, and Landscape Architecture Works prepared by Chen Moore and Associates dated October 28, 2025. (Please note if there are any questions regarding this bid, contact the Purchasing Division of the City of Sarasota.)
c. Bidder to coordinate the bulkhead project with Suntex Marinas and City to maintain operations throughout construction of Freedom Boat Club, LeBarge Tropical Cruises, Suntex Boat Club & Rentals, and Carefree Learner. Bidder to coordinate any proposed interruptions with the City and Suntex Marinas.
d. Bidder is responsible for all aspects of material staging throughout the entirety of construction.
e. Bidder is to present a construction schedule given the constraints outlined in the Construction Scope of Work (separate enclosed document).
f. Bidder has examined and carefully studied, in detail, the Construction Drawings, Project General Notes on Sheets CM-1.0 through CM-1.2, CN-1.0, EP-01, L-204, L- 301 through L-305, L-401, and L-404 and other related data identified in the Construction Drawings, and any subsequent addenda to this bid request.
g. Bidder has visited the Project site and become familiar with and is satisfied as to the general, local, site, and structure conditions that may affect cost, progress, and performance of the Work.
h. The Plans are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
i. Bidder has read the Construction Scope of Work (separate enclosed document).