Submittal Register - Perimeter Bridge McChord.xlsx
XLSX spreadsheet 52 KB Posted
- Attached to
- Repairs to McChord Bridge - Perimeter Road
- Solicitation number
- W912DW24B0YY2
About this file
This document contains a submittal register and related federal contract opportunity. The submittal register outlines 244 pre-construction, shop drawing, product data, design data, test report, certificate, operation and maintenance, and closeout submittal line items required for the "Repairs to McChord Bridge - Perimeter Road" project. The project scope involves repairs to the perimeter road bridge at Joint Base Lewis-McChord in Washington. Submittals include plans, schedules, safety documentation, drawings, manuals, inspection reports, material specifications, test results, and as-built records.
The associated federal contract opportunity is a 100% small business set-aside solicitation from the Department of the Army Corps of Engineers seeking offers for the "Repair Perimeter Rd. Bridge (J84018)" project. The estimated value is between $5-10 million. The NAICS code is 237310 and small business size standard is $45 million. The solicitation closes in June 2024. The opportunity is restricted to eligible 8(a) small businesses only.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UFGS4288
| TITLE: | Perimeter Bridge Construction - Draft Submittal Register | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | ||||||||||||||||||
| LOCATION: | ||||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 30 00 | 1 | Preconstruction Submittals | View Location Map | 1.3 | |||||||||||||||
| 2 | 01 30 00 | 1 | Preconstruction Submittals | Progress and Completion Pictures | 1.4 | |||||||||||||||
| 3 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Preliminary Project Schedule | 3.4.1 | G | ||||||||||||||
| 4 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Initial Project Schedule | 3.4.2 | G | ||||||||||||||
| 5 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Periodic Schedule Update | 3.6.2 | G | ||||||||||||||
| 6 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Project Scheduler Qualifications | 1.3 | |||||||||||||||
| 7 | 01 33 00 | 1 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||||||||||||||
| 8 | 01 35 26 | 1 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.7 | G | ||||||||||||||
| 9 | 01 35 26 | 1 | Preconstruction Submittals | Activity Hazard Analysis (AHA) | 1.8 | G | ||||||||||||||
| 10 | 01 35 26 | 1 | Preconstruction Submittals | Utility Coordination and Protection Plan | 1.17 | G | ||||||||||||||
| 11 | 01 35 26 | 1 | Preconstruction Submittals | Crane Critical Lift Plan | 1.7.2 | G | ||||||||||||||
| 12 | 01 35 26 | 6 | Test Reports | Notifications and Reports | 1.12 | |||||||||||||||
| 13 | 01 35 26 | 6 | Test Reports | LHE Inspection Reports | 1.12.3 | |||||||||||||||
| 14 | 01 35 26 | 6 | Test Reports | Accident Reports | 1.12.2 | G | ||||||||||||||
| 15 | 01 35 26 | 6 | Test Reports | Monthly Exposure Reports | 1.4 | |||||||||||||||
| 16 | 01 35 26 | 7 | Certificates | Confined Space Entry Permit | 1.9.1 | |||||||||||||||
| 17 | 01 35 26 | 7 | Certificates | Hot Work Permit | 1.9.1 | |||||||||||||||
| 18 | 01 45 00.00 10 | 1 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 3.2 | G | ||||||||||||||
| 19 | 01 45 00.00 10 | 1 | Preconstruction Submittals | Verification Statement | 3.9.2 | |||||||||||||||
| 20 | 01 45 35 | 1 | Preconstruction Submittals | SIOR Letter of Acceptance | 3.1.1 | G | ||||||||||||||
| 21 | 01 45 35 | 1 | Preconstruction Submittals | Project Manual | 3.1.1 | G | ||||||||||||||
| 22 | 01 45 35 | 1 | Preconstruction Submittals | Project Manual | 3.1.1 | G | ||||||||||||||
| 23 | 01 45 35 | 1 | Preconstruction Submittals | Written Practices | 3.1.1 | |||||||||||||||
| 24 | 01 45 35 | 1 | Preconstruction Submittals | Written Practices | 3.1.3 | |||||||||||||||
| 25 | 01 45 35 | 1 | Preconstruction Submittals | NDT Procedures and Equipment Calibration Records | 3.1.1 | |||||||||||||||
| 26 | 01 45 35 | 1 | Preconstruction Submittals | NDT Procedures and Equipment Calibration Records | 3.1.3 | |||||||||||||||
| 27 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.1 | |||||||||||||||
| 28 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.3 | |||||||||||||||
| 29 | 01 45 35 | 6 | Test Reports | Daily Reports | 3.1.3 | |||||||||||||||
| 30 | 01 45 35 | 6 | Test Reports | Biweekly Reports | 3.1.1 | |||||||||||||||
| 31 | 01 45 35 | 6 | Test Reports | Biweekly Reports | 3.1.2 | |||||||||||||||
| 32 | 01 45 35 | 7 | Certificates | AISC Certified Steel Fabricator | 2.1 | |||||||||||||||
| 33 | 01 45 35 | 7 | Certificates | Steel Truss Plant | 2.1 | |||||||||||||||
| 34 | 01 45 35 | 7 | Certificates | Certified Plant | 2.1 | |||||||||||||||
| 35 | 01 45 35 | 7 | Certificates | Certificate of Compliance | 2.1 | |||||||||||||||
| 36 | 01 45 35 | 7 | Certificates | Special Inspector of Record | 1.5.10 | G | ||||||||||||||
| 37 | 01 45 35 | 7 | Certificates | Special Inspector | 1.5 | G | ||||||||||||||
| 38 | 01 45 35 | 7 | Certificates | Qualification Records | 3.1.1 | |||||||||||||||
| 39 | 01 45 35 | 7 | Certificates | Qualification Records | 3.1.3 | |||||||||||||||
| 40 | 01 45 35 | 11 | Closeout Submittals | Interim Final Report | 3.1.1 | G | ||||||||||||||
| 41 | 01 45 35 | 11 | Closeout Submittals | Interim Final Report | 3.1.3 | G | ||||||||||||||
| 42 | 01 45 35 | 11 | Closeout Submittals | Comprehensive Final Report | 3.1.1 | G | ||||||||||||||
| 43 | 01 45 35 | 11 | Closeout Submittals | Comprehensive Final Report | 3.1.3 | G | ||||||||||||||
| 44 | 01 50 00 | 1 | Preconstruction Submittals | Construction Site Plan | 1.3 | G | ||||||||||||||
| 45 | 01 50 00 | 1 | Preconstruction Submittals | Traffic Control Plan | 3.4.1 | G | ||||||||||||||
| 46 | 01 56 00 | 1 | Preconstruction Submittals | Care and Diversion Work Plan | 1.5 | G | ||||||||||||||
| 47 | 01 56 00 | 1 | Preconstruction Submittals | In-Water Safety Plan | 1.7 | |||||||||||||||
| 48 | 01 56 00 | 2 | Shop Drawings | Shop Drawings | 1.8 | G | ||||||||||||||
| 49 | 01 56 00 | 5 | Design Data | Design Calculations | 1.9 | G | ||||||||||||||
| 50 | 01 57 19 | 1 | Preconstruction Submittals | Preconstruction Survey | 1.6.1 | |||||||||||||||
| 51 | 01 57 19 | 1 | Preconstruction Submittals | Regulatory Notifications | 1.6.2 | G | ||||||||||||||
| 52 | 01 57 19 | 1 | Preconstruction Submittals | Environmental Protection Plan | 1.7 | G | ||||||||||||||
| 53 | 01 57 19 | 1 | Preconstruction Submittals | Stormwater Pollution Prevention Plan | 3.2.1.1 | G | ||||||||||||||
| 54 | 01 57 19 | 1 | Preconstruction Submittals | Stormwater Notice of Intent | 3.2.1.2 | G | ||||||||||||||
| 55 | 01 57 19 | 1 | Preconstruction Submittals | Employee Training Records | 1.6.5 | G | ||||||||||||||
| 56 | 01 57 19 | 1 | Preconstruction Submittals | Environmental Manager Qualifications | 1.6.4 | G | ||||||||||||||
| 57 | 01 57 19 | 1 | Preconstruction Submittals | Waste Determination Documentation | 3.7.1 | |||||||||||||||
| 58 | 01 57 19 | 1 | Preconstruction Submittals | Hazardous Waste/Debris Management | 3.7.3.1 | |||||||||||||||
| 59 | 01 57 19 | 6 | Test Reports | Inspection Reports | 3.2.1.3 | |||||||||||||||
| 60 | 01 57 19 | 6 | Test Reports | Disposal Documentation for Hazardous and Regulated Waste | 3.7.3.6 | |||||||||||||||
| 61 | 01 57 19 | 6 | Test Reports | Contractor Hazardous Material Inventory Log | 3.8.1 | |||||||||||||||
| 62 | 01 57 19 | 6 | Test Reports | PFAS Test Results | 3.21 | |||||||||||||||
| 63 | 01 57 19 | 7 | Certificates | Employee Training Records | 1.6.5 | G | ||||||||||||||
| 64 | 01 57 19 | 7 | Certificates | ECATTS Certificate Of Completion | 1.4.1.2 | G | ||||||||||||||
| 65 | 01 57 19 | 7 | Certificates | Certificate of Competency | 1.6.5.1 | |||||||||||||||
| 66 | 01 57 19 | 7 | Certificates | Erosion and Sediment Control Inspector | 1.6.5 | |||||||||||||||
| 67 | 01 57 19 | 11 | Closeout Submittals | Stormwater Pollution Prevention Plan Compliance Notebook | 3.2.1.4 | G | ||||||||||||||
| 68 | 01 57 19 | 11 | Closeout Submittals | Stormwater Notice of Termination | 3.2.1.5 | G | ||||||||||||||
| 69 | 01 57 19 | 11 | Closeout Submittals | Assembled Employee Training Records | 1.6.5 | G | ||||||||||||||
| 70 | 01 57 19 | 11 | Closeout Submittals | Regulatory Notifications | 1.6.2 | G | ||||||||||||||
| 71 | 01 57 19 | 11 | Closeout Submittals | As-Built Topographic Survey | 3.2.1.5 | |||||||||||||||
| 72 | 01 74 19 | 1 | Preconstruction Submittals | Construction Waste Management Plan | 1.7 | G | ||||||||||||||
| 73 | 01 74 19 | 6 | Test Reports | Quarterly Reports | 1.9.2 | |||||||||||||||
| 74 | 01 74 19 | 6 | Test Reports | Annual Report | 1.9.3 | |||||||||||||||
| 75 | 01 74 19 | 11 | Closeout Submittals | Final Construction Waste Diversion Report | 1.1 | |||||||||||||||
| 76 | 01 78 00 | 3 | Product Data | Warranty Management Plan | 1.10.1 | |||||||||||||||
| 77 | 01 78 00 | 3 | Product Data | Warranty Tags | 1.10.5 | |||||||||||||||
| 78 | 01 78 00 | 3 | Product Data | Spare Parts Data | 1.7 | |||||||||||||||
| 79 | 01 78 00 | 8 | Manufacturer's Instructions | Instructions | 1.10.1 | |||||||||||||||
| 80 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.7 | G | ||||||||||||||
| 81 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 3.1 | G | ||||||||||||||
| 82 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.3 | G | ||||||||||||||
| 83 | 01 78 00 | 11 | Closeout Submittals | As-Built Record of Equipment and Materials | 1.10.1 | |||||||||||||||
| 84 | 01 78 00 | 11 | Closeout Submittals | As-Built Record of Equipment and Materials | 3.6 | |||||||||||||||
| 85 | 01 78 00 | 11 | Closeout Submittals | Final Approved Shop Drawings | 3.4 | G | ||||||||||||||
| 86 | 01 78 00 | 11 | Closeout Submittals | Bridge Inspection and Load Rating Analysis | 2.2 | G | ||||||||||||||
| 87 | 01 78 00 | 11 | Closeout Submittals | Interim DD FORM 1354 | 3.9.1 | G | ||||||||||||||
| 88 | 01 78 00 | 11 | Closeout Submittals | Final DD FORM 1354 | 3.9.2 | G | ||||||||||||||
| 89 | 01 78 00 | 11 | Closeout Submittals | Checklist for DD FORM 1354 | 3.9.2 | G | ||||||||||||||
| 90 | 01 78 00 | 11 | Closeout Submittals | Construction Contract Specifications | 3.5 | G | ||||||||||||||
| 91 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.4 | G | ||||||||||||||
| 92 | 02 41 00 | 1 | Preconstruction Submittals | Demolition Plan | 1.2.2 | G | ||||||||||||||
| 93 | 02 41 00 | 1 | Preconstruction Submittals | Deconstruction Plan | 1.2.2 | G | ||||||||||||||
| 94 | 02 41 00 | 7 | Certificates | Notification | 1.6 | G | ||||||||||||||
| 95 | 03 01 00 | 1 | Preconstruction Submittals | Qualifications | 1.5.3 | G | ||||||||||||||
| 96 | 03 01 00 | 1 | Preconstruction Submittals | Work Plan | 1.5.5 | G | ||||||||||||||
| 97 | 03 01 00 | 1 | Preconstruction Submittals | Work Plan | 1.6.1 | G | ||||||||||||||
| 98 | 03 01 00 | 1 | Preconstruction Submittals | Quality Control Plan | 1.5.2 | G | ||||||||||||||
| 99 | 03 01 00 | 3 | Product Data | Conventional Concrete | 2.5 | |||||||||||||||
| 100 | 03 01 00 | 3 | Product Data | Polymers | 2.6 | |||||||||||||||
| 101 | 03 01 00 | 3 | Product Data | Miscellaneous Materials And Equipment | 2.7 | |||||||||||||||
| 102 | 03 01 00 | 5 | Design Data | Formwork And Shoring | 3.1.3 | G | ||||||||||||||
| 103 | 03 01 00 | 5 | Design Data | Repair Procedures | 1.5.1 | G | ||||||||||||||
| 104 | 03 01 00 | 5 | Design Data | Mixture Proportioning | 2.8 | G | ||||||||||||||
| 105 | 03 01 00 | 6 | Test Reports | Mixture Proportioning | 2.8 | |||||||||||||||
| 106 | 03 01 00 | 6 | Test Reports | Quality Control | 3.1.5 | |||||||||||||||
| 107 | 03 01 00 | 6 | Test Reports | Quality Control | 3.2.3 | |||||||||||||||
| 108 | 03 01 00 | 6 | Test Reports | Quality Control | 3.3.3 | |||||||||||||||
| 109 | 03 01 00 | 7 | Certificates | Qualifications | 1.5.3 | |||||||||||||||
| 110 | 03 01 00 | 7 | Certificates | Reinforcement And Reinforcement Supports | 2.4 | |||||||||||||||
| 111 | 03 45 33 | 2 | Shop Drawings | Drawings of Precast Members | 2.1.1.2 | G | ||||||||||||||
| 112 | 03 45 33 | 2 | Shop Drawings | Drawings of Precast Prestressed Concrete Members | 2.1.1.2 | G | ||||||||||||||
| 113 | 03 45 33 | 5 | Design Data | Design Calculations | 2.1.1.2 | G | ||||||||||||||
| 114 | 03 45 33 | 5 | Design Data | Concrete Mix Design | 1.4.3 | G | ||||||||||||||
| 115 | 03 45 33 | 6 | Test Reports | Concrete Mix Design | 1.4.3 | G | ||||||||||||||
| 116 | 03 45 33 | 7 | Certificates | Construction Records | 3.12 | G | ||||||||||||||
| 117 | 03 45 33 | 7 | Certificates | Erector's Post Audit Declaration | 1.4.1.3 | |||||||||||||||
| 118 | 03 45 33 | 11 | Closeout Submittals | Batch Ticket | 1.4.4 | |||||||||||||||
| 119 | 03 45 33 | 11 | Closeout Submittals | Recycled Content for Silica Fume | 2.2.1 | |||||||||||||||
| 120 | 03 45 33 | 11 | Closeout Submittals | Recycled Content for Fly Ash and Pozzolan | 2.2.1 | |||||||||||||||
| 121 | 03 45 33 | 11 | Closeout Submittals | Recycled Content for Ground Iron Blast-Furnace Slag | 2.2.1 | |||||||||||||||
| 122 | 03 70 00 | 3 | Product Data | Curing and Protection | 3.2 | G | ||||||||||||||
| 123 | 05 05 20.00 27 | 1 | Preconstruction Submittals | Installer Qualifications | 1.5.1.1 | G | ||||||||||||||
| 124 | 05 05 20.00 27 | 1 | Preconstruction Submittals | Post-Installed Anchor Special Inspector Qualifications | 1.5.1.2 | G | ||||||||||||||
| 125 | 05 05 20.00 27 | 3 | Product Data | Mechanical Anchors in Concrete | 2.1.1.3 | G | ||||||||||||||
| 126 | 05 05 20.00 27 | 3 | Product Data | Adhesive Anchor System in Concrete | 2.1.1.4 | G | ||||||||||||||
| 127 | 05 05 20.00 27 | 3 | Product Data | Non-Shrink, Non-Metallic Grout | 3.1.3 | G | ||||||||||||||
| 128 | 05 05 20.00 27 | 6 | Test Reports | Post-Installed Anchor Special Inspections Report | 3.3.4 | G | ||||||||||||||
| 129 | 05 05 20.00 27 | 7 | Certificates | Post-Installed Anchor Certification | 2.1.1.1 | G | ||||||||||||||
| 130 | 05 05 20.00 27 | 8 | Manufacturer's Instructions | Manufacturer's Printed Installation Instructions | 2.1.1.2 | G | ||||||||||||||
| 131 | 05 05 20.00 27 | 8 | Manufacturer's Instructions | Non-Shrink, Non-Metallic Grout | 3.1.3 | G | ||||||||||||||
| 132 | 05 05 20.00 27 | 8 | Manufacturer's Instructions | Manufacturer's Material Safety Data Sheets | 1.5 | |||||||||||||||
| 133 | 05 05 23.16 | 3 | Product Data | Welding Procedure Qualifications | 1.3 | G | ||||||||||||||
| 134 | 05 05 23.16 | 3 | Product Data | Welder, Welding Operator, and Tacker Qualification | 1.3.4 | |||||||||||||||
| 135 | 05 05 23.16 | 3 | Product Data | Previous Qualifications | 1.3.2 | |||||||||||||||
| 136 | 05 05 23.16 | 3 | Product Data | Pre-Qualified Procedures | 1.3.3 | G | ||||||||||||||
| 137 | 05 05 23.16 | 3 | Product Data | Welding Electrodes and Rods | 2.2 | |||||||||||||||
| 138 | 05 05 23.16 | 6 | Test Reports | Nondestructive Testing | 3.3 | |||||||||||||||
| 139 | 05 05 23.16 | 7 | Certificates | Certified Welding Procedure Specifications (WPS) | 1.3.1 | |||||||||||||||
| 140 | 05 05 23.16 | 7 | Certificates | Certified Brazing Procedure Specifications (BPS) | 1.3.1 | |||||||||||||||
| 141 | 05 05 23.16 | 7 | Certificates | Certified Procedure Qualification Records (PQR) | 1.3.1 | |||||||||||||||
| 142 | 05 05 23.16 | 7 | Certificates | Certified Welder Performance Qualifications (WPQ) | 1.3.1 | |||||||||||||||
| 143 | 05 05 23.16 | 7 | Certificates | Certified Brazer Performance Qualifications (BPQ) | 1.3.1 | |||||||||||||||
| 144 | 05 05 23.16 | 7 | Certificates | Certified Welding Inspector | 1.3.5 | |||||||||||||||
| 145 | 05 05 23.16 | 7 | Certificates | Nondestructive Testing Personnel | 1.3.5 | |||||||||||||||
| 146 | 05 12 00 | 1 | Preconstruction Submittals | Erection and Erection Bracing Drawings | 1.5.1.1 | G | ||||||||||||||
| 147 | 05 12 00 | 2 | Shop Drawings | Fabrication Drawings | 1.5.2 | G | ||||||||||||||
| 148 | 05 12 00 | 3 | Product Data | Shop Primer | 2.6.2 | |||||||||||||||
| 149 | 05 12 00 | 3 | Product Data | Welding Electrodes and Rods | 2.4.1 | |||||||||||||||
| 150 | 05 12 00 | 3 | Product Data | Non-Shrink Grout | 2.4.2 | |||||||||||||||
| 151 | 05 12 00 | 3 | Product Data | Recycled Content for Structural Steel | 2.2.1 | S | ||||||||||||||
| 152 | 05 12 00 | 3 | Product Data | Recycled Content for Structural Steel Tubing | 2.2.2 | S | ||||||||||||||
| 153 | 05 12 00 | 3 | Product Data | Recycled Content for Steel Pipe | 2.2.3 | S | ||||||||||||||
| 154 | 05 12 00 | 5 | Design Data | Design Calculations for Steel Connections | 1.5.3 | G | ||||||||||||||
| 155 | 05 12 00 | 5 | Design Data | Shoring and Temporary Bracing | 1.5.2 | G | ||||||||||||||
| 156 | 05 12 00 | 6 | Test Reports | Class B Coating | 2.6.2 | |||||||||||||||
| 157 | 05 12 00 | 6 | Test Reports | Bolts, Nuts, and Washers | 2.3 | |||||||||||||||
| 158 | 05 12 00 | 6 | Test Reports | Bolt Testing Reports | 3.7.2.1 | |||||||||||||||
| 159 | 05 12 00 | 6 | Test Reports | Embrittlement Test Reports | 3.7.3 | |||||||||||||||
| 160 | 05 12 00 | 7 | Certificates | Steel | 2.2 | |||||||||||||||
| 161 | 05 12 00 | 7 | Certificates | Bolts, Nuts, and Washers | 2.3 | |||||||||||||||
| 162 | 05 12 00 | 7 | Certificates | Galvanizing | 2.5 | |||||||||||||||
| 163 | 05 12 00 | 7 | Certificates | AISC Structural Steel Fabricator Quality Certification | 1.3 | |||||||||||||||
| 164 | 05 12 00 | 7 | Certificates | AISC Structural Steel Erector Quality Certification | 1.3 | |||||||||||||||
| 165 | 05 12 00 | 7 | Certificates | Welding Procedures and Qualifications | 1.5.4.1 | |||||||||||||||
| 166 | 05 12 00 | 7 | Certificates | Welding Electrodes and Rods | 2.4.1 | |||||||||||||||
| 167 | 05 12 00 | 7 | Certificates | Certified Welding Inspector | 3.7.1.1 | |||||||||||||||
| 168 | 05 12 00 | 7 | Certificates | Welding Procedure Specifications (WPS) | 3.4 | |||||||||||||||
| 169 | 05 50 14 | 2 | Shop Drawings | Detail Drawings | 1.3.1 | G | ||||||||||||||
| 170 | 05 50 14 | 2 | Shop Drawings | Welding Procedures | 2.1.2.1.1 | G | ||||||||||||||
| 171 | 05 50 14 | 2 | Shop Drawings | Welding Repair Plan | 2.2.3 | |||||||||||||||
| 172 | 05 50 14 | 3 | Product Data | Filler Metal | 2.1.2.1.3.1 | |||||||||||||||
| 173 | 05 50 14 | 6 | Test Reports | Tests, Inspections, and Verifications | 2.2 | |||||||||||||||
| 174 | 05 50 14 | 7 | Certificates | Welding Qualifications | 1.3.2 | |||||||||||||||
| 175 | 05 50 14 | 7 | Certificates | Application Qualification for Steel Studs | 2.1.2.3.1 | G | ||||||||||||||
| 176 | 05 50 14 | 7 | Certificates | Welding of Aluminum | 2.1.2.4 | |||||||||||||||
| 177 | 05 50 14 | 7 | Certificates | Weld Inspection Log | 2.2.2.1 | |||||||||||||||
| 178 | 05 50 14 | 7 | Certificates | Certified Welding Inspector | 2.2.2.1 | |||||||||||||||
| 179 | 05 50 14 | 7 | Certificates | Nondestructive Testing Personnel | 2.2.2.2.1 | |||||||||||||||
| 180 | 05 50 16 | 1 | Preconstruction Submittals | Erection and Erection Bracing Drawings | 1.7.1 | G | ||||||||||||||
| 181 | 05 50 16 | 1 | Preconstruction Submittals | Welding Quality Assurance Plan | 1.7.5 | G | ||||||||||||||
| 182 | 05 50 16 | 1 | Preconstruction Submittals | Welding Procedure Qualifications | 1.7.5 | G | ||||||||||||||
| 183 | 05 50 16 | 2 | Shop Drawings | Detail Drawings | 1.7.1 | G | ||||||||||||||
| 184 | 05 50 16 | 2 | Shop Drawings | Bridge Fabrication Drawings | 1.7.2 | G | ||||||||||||||
| 185 | 05 50 16 | 2 | Shop Drawings | Stair Fabrication Drawings | 1.7.1 | G | ||||||||||||||
| 186 | 05 50 16 | 2 | Shop Drawings | Welding Repair Plan | 1.7.5 | |||||||||||||||
| 187 | 05 50 16 | 2 | Shop Drawings | Installation Plan | 1.7.4 | G | ||||||||||||||
| 188 | 05 50 16 | 2 | Shop Drawings | Bridge As-Built Drawings | 1.7.7 | G | ||||||||||||||
| 189 | 05 50 16 | 2 | Shop Drawings | Bridge As-Built Drawings | 1.7.7 | G | ||||||||||||||
| 190 | 05 50 16 | 6 | Test Reports | Tests, Inspections, Verifications, Product Data, and Qualifications | 1.7.6 | |||||||||||||||
| 191 | 05 50 16 | 6 | Test Reports | Bolts, Nuts, and Washers | 2.4 | |||||||||||||||
| 192 | 05 50 16 | 7 | Certificates | Steel | 2.3 | |||||||||||||||
| 193 | 05 50 16 | 7 | Certificates | Bolts, Nuts, and Washers | 2.4 | |||||||||||||||
| 194 | 05 50 16 | 7 | Certificates | Welding Procedures and Qualifications | 1.7.5 | |||||||||||||||
| 195 | 05 52 00 | 2 | Shop Drawings | Fabrication Drawings | 1.2.1 | G | ||||||||||||||
| 196 | 05 52 00 | 2 | Shop Drawings | Iron and Steel Hardware | 3.2 | G | ||||||||||||||
| 197 | 05 52 00 | 2 | Shop Drawings | Steel Shapes, Plates, Bars and Strips | 3.2 | G | ||||||||||||||
| 198 | 05 52 00 | 3 | Product Data | Structural-Steel Plates, Shapes, and Bars | 2.2.1 | G | ||||||||||||||
| 199 | 05 52 00 | 3 | Product Data | Structural-Steel Tubing | 2.2.2 | G | ||||||||||||||
| 200 | 05 52 00 | 3 | Product Data | Cold-Finished Steel Bars | 2.2.4 | G | ||||||||||||||
| 201 | 05 52 00 | 3 | Product Data | Hot-Rolled Carbon Steel Bars | 2.2.3 | G | ||||||||||||||
| 202 | 05 52 00 | 3 | Product Data | Cold-Drawn Steel Tubing | 2.2.5 | G | ||||||||||||||
| 203 | 05 52 00 | 3 | Product Data | Concrete Inserts | 2.2.7 | G | ||||||||||||||
| 204 | 05 52 00 | 3 | Product Data | Protective Coating | 2.1.3 | G | ||||||||||||||
| 205 | 05 52 00 | 3 | Product Data | Steel Railings and Handrails | 2.2.9 | G | ||||||||||||||
| 206 | 05 52 00 | 3 | Product Data | Aluminum Railings and Handrails | 2.2.10 | G | ||||||||||||||
| 207 | 05 52 00 | 3 | Product Data | Anchorage and Fastening Systems | 1.2.1 | G | ||||||||||||||
| 208 | 05 52 00 | 7 | Certificates | Welding Procedures | 1.4.1 | G | ||||||||||||||
| 209 | 05 52 00 | 7 | Certificates | Welder Qualification | 1.4.2 | G | ||||||||||||||
| 210 | 05 52 00 | 8 | Manufacturer's Instructions | Installation Instructions | 3.2 | |||||||||||||||
| 211 | 10 14 53 | 3 | Product Data | Traffic Sign Posts | 2.1 | |||||||||||||||
| 212 | 10 14 53 | 3 | Product Data | Traffic Sign Retroreflective Sheeting | 2.4 | |||||||||||||||
| 213 | 10 14 53 | 4 | Samples | Flexible Posts | 2.6.2 | |||||||||||||||
| 214 | 25 05 11.01 | 1 | Preconstruction Submittals | Device Account Lock Exception Request | 3.3.2 | G | ||||||||||||||
| 215 | 25 05 11.01 | 1 | Preconstruction Submittals | Qualifications | 1.7.1 | G | ||||||||||||||
| 216 | 25 05 11.01 | 1 | Preconstruction Submittals | Contractor Computer Cybersecurity Compliance Statements | 1.10.1.6 | G | ||||||||||||||
| 217 | 25 05 11.01 | 1 | Preconstruction Submittals | Contractor Temporary Network Cybersecurity Compliance Statements | 1.10.5 | G | ||||||||||||||
| 218 | 25 05 11.01 | 1 | Preconstruction Submittals | Proposed STIG and SRG Applicability Report | 1.8.1 | G | ||||||||||||||
| 219 | 25 05 11.01 | 2 | Shop Drawings | Network Communication Report | 1.8.2 | G | ||||||||||||||
| 220 | 25 05 11.01 | 2 | Shop Drawings | Cybersecurity Riser Diagram | 1.8.5 | G | ||||||||||||||
| 221 | 25 05 11.01 | 3 | Product Data | Control System Cybersecurity Documentation | 1.8.7 | G | ||||||||||||||
| 222 | 25 05 11.01 | 6 | Test Reports | Control System Cybersecurity Testing Procedures | 3.14.1 | G | ||||||||||||||
| 223 | 25 05 11.01 | 6 | Test Reports | Control System Cybersecurity Testing Report | 3.14.3 | G | ||||||||||||||
| 224 | 25 05 11.01 | 7 | Certificates | Software Licenses | 1.9 | G | ||||||||||||||
| 225 | 25 05 11.01 | 11 | Closeout Submittals | Confidential Password Report | 3.4.4.4 | G | ||||||||||||||
| 226 | 25 05 11.01 | 11 | Closeout Submittals | Enclosure Keys | 3.3.5 | G | ||||||||||||||
| 227 | 25 05 11.01 | 11 | Closeout Submittals | Software and Configuration Backups | 1.8.4 | G | ||||||||||||||
| 228 | 25 05 11.01 | 11 | Closeout Submittals | System Maintenance Tool Software | 3.9 | G | ||||||||||||||
| 229 | 25 05 11.01 | 11 | Closeout Submittals | Control System Scanning Tools | 3.11.2 | G | ||||||||||||||
| 230 | 25 05 11.01 | 11 | Closeout Submittals | STIG, SRG and Vendor Guide Compliance Result Report | 1.8.6 | G | ||||||||||||||
| 231 | 25 05 11.01 | 11 | Closeout Submittals | Control System Inventory Report | 1.8.3 | G | ||||||||||||||
| 232 | 26 60 14 | 3 | Product Data | Catalog Cut Sheets and Shop Drawings | 1.6 | G | ||||||||||||||
| 233 | 31 00 00 | 1 | Preconstruction Submittals | Shoring | 3.3 | G | ||||||||||||||
| 234 | 31 00 00 | 1 | Preconstruction Submittals | Dewatering Work Plan | 1.6.3 | G | ||||||||||||||
| 235 | 31 00 00 | 3 | Product Data | Utilization of Excavated Materials | 3.7 | G | ||||||||||||||
| 236 | 31 00 00 | 3 | Product Data | Rock Excavation | 1.6.1.2 | |||||||||||||||
| 237 | 31 00 00 | 3 | Product Data | Opening of any Excavation or Borrow Pit | 3.2 | |||||||||||||||
| 238 | 31 00 00 | 3 | Product Data | Shoulder Construction | 3.13 | |||||||||||||||
| 239 | 31 00 00 | 6 | Test Reports | Testing | 3.15 | |||||||||||||||
| 240 | 31 00 00 | 7 | Certificates | Testing | 3.15 | |||||||||||||||
| 241 | 31 11 00 | 3 | Product Data | Tree Removal Plan | 1.3 | G | ||||||||||||||
| 242 | 31 43 13.13 | 3 | Product Data | Drilling Equipment | 3.1.2 | |||||||||||||||
| 243 | 31 43 13.13 | 3 | Product Data | Grouting Equipment | 3.1.3 | |||||||||||||||
| 244 | 31 43 13.13 | 3 | Product Data | Grout Plant | 3.1.3 | G | ||||||||||||||
| 245 | 31 62 23.13 | 2 | Shop Drawings | Installation Plan | 3.1 | |||||||||||||||
| 246 | 31 62 23.13 | 3 | Product Data | Driving Pile Casings | 3.1.1 | |||||||||||||||
| 247 | 31 62 23.13 | 3 | Product Data | Equipment | 1.3.2 | |||||||||||||||
| 248 | 31 62 23.13 | 6 | Test Reports | Test Piles | 3.2.1 | |||||||||||||||
| 249 | 31 63 16 | 1 | Preconstruction Submittals | Installation Procedures | 1.7.2 | G | ||||||||||||||
| 250 | 31 63 16 | 1 | Preconstruction Submittals | Load Test Procedures | 1.7.1 | G | ||||||||||||||
| 251 | 31 63 16 | 1 | Preconstruction Submittals | Concrete Mix Design | 1.7.3 | G | ||||||||||||||
| 252 | 31 63 16 | 1 | Preconstruction Submittals | Field Quality Control Procedures | 1.7.1 | G | ||||||||||||||
| 253 | 31 63 16 | 3 | Product Data | Concrete Pump | 1.4.2 | |||||||||||||||
| 254 | 31 63 16 | 3 | Product Data | Materials | 2.1 | |||||||||||||||
| 255 | 31 63 16 | 11 | Closeout Submittals | Pile Records | 3.6 | |||||||||||||||
| 256 | 32 05 33 | 1 | Preconstruction Submittals | Integrated Pest Management Plan | 2.4 | G | ||||||||||||||
| 257 | 32 05 33 | 3 | Product Data | Fertilizer | 2.1 | G | ||||||||||||||
| 258 | 32 05 33 | 3 | Product Data | Mulch | 2.3 | G | ||||||||||||||
| 259 | 32 05 33 | 3 | Product Data | Organic Mulch Materials | 2.3.1 | |||||||||||||||
| 260 | 32 05 33 | 7 | Certificates | Maintenance Inspection Report | 3.5.1 | |||||||||||||||
| 261 | 32 05 33 | 7 | Certificates | Plant Quantities | 3.5.2 | G | ||||||||||||||
| 262 | 32 05 33 | 11 | Closeout Submittals | Tree Staking and Guying Removal | 3.5.3 | |||||||||||||||
| 263 | 32 11 23 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||||||||||||||
| 264 | 32 11 23 | 6 | Test Reports | Initial Tests | 2.3.1 | G | ||||||||||||||
| 265 | 32 11 23 | 6 | Test Reports | In-Place Tests | 3.13.1 | G | ||||||||||||||
| 266 | 32 12 13 | 6 | Test Reports | Sampling and Testing | 3.7 | |||||||||||||||
| 267 | 32 12 16.16 | 2 | Shop Drawings | Placement Plan | 2.1 | G | ||||||||||||||
| 268 | 32 12 16.16 | 3 | Product Data | Diamond Grinding Plan | 2.1.6 | G | ||||||||||||||
| 269 | 32 12 16.16 | 3 | Product Data | Mix Design | 2.4 | G | ||||||||||||||
| 270 | 32 12 16.16 | 3 | Product Data | Contractor Quality Control | 3.1 | G | ||||||||||||||
| 271 | 32 12 16.16 | 4 | Samples | Aggregates | 2.2 | |||||||||||||||
| 272 | 32 12 16.16 | 4 | Samples | Asphalt Cement Binder | 2.3 | |||||||||||||||
| 273 | 32 12 16.16 | 6 | Test Reports | Aggregates | 2.2 | G | ||||||||||||||
| 274 | 32 12 16.16 | 6 | Test Reports | QC Monitoring | 3.1.3.9 | |||||||||||||||
| 275 | 32 12 16.16 | 7 | Certificates | Asphalt Cement Binder | 2.3 | G | ||||||||||||||
| 276 | 32 12 16.16 | 7 | Certificates | Laboratory Accreditation and Validation | 1.3.11 | |||||||||||||||
| 277 | 32 15 00 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||||||||||||||
| 278 | 32 15 00 | 6 | Test Reports | Initial Tests | 2.3.1 | G | ||||||||||||||
| 279 | 32 15 00 | 6 | Test Reports | In-Place Tests | 3.11.1 | G | ||||||||||||||
| 280 | 32 16 19 | 3 | Product Data | Concrete | 2.1 | |||||||||||||||
| 281 | 32 16 19 | 3 | Product Data | Biodegradable Form Release Agent | 2.6.5 | |||||||||||||||
| 282 | 32 16 19 | 3 | Product Data | Biodegradable Form Release Agent | 3.2 | |||||||||||||||
| 283 | 32 16 19 | 6 | Test Reports | Field Quality Control | 3.8 | |||||||||||||||
| 284 | 32 17 23 | 3 | Product Data | Surface Preparation Equipment List | 2.1.1.1 | G | ||||||||||||||
| 285 | 32 17 23 | 3 | Product Data | Application Equipment List | 2.1.2 | G | ||||||||||||||
| 286 | 32 17 23 | 3 | Product Data | Exterior Surface Preparation | 3.2 | |||||||||||||||
| 287 | 32 17 23 | 3 | Product Data | Safety Data Sheets | 1.3.1 | G | ||||||||||||||
| 288 | 32 17 23 | 6 | Test Reports | Test Reports | 3.4.1 | |||||||||||||||
| 289 | 32 17 23 | 7 | Certificates | Qualifications | 1.3.2 | G | ||||||||||||||
| 290 | 32 17 23 | 7 | Certificates | Volatile Organic Compound | 1.3.1 | G | ||||||||||||||
| 291 | 32 31 13.53 | 2 | Shop Drawings | Fence Installation Drawings | 3.2.1 | G | ||||||||||||||
| 292 | 32 31 13.53 | 3 | Product Data | Fabric | 2.1.1.1 | |||||||||||||||
| 293 | 32 31 13.53 | 3 | Product Data | Posts | 2.1.2 | |||||||||||||||
| 294 | 32 31 13.53 | 3 | Product Data | Post Caps | 2.1.2.2 | |||||||||||||||
| 295 | 32 31 13.53 | 3 | Product Data | Chain Link Braces | 2.1.3 | |||||||||||||||
| 296 | 32 31 13.53 | 3 | Product Data | Sleeves | 3.2.3.2 | |||||||||||||||
| 297 | 32 31 13.53 | 3 | Product Data | Tension Wire | 2.1.2.2 | |||||||||||||||
| 298 | 32 31 13.53 | 3 | Product Data | Barbed Wire | 2.2.1.2 | |||||||||||||||
| 299 | 32 31 13.53 | 3 | Product Data | Barbed Wire Supporting Arms | 2.1.2.2 | |||||||||||||||
| 300 | 32 31 13.53 | 3 | Product Data | Latches | 2.1.4.3 | |||||||||||||||
| 301 | 32 31 13.53 | 3 | Product Data | Hinges | 2.1.4.3 | |||||||||||||||
| 302 | 32 31 13.53 | 3 | Product Data | Stops | 2.1.4.3 | |||||||||||||||
| 303 | 32 31 13.53 | 3 | Product Data | Keepers | 2.1.4.3 | |||||||||||||||
| 304 | 32 31 13.53 | 3 | Product Data | Rollers | 2.1.4.3 | |||||||||||||||
| 305 | 32 31 13.53 | 3 | Product Data | Padlocks | 2.1.5 | |||||||||||||||
| 306 | 32 31 13.53 | 3 | Product Data | Wire Ties | 2.2.1.1 | |||||||||||||||
| 307 | 32 31 13.53 | 3 | Product Data | Fence Fabric Reinforcement | 2.3 | |||||||||||||||
| 308 | 32 31 13.53 | 7 | Certificates | Chain Link Fence | 2.1.2.1 | |||||||||||||||
| 309 | 32 31 13.53 | 7 | Certificates | Fabric | 2.1.1.1 | |||||||||||||||
| 310 | 32 31 13.53 | 7 | Certificates | Barbed Wire | 2.2.1.2 | |||||||||||||||
| 311 | 32 31 13.53 | 7 | Certificates | Gate Hardware and Accessories | 3.2.1 | |||||||||||||||
| 312 | 32 31 13.53 | 7 | Certificates | Concrete | 2.2.2 | |||||||||||||||
| 313 | 32 31 13.53 | 7 | Certificates | Gate Operator | 2.1.6 | |||||||||||||||
| 314 | 32 31 13.53 | 10 | Operation and Maintenance Data | Gate Operator | 2.1.6 | |||||||||||||||
| 315 | 32 31 13.53 | 10 | Operation and Maintenance Data | Operating and maintenance instructions | 3.2.7 | |||||||||||||||
| 316 | 32 32 23.13 | 2 | Shop Drawings | Shop Drawings | 2.1.3 | G | ||||||||||||||
| 317 | 32 32 23.13 | 3 | Product Data | Segmental Concrete Units | 2.2.1 | |||||||||||||||
| 318 | 32 32 23.13 | 5 | Design Data | Survey And Grade Results | 3.3.1 | G | ||||||||||||||
| 319 | 32 32 23.13 | 6 | Test Reports | Soil Testing | 3.4.1 | G | ||||||||||||||
| 320 | 32 84 24 | 2 | Shop Drawings | Irrigation Sprinkler System | 1.3 | |||||||||||||||
| 321 | 32 84 24 | 3 | Product Data | Piping Materials | 2.1 | |||||||||||||||
| 322 | 32 84 24 | 3 | Product Data | Valves | 2.3 | |||||||||||||||
| 323 | 32 84 24 | 3 | Product Data | Heads | 2.2 | |||||||||||||||
| 324 | 32 84 24 | 3 | Product Data | Backflow Preventers | 2.3.6 | |||||||||||||||
| 325 | 32 84 24 | 3 | Product Data | Automatic Controller | 2.5 | |||||||||||||||
| 326 | 32 84 24 | 3 | Product Data | Controller Enclosure | 2.5.2 | |||||||||||||||
| 327 | 32 84 24 | 3 | Product Data | Solvent Cement | 2.1.4 | |||||||||||||||
| 328 | 32 84 24 | 3 | Product Data | Control Wiring | 2.6.1 | |||||||||||||||
| 329 | 32 84 24 | 3 | Product Data | Drip Irrigation | 2.1.7 | |||||||||||||||
| 330 | 32 84 24 | 3 | Product Data | Water Hammer Arresters | 2.4.4.2 | |||||||||||||||
| 331 | 32 84 24 | 3 | Product Data | Water Meter | 2.4.2 | |||||||||||||||
| 332 | 32 84 24 | 3 | Product Data | Rain Shut-Off Device | 2.4.5.1 | |||||||||||||||
| 333 | 32 84 24 | 3 | Product Data | Freeze Shut-Off Device | 2.4.5.2 | |||||||||||||||
| 334 | 32 84 24 | 3 | Product Data | Soil Moisture Sensor | 2.4.5.3 | |||||||||||||||
| 335 | 32 84 24 | 3 | Product Data | Tapping Tee | 2.4.1 | |||||||||||||||
| 336 | 32 84 24 | 3 | Product Data | Valve Boxes and Lids | 3.1.7.3 | |||||||||||||||
| 337 | 32 84 24 | 3 | Product Data | Drip Head Accessories | 2.4.3 | |||||||||||||||
| 338 | 32 84 24 | 6 | Test Reports | Tests | 1.7.1 | |||||||||||||||
| 339 | 32 84 24 | 6 | Test Reports | Backflow Preventers | 2.3.6 | |||||||||||||||
| 340 | 32 84 24 | 6 | Test Reports | Pressure Test | 3.2.1 | |||||||||||||||
| 341 | 32 84 24 | 6 | Test Reports | Operation Test | 3.2.2 | |||||||||||||||
| 342 | 32 84 24 | 7 | Certificates | Backflow Preventers | 2.3.6 | |||||||||||||||
| 343 | 32 84 24 | 8 | Manufacturer's Instructions | Automatic Controller | 2.5 | |||||||||||||||
| 344 | 32 84 24 | 8 | Manufacturer's Instructions | Heads | 2.2 | |||||||||||||||
| 345 | 32 84 24 | 8 | Manufacturer's Instructions | Piping Materials | 2.1 | |||||||||||||||
| 346 | 32 84 24 | 8 | Manufacturer's Instructions | Backflow Preventers | 2.3.6 | |||||||||||||||
| 347 | 32 84 24 | 8 | Manufacturer's Instructions | Valves | 2.3 | |||||||||||||||
| 348 | 32 84 24 | 8 | Manufacturer's Instructions | Solvent Cement | 2.1.4 | |||||||||||||||
| 349 | 32 84 24 | 8 | Manufacturer's Instructions | Control Wiring | 2.6.1 | |||||||||||||||
| 350 | 32 84 24 | 8 | Manufacturer's Instructions | Drip Irrigation | 2.1.7 | |||||||||||||||
| 351 | 32 84 24 | 8 | Manufacturer's Instructions | Water Hammer Arresters | 2.4.4.2 | |||||||||||||||
| 352 | 32 84 24 | 8 | Manufacturer's Instructions | Water Meter | 2.4.2 | |||||||||||||||
| 353 | 32 84 24 | 8 | Manufacturer's Instructions | Rain Shut-Off Device | 2.4.5.1 | |||||||||||||||
| 354 | 32 84 24 | 8 | Manufacturer's Instructions | Freeze Shut-Off Device | 2.4.5.2 | |||||||||||||||
| 355 | 32 84 24 | 8 | Manufacturer's Instructions | Soil Moisture Sensor | 2.4.5.3 | |||||||||||||||
| 356 | 32 84 24 | 10 | Operation and Maintenance Data | Piping Materials | 2.1 | G | ||||||||||||||
| 357 | 32 84 24 | 10 | Operation and Maintenance Data | Heads | 2.2 | G | ||||||||||||||
| 358 | 32 84 24 | 10 | Operation and Maintenance Data | Backflow Preventers | 2.3.6 | G | ||||||||||||||
| 359 | 32 84 24 | 10 | Operation and Maintenance Data | Valves | 2.3 | G | ||||||||||||||
| 360 | 32 84 24 | 10 | Operation and Maintenance Data | Automatic Controller | 2.5 | G | ||||||||||||||
| 361 | 32 84 24 | 10 | Operation and Maintenance Data | Drip Irrigation | 2.1.7 | G | ||||||||||||||
| 362 | 32 84 24 | 10 | Operation and Maintenance Data | Water Hammer Arresters | 2.4.4.2 | G | ||||||||||||||
| 363 | 32 84 24 | 10 | Operation and Maintenance Data | Water Meter | 2.4.2 | G | ||||||||||||||
| 364 | 32 84 24 | 10 | Operation and Maintenance Data | Rain Shut-Off Device | 2.4.5.1 | G | ||||||||||||||
| 365 | 32 84 24 | 10 | Operation and Maintenance Data | Freeze Shut-Off Device | 2.4.5.2 | G | ||||||||||||||
| 366 | 32 84 24 | 10 | Operation and Maintenance Data | Soil Moisture Sensor | 2.4.5.3 | G | ||||||||||||||
| 367 | 32 84 24 | 11 | Closeout Submittals | Controller Charts | 3.2.3 | |||||||||||||||
| 368 | 32 92 19 | 3 | Product Data | Hydraulic Mulch | 2.5.1 | G | ||||||||||||||
| 369 | 32 92 19 | 3 | Product Data | Fertilizer | 2.4 | |||||||||||||||
| 370 | 32 92 19 | 6 | Test Reports | Topsoil Composition Tests | 2.2.3 | |||||||||||||||
| 371 | 32 92 19 | 7 | Certificates | Seed | 2.1 | |||||||||||||||
| 372 | 32 92 19 | 8 | Manufacturer's Instructions | Erosion Control Materials | 2.7 | |||||||||||||||
| 373 | 32 93 00 | 1 | Preconstruction Submittals | State Landscape Contractor's License | 1.4.3 | |||||||||||||||
| 374 | 32 93 00 | 1 | Preconstruction Submittals | Time Restrictions and Planting Conditions | 1.6 | |||||||||||||||
| 375 | 32 93 00 | 3 | Product Data | Peat | 2.3.5 | |||||||||||||||
| 376 | 32 93 00 | 3 | Product Data | Compost | 2.3.8 | |||||||||||||||
| 377 | 32 93 00 | 3 | Product Data | Organic Mulch Materials | 2.7.1 | |||||||||||||||
| 378 | 32 93 00 | 3 | Product Data | Gypsum | 2.3.9 | |||||||||||||||
| 379 | 32 93 00 | 3 | Product Data | Mulch | 2.7 | G | ||||||||||||||
| 380 | 32 93 00 | 3 | Product Data | Ground Stakes | 2.8.1.1 | |||||||||||||||
| 381 | 32 93 00 | 3 | Product Data | Recycled Plastic Edging | 2.9.1 | |||||||||||||||
| 382 | 32 93 00 | 3 | Product Data | Fertilizer | 2.5 | |||||||||||||||
| 383 | 32 93 00 | 3 | Product Data | Weed Control Fabric | 2.6 | G | ||||||||||||||
| 384 | 32 93 00 | 3 | Product Data | Root Control Barrier | 2.12 | G | ||||||||||||||
| 385 | 32 93 00 | 3 | Product Data | Staking Material | 2.8.1 | |||||||||||||||
| 386 | 32 93 00 | 3 | Product Data | Antidesiccants | 2.1 | |||||||||||||||
| 387 | 32 93 00 | 3 | Product Data | Erosion Control Materials | 2.11 | |||||||||||||||
| 388 | 32 93 00 | 3 | Product Data | Photographs | 1.4.4 | G | ||||||||||||||
| 389 | 32 93 00 | 4 | Samples | Mulch | 2.7 | G | ||||||||||||||
| 390 | 32 93 00 | 6 | Test Reports | Topsoil Composition Tests | 2.2.4 | |||||||||||||||
| 391 | 32 93 00 | 6 | Test Reports | Percolation Test | 1.4.5 | |||||||||||||||
| 392 | 32 93 00 | 10 | Operation and Maintenance Data | Plastic Identification | 1.8 | |||||||||||||||
| 393 | 33 40 00 | 7 | Certificates | Determination of Density | 3.7.1.3 | |||||||||||||||
| 394 | 33 40 00 | 11 | Closeout Submittals | Post-Installation Inspection Report | 3.7.2.1.3 | G | ||||||||||||||
| 395 | 33 71 02 | 2 | Shop Drawings | Aluminum Conductors | 1.5.1 | G | ||||||||||||||
| 396 | 33 71 02 | 2 | Shop Drawings | Precast Underground Structures | 1.5.1 | G | ||||||||||||||
| 397 | 33 71 02 | 2 | Shop Drawings | Raceway Design on Utility Bridge | 1.5.1 | |||||||||||||||
| 398 | 33 71 02 | 3 | Product Data | Live End Caps | 2.6 | G | ||||||||||||||
| 399 | 33 71 02 | 3 | Product Data | Precast Concrete Structures | 2.10.1.1 | G | ||||||||||||||
| 400 | 33 71 02 | 3 | Product Data | Sealing Material | 2.10.1.4 | |||||||||||||||
| 401 | 33 71 02 | 3 | Product Data | Pulling-In Irons | 3.4.2 | |||||||||||||||
| 402 | 33 71 02 | 3 | Product Data | Manhole Frames and Covers | 2.10.2 | G | ||||||||||||||
| 403 | 33 71 02 | 3 | Product Data | Handhole Frames and Covers | 2.10.3 | G | ||||||||||||||
| 404 | 33 71 02 | 3 | Product Data | Frames and Covers for Airfield Facilities | 2.10.4 | G | ||||||||||||||
| 405 | 33 71 02 | 3 | Product Data | Ductile Iron Frames and Covers for Airfield Facilities | 2.10.5 | G | ||||||||||||||
| 406 | 33 71 02 | 3 | Product Data | Cable Supports | 2.11 | G | ||||||||||||||
| 407 | 33 71 02 | 6 | Test Reports | Field Acceptance Checks and Tests | 3.17.1 | G | ||||||||||||||
| 408 | 33 71 02 | 6 | Test Reports | Arc-proofing Test | 3.17.2 | G | ||||||||||||||
| 409 | 33 71 02 | 6 | Test Reports | Cable Installation Plan and Procedure | 3.3 | G | ||||||||||||||
| 410 | 33 71 02 | 7 | Certificates | Cable splicer/terminator | 1.5.2 | G | ||||||||||||||
| 411 | 33 71 02 | 7 | Certificates | Cable Installer Qualifications | 1.5.3 | G | ||||||||||||||
| 412 | 33 71 02 | 7 | Certificates | Certificate of Conformance | 1.5.4 | G | ||||||||||||||
| 413 | 33 82 00 | 2 | Shop Drawings | Telecommunications Outside Plant | 1.6.1.1 | G | ||||||||||||||
| 414 | 33 82 00 | 3 | Product Data | Wire and cable | 2.6 | G | ||||||||||||||
| 415 | 33 82 00 | 3 | Product Data | Cable splices, and connectors | 2.3 | G | ||||||||||||||
| 416 | 33 82 00 | 3 | Product Data | Closures | 2.2 | G | ||||||||||||||
| 417 | 33 82 00 | 6 | Test Reports | Pre-installation tests | 3.3.1 | G | ||||||||||||||
| 418 | 33 82 00 | 6 | Test Reports | Acceptance tests | 3.3.2 | G | ||||||||||||||
| 419 | 33 82 00 | 6 | Test Reports | Outside Plant Test Plan | 1.6.3 | G | ||||||||||||||
| 420 | 33 82 00 | 7 | Certificates | Telecommunications Contractor | 1.6.2.1 | G | ||||||||||||||
| 421 | 33 82 00 | 7 | Certificates | Key Personnel | 1.6.2.2 | G | ||||||||||||||
| 422 | 33 82 00 | 7 | Certificates | Manufacturer's Qualifications | 1.6.2.3 | G | ||||||||||||||
| 423 | 33 82 00 | 8 | Manufacturer's Instructions | Cable tensions | 3.1.5.1 | G | ||||||||||||||
| 424 | 33 82 00 | 8 | Manufacturer's Instructions | Fiber Optic Splices | 3.1.6.2 | G | ||||||||||||||
| 425 | 33 82 00 | 9 | Manufacturer's Field Reports | Factory Reel Test Data | 2.10.1 | G | ||||||||||||||
| 426 | 33 82 00 | 10 | Operation and Maintenance Data | Telecommunications outside plant (OSP) | 1.6.1.1 | G | ||||||||||||||
| 427 | 33 82 00 | 11 | Closeout Submittals | Record Documentation | 1.8.1 | G | ||||||||||||||
| 428 | 34 71 13.16 | 3 | Product Data | FHWA Acceptance Letter | 2.1.3 | |||||||||||||||
| 429 | 34 71 13.16 | 3 | Product Data | FHWA Acceptance Letter | 2.5 | |||||||||||||||
| 430 | 34 71 13.16 | 8 | Manufacturer's Instructions | End Anchorage | 3.4 | |||||||||||||||
| 431 | 35 20 16.55 | 2 | Shop Drawings | Detail Drawings | 2.3.1 | G | ||||||||||||||
| 432 | 35 20 16.55 | 3 | Product Data | Materials | 2.1 | G | ||||||||||||||
| 433 | 35 20 16.55 | 3 | Product Data | Materials | 2.1 | G | ||||||||||||||
| 434 | 35 20 16.55 | 3 | Product Data | Welding | 2.3.2.1 | G | ||||||||||||||
| 435 | 35 20 16.55 | 6 | Test Reports | Tests, Inspections, and Verifications | 2.4 | |||||||||||||||
| 436 | 35 20 16.55 | 6 | Test Reports | Acceptance Trial Operation and Test | 3.2 | |||||||||||||||
| 437 | 35 31 19.20 | 2 | Shop Drawings | Block Installation | 3.3 | G | ||||||||||||||
| 438 | 35 31 19.20 | 2 | Shop Drawings | Geotextile Installation | 3.2 | G | ||||||||||||||
| 439 | 35 31 19.20 | 2 | Shop Drawings | Anchor and Cable Installation | 3.4 | G | ||||||||||||||
| 440 | 35 31 19.20 | 3 | Product Data | Articulating Concrete Block | 2.1 | G | ||||||||||||||
| 441 | 35 31 19.20 | 3 | Product Data | Geotextile | 2.2 | G | ||||||||||||||
| 442 | 35 31 19.20 | 3 | Product Data | Anchors | 2.3 | G | ||||||||||||||
| 443 | 35 31 19.20 | 4 | Samples | Articulating Concrete Block | 2.1 | |||||||||||||||
| 444 | 35 31 19.20 | 6 | Test Reports | Flume Test | 2.1.2.1 |
File details come from the government source that posted it. Updated .